Resolved – That scheme 2.37 Bracknell: A322/A329 Corridor Improvements be given full financial approval for an additional sum of £450,000 in 2021/22 for the Birch Hill Junction Upgrade on the terms of the funding agreement set out at paragraph 11 step 5 of the report. This brought the total funding for the project to £850,000.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To consider giving financial approval for additional funding to scheme 2.37 Bracknell: A322 A329 Corridor Improvements for Birch Hill Junction Upgrade.
2. This project delivers upgrades to signalling equipment at the Birch Hill Junction, situated along the A322 and A329 corridor.
3. The scheme represents a relatively small-scale investment in the replacement of obsolete, and failing, signalling technology at the junction, to ensure greater resilience to the strategically important A322/A329 corridor, as well as provide day- to-day operational benefits.
4. This proposes an increment to an already approved Local Growth Fund (LGF) Bracknell project, scheme 2.37: Bracknell A322 A329 Corridor Improvements. The project will significantly help in terms of accommodating movements and reducing congestion between the M4 and M3 and between Reading, Wokingham, Bracknell, Bagshot and beyond, as well as improving North-South links between the M3 and M4.
Recommendation
5. You are recommended to give scheme 2.37 Bracknell: A322/A329 Corridor Improvements, full financial approval for an additional sum of £450,000 in 2021/22 for the Birch Hill Junction Upgrade on the terms of the funding agreement set out at paragraph 11 step 5 below. This brings the total funding for this project to £850,000.
Other Implications
Financial
6. A re-prioritisation exercise was undertaken in advance of previously allocated Getting Building Fund (GBF) monies returned to the “pot” for re-allocation. At the March 2021 BLTB meeting an additional £450,000 of GBF was allocated to Scheme 2.37 Bracknell: A322/A329 Corridor Improvement for the Birch Hill Junction Upgrade.
Item 7: Financial Approval 2.37 Bracknell A322/ A329 Corridor Improvements: Birch Hill Junction Upgrade 7. This report recommends that Bracknell Forest Council be authorised to draw down the capital sum £450,000 from the Getting Building Fund for this scheme.
8. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Risk management
9. The risk management arrangements already put in place by the Local Transport Body are as follows: The Assurance Framework1 has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
10. The scheme promoter is a local authority and they have to act within the law. Slough Borough Council will provide legal support for the BLTB, should any questions arise.
Supporting Information
11. The scheme will be carried out for Bracknell Forest Council.
12. The full details of the scheme are available from the Bracknell Forest website2. A summary of the key points is given below:
Task Timescale Procurement Via the Council’s Term Contractor Contractor appointed As above Construction January 2022 Open to public March 2022
Activity Funder Cost Scheme development (original) Bracknell Forest Council £ 117,658 Major scheme funding (original) Berkshire Local Transport Body £400,000
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.