Resolved
Resolved – That scheme 2.28 Bracknell: A3095 Corridor full financial approval in the sum of £2,000,000 in 2019/20 and £3,518,800 in 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 of the report.
Berkshire Local Transport Body approved this item on Thursday 19 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That scheme 2.28 Bracknell: A3095 Corridor full financial approval in the sum of £2,000,000 in 2019/20 and £3,518,800 in 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 of the report.
1. To consider giving financial approval to scheme 2.28 Bracknell: A3095 Corridor.
2. This project delivers significant improvements to one of the key highway corridors in the Thames Valley Berkshire. The project will significantly help in terms of accommodating movements and reducing congestion between the M4 (J8/9/10) and M3 (J4) and between Maidenhead, Reading, Wokingham, Bracknell, and Camberley/Blackwater Valley and beyond. This work will also assist in unlocking housing delivery at TRL and Broadmoor that will provide 1,415 new houses and enhance urban connectivity.
3. You are recommended to give scheme 2.28 Bracknell: A3095 Corridor full financial approval in the sum of £2,000,000 in 2019/20 and £3,518,800 in 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 below.
Other Implications
Financial
4. Scheme 2.28 Bracknell: A3095 Corridor is a named scheme in the Thames Valley Berkshire Growth Deal 3i announced on 2 February 2017ii
5. This report recommends that Bracknell Forest Council be authorised to draw down the capital sum £5,518,800 from the Local Transport Body funding for this scheme.
6. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Item 11: BLTB 19 July 2018 Financial Approval 2.28 Bracknell A3095 Corridor Risk Management
7. The risk management arrangements already put in place by the Local Transport Body are as follows: The Assurance Frameworkiii has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes White Young Green (WYG) have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
8. The scheme promoter is a local authority and they have to act within the law. Slough Borough Council will provide legal support for the BLTB, should any questions arise.
Supporting Information
9. The scheme will be carried out for Bracknell Forest Council.
10. The full details of the scheme are available from the Bracknell Forest websiteiv. A summary of the key points is given below:
Task Timescale Procurement Via the Council’s Term Contractor Contractor appointed As above Construction November 2019 Open to public November 2021
Activity Funder Cost (approx) Scheme development Bracknell Forest Council Major scheme funding Berkshire Local Transport Body £5.518m Section 106 agreements Developers etc £2.500m Total £8.018m
11. The table below sets out the details of this scheme’s compliance with steps1-5 of paragraph 14 of Assurance Frameworkv.
Assurance Framework 2.28 Bracknell A3095 Corridor Check list The scheme was originally developed by Bracknell Forest Council in response to the growth pressures along this corridor, and in particular to developments at the former TRL site and Broadmoor.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2.28 Bracknell A3095Appendix 1 | 231 KB | Download |
PDF |
Financial Approval 2.28 Bracknell: A3095 CorridorReport | 136 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.