Resolved
Resolved – That the progress made on schemes previously given programme entry status be noted. (Councillor Jorgensen joined the meeting)
Berkshire Local Transport Body noted this item on Thursday 12 November 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the progress made on schemes previously given programme entry status be noted. (Councillor Jorgensen joined the meeting)
1. To report on the progress of the Thames Valley Berkshire Local Growth Deali, as amended by Growth Deal 2 (£10.2 million further support to Thames Valley Berkshireii) and Growth Deal 3 (Factsheet GD3iii) with particular reference to the schemes included in the Transport Packages of the Strategic Economic Planiv; and on the progress of schemes funded by the Business Rates Retention Pilots (BRRP) of 2018/19 and 2019/20. This report also reports on the transport element of the Getting Building Fund (GBF) released in September 2020.
2. The headline figure for transport scheme grants under the three Local Growth Deals is £135.926m. This includes £24m of “DfT retained” allocation relating to the Wokingham Distributor Roads. This report provides progress reports on all programme entry schemes and the TVB Smart City Cluster scheme. A further £25m has been released through BRRP1 2018/19 and £11m from BRRP2 2019/20. Thames Valley Berkshire has received £7.5m through the GBF, of which £1,643,000 has been allocated to a transport project.
3. £14.742m LGF was spent on transport schemes in 2015/16, £16.546m in 2016/17, £15.055m in 2017/18, £8.810m in 2018/19 and £12.441m 2019/20. In addition, £21.487m was spent from BRRP.
4. That you note the progress made on the schemes previously given programme entry status, as set out in the accompanying composite report.
Other Implications
5. The delegation of programme management responsibilities to the LEP/BLTB brings risks. The well- established scrutiny given by both BST(O)F and BLTB meetings is designed to mitigate that risk.
6. There will be an element of risk for scheme promoters who invest in developing their schemes to full business case stage in accordance with the approved Assurance Frameworkv. However, there is also risk involved in not developing the schemes; that risk is that any reluctance to bring the schemes forward will result in any final approval being delayed or refused.
7. The risks associated with each scheme are monitored locally. Table 4 has been adapted to show the current risk rating of each of the schemes. Completed schemes are shown in blue.
Item 5 BLTB 12 November 2020 - Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21 Financial
8. Thames Valley Berkshire LEP has been granted freedoms and flexibilities in managing the Local Growth Deal Capital Programme. This means that we will receive an annual allocation of capital within which it will be our responsibility to manage the award of LGF to individual schemes. This is a positive development for TVB LEP and recognises the confidence that government has in our governance arrangements.
Table 1: Available Finance for Transport Schemes in TVB Local Growth Deal, BRRP and GBF
£m 2015/16 – 2020/21 LTB previously approved 14.5 Growth Deal 1 56.1 Growth Deal 1 “DfT Major Schemes” 24.0 Growth Deal 2 7.5 Growth Deal 3 33.8 Local Growth Deal Total 135.9 BRRP 2018/19 and 2019/20 36.0 Getting Building Fund 2020/21 and 2021/22 1.6 Grand Total 173.5
9. The profile and status of the available money in each year is as follows:
Table 2: Local Growth Deal, BRRP and GBF Financial Allocations for Transport Schemes by Financial Year £m 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 Total Combined Growth Deal 1, 2, 3 and LTB Allocation 14.7 16.5 15.1 8.8 12.4 - - 67.6 approved Growth Deal 1 (DfT Major - - - 0.9 22.1 1.0 - 24.0 Schemes) indicative Combined Growth Deal 1, 2 and 3 LTB Allocation - - - - - 44.3 - 44.3 indicative profile Local Growth Deal Total 14.7 16.5 15.1 9.7 34.5 45.3 - 135.9 BRRP - - - 11.5 10.0 14.5 - 36.0 Getting Building Fund - - - - - - 1.6 1.6 Grand Total 14.7 16.5 15.1 21.2 44.5 59.8 1.6 173.5
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21Report | 153 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.