Resolved – That scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 be given re-profiled financial approval in the sum of £4,213,000 from the Local Growth Fund (LGF) and £1,068,000 from the Business Rates Retention Pilot (BRRP) funds in 2020/21 on the terms of the funding agreement set out at paragraph 12 step 5 of the report.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To consider giving financial approval to scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1, reprofiled.
2. This scheme was originally submitted for financial approval and conditionally approved by the Berkshire Local Transport Body (BLTB) in January 2019. Since then, the Royal Borough of Windsor and Maidenhead (RBWM) has been required to amend its Local Plan, resulting in a reconfiguration of development site allocations. This has resulted in necessary amendments to the original scheme proposals, as well as revisions to the dependent development ‘unlocked’ by the scheme. The revised scheme sets out the case for investment in capacity improvements at six key junctions around Maidenhead. The schemes will provide congestion relief associated with background growth in traffic, alongside trips generated by specific residential and commercial development sites within the town centre that have been allocated within the Local Plan.
3. The six junctions are spread across the town centre, as follows across two phases: Phase 1: - A308/ Stafferton Way/ Rushington Avenue (Stafferton Roundabout) - A4/ A308 Castle Hill (Castle Hill Roundabout) - A4/ B4447 Cookham Road/ Market Street (Cookham Roundabout) - A4/ A4094 Ray Mead Road/ Guard Club Road (Ray Mead Roundabout) Phase 2: - A308(M)/ A308 The Binghams (Braywick Roundabout) - A4/ B3024 Oldfield Road/ Lassell Gardens (Oldfield Junction)
4. The improvements encompass a range of measures including carriageway widening, signalisation, and junction reconfiguration, with some associated improvements to cycling provision.
Recommendation
1. You are recommended to give scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 reprofiled financial approval in the sum of £4,213,000 from the Local Growth Fund (LGF) and £1,068,000 from the Business Rates Retention Pilot (BRRP) funds in 2020/21 on the terms of the funding agreement set out at paragraph 12 step 5 below.
Item 9: BLTB 15 July 2020 Financial Approval 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 reprofiled Other Implications
Financial
5. Scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 is a replacement scheme being funded from the Thames Valley Berkshire Growth Deal 3i announced on 2 February 2017ii.
6. In July 2018, you re-allocated some previously approved LGF schemes for funding from the Business Rates Retention Pilot. This scheme was submitted as part of the process to reallocate Local Growth Deal allocations. The funding for this scheme is from both the LGF and BRRP.
7. This report recommends that the Royal Borough of Windsor and Maidenhead be authorised to draw down the capital sum £4,213,200 in LGF and £1,068,000 in BRRP from the Local Transport Body funding for this scheme.
8. The funding agreement set out at paragraph 12 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Risk management
9. The risk management arrangements already put in place by the Local Transport Body are as follows: The Assurance Frameworkiii has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.