It was agreed that the solicitors advice on State Aid be circulated to all members of BLTB. Any substantive concerns should be raised with the LEP and if necessary an additional meeting could be convened if those issues could not be resolved. The recommendation to grant “The Deck” programme entry status was agreed. Resolved – (a) That the prioritisation scores of the sixteen bids received as set out in Table 1 of the report and the creation of a new pipeline of schemes be approved. (b) The programme entry status be given to Bracknell “The Deck” town centre regeneration project within the Local Growth Fund Programme.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To present the prioritised list of sixteen bids received in response to the July 2020 call for bids.
2. To recommend a pipeline of future schemes that can be mobilised quickly should any additional LEP funding become available.
3. To give programme entry status to Bracknell Town Centre - “The Deck”, a town centre regeneration project.
Recommendation
You are recommended to:
4. Approve the prioritisation scores of the sixteen bids received as set out in Table 1 and creation of a new pipeline.
5. Give programme entry status to Bracknell: “The Deck” town centre regeneration project within the Local Growth Fund programme.
Other Implications
Financial
6. The risks associated with large scale infrastructure investments are well known, and the BLTB has established risk management arrangements for the Local Growth Fund transport capital programme (£135.9m over six years), referred to as the BLTB Assurance Framework.
7. As part of the Local Growth Fund oversight a new BLTB Assurance Framework (Third Revision) was approved by the BLTB in July 2019, item 11.
8. Compliance with the Assurance Framework and the updated prioritisation methodology is specifically designed to address the risks inherent with planning and managing a major capital programme of investment. The objectives are to identify, prioritise and support individual capital schemes which will:
9. Support economic development in general and the LEP’s strategy in particular
a) Represent good or better value for money
b) Be delivered on time and to budget
c) Follow appropriate procurement procedures.
10. Promoters of infrastructure projects seeking funding will need to follow the Assurance Framework and updated prioritisation methodology for any additional funding. This means that
Item 6 BLTB 12 November 2020 Call for Bids schemes to establish a new pipeline of projects the pipeline of schemes will be prioritised having met the eligibility criteria, according to the evaluation process, moving to Programme Entry Status acceptance, followed by submission and independent assessment of a WebTAG compliant Full Business Case before being considered for financial approval.
11. It is a requirement of government that all LGF monies must be transferred to delivery partners by March 2021. In order to do so schemes must have made a “significant” start by this date.
12. Local Growth Funds are administered and controlled by Thames Valley Berkshire LEP and the Royal Borough of Windsor & Maidenhead, the LEP’s Accountable Body.
Risk management
13. The risk management arrangements already put in place by the Local Transport Body are as follows:
a) The Assurance Framework has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes.
b) Hatch Regeneris have been appointed to act as Independent Assessors for all LEP-funded schemes.
Human Rights Act and Other Legal Implications
14. Slough Borough Council will provide legal support for the BLTB should any questions arise.
Supporting Information
15. The call for bids was approved at your meeting on 15 July 2020 (item 28), and the prioritisation methodology is set out at Appendix 2 below.
16. The table below sets out the details of the bids received. The full pro-forma submissions of the 16 registered bids are available via the hyperlinks in the table below. Hatch Regeneris, the Independent Assessor has also been involved in this process and has endorsed our approach.
Prioritisation of future projects
17. Table 1 shows the results of the prioritisation scoring, using the prioritisation methodology outlined within appendix 1.
Item 6 BLTB 12 November 2020 Call for Bids schemes to establish a new pipeline of projects Table 1 New Schemes Pipeline November 2020
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.