Capital Programme 2011-2021

Agreed Executive 7 papers

AI summarySouthwark Cabinet agreed the refreshed ten year capital programme and housing investment programme. [P2][P3] It approved New Homes Bonus and LPSA funding, with a £63.8m overall favourable variance and a £12m 2011/12 funding shortfall. [P4][P5][P121][P122]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreed
Money£63.8m favourable variance. [P121]Housing investment programme totals £416m; 2011/12 shortfall £12m. [P118][P122]
What happens nextCouncil Assembly, 6 July 2011. [D]Cabinet recommends the general fund programme to Council Assembly. [D][P2]
Who it affectsCouncil services and housing. [P52][P111]

What was decided

Cabinet agreed the refreshed ten year general fund capital programme for recommendation to Council Assembly on 6 July 2011. Appendices A and F contain the detail. This part of the decision could not be called in for scrutiny. Report P2

Cabinet agreed the Housing Investment Programme and the use of estimated surplus New Homes Bonus resources up to 2016/17 for the capital programme. The housing programme covers works to council homes, estates and related regeneration. Report P3, P4, P36, P112, P113

Cabinet agreed to apply the LPSA Reward Grant to the capital programme. It also required the refreshed capital programme to be reported in February 2012 after the Olympic legacy bids. Report P5, P6

Why

Central government capital funding was expected to fall by 45%. New priorities, bids, project data and resource forecasts also required a refresh. Report P13, P14, P15

The 2010/11 outturn was 52% lower than the original in year budget. This allowed priorities and project and resource information to be updated. Report P12, P13

The housing programme was designed to deliver warm, safe and dry homes, regenerate estates and meet landlord obligations. Report P17

What happens next

Council Assembly should consider the refreshed general fund capital programme on 6 July 2011. Report P2

Cabinet should receive a refreshed capital programme in February 2012, following the Olympic legacy bids. Report P6

Cabinet should receive quarterly monitoring reports. If in year funding is insufficient, the council may use earmarked reserves or faster disposals, or defer or reprofile projects. Prudential borrowing would require Council Assembly approval. Report P20, P123, P124

The money

  • £63.8m Favourable variance between resources and forecast expenditure Report P121
  • £416m Net capital programme for the five year housing investment programme Report P113, P118
  • £54.3m Estimated New Homes Bonus receipts over six years Report P37
  • £4.3m One off LPSA Reward Grant, split 30% capital and 70% revenue Report P43, P44
  • £12m Potential funding shortfall for 2011/12 Report P122
  • £222m Ten year forecast disposal receipts for the general fund programme Report P24
  • £142m Five year forecast disposal receipts for the housing programme Report P24
  • £2m Corporate resources recommended for successful Olympic legacy projects Report P57

Options considered

  • Chosen: Refresh the general fund capital programme. The outturn position allowed priorities, bids, project information and resource forecasts to be updated. Report P2, P12, P13
  • Chosen: Agree the Housing Investment Programme. The programme focuses on warm, safe and dry homes, estate regeneration and landlord obligations. Report P3, P17, P112
  • Chosen: Apply estimated surplus New Homes Bonus to capital. The grant is unringfenced, and surplus above the revenue commitment can support the ten year capital programme. Report P4, P31, P36
  • Chosen: Apply the LPSA Reward Grant to capital. The one off grant is unrestricted, so its whole allocation can support capital expenditure. Report P5, P44, P45, P46
  • Chosen: Refresh the programme again in February 2012. This would maintain a ten year programme and address priorities not successful through the Olympic legacy scheme. Report P6, P124

Implications

  • Financial: The ten year programme has sufficient resources for anticipated spending. It has a £63.8m favourable variance. Report P121, P133
  • Financial: The 2011/12 programme has a potential £12m funding shortfall, so projects may need reprofiling or deferral. Report P20, P122
  • Risk: The programme depends heavily on property disposal receipts, whose value and timing remain uncertain. Report P22, P23
  • Legal: Cabinet is responsible for effective financial control and value for money. The council must maintain a balanced budget, monitor its position and act if that position deteriorates. Report P137, P138, P139
  • Equalities: Each project must be considered for effects on age, disability, faith or religion, gender, race and ethnicity, and sexual orientation. Report P127
  • Climate: The programme includes low or zero carbon energy provision and housing retrofit contributing to carbon emissions targets. Report P82, P106
  • Staffing: Delivery will be identified project by project and generally within current staffing. Report P131
  • Other: No consultation took place on the overall programme. Individual projects remain subject to the consultation required or considered desirable. Report P134

Who and where

  • Council residents and communities Report P126, P128
  • Children and schools Report P59, P63, P64
  • Council housing tenants and leaseholders Report P82, P114
  • People using adult social care and community services Report P73, P77
  • Residents using roads, parks, libraries and leisure centres Report P80, P81, P82
  • Local businesses, workers and visitors Report P96
  • Council staff and service users in council buildings Report P90, P102
  • Schools, sports groups and Olympic legacy applicants Report P55, P56

Timeline

  • 2010/11: General fund capital expenditure was £96.1m and housing investment expenditure was £70.5m. Report P11
  • 25 January 2011: Cabinet noted the potential New Homes Bonus and committed £1.5m to the revenue budget from 2011/12. Report P33
  • March 2011: The council received the £4.3m LPSA Reward Grant. Report P43
  • 3 March 2011: The Olympic capital legacy fund was launched and invited bids. Report P55
  • 31 May 2011: The Housing Investment Programme and Revised Strategy report went to Cabinet. Report P112
  • 6 July 2011: Council Assembly was to consider the refreshed general fund capital programme. Report P2
  • October 2011: Final decisions were due on successful Olympic legacy applications. Report P55
  • February 2012: Cabinet was to receive the refreshed capital programme. Report P6, P124

Plain English for the jargon

  • Housing Investment Programme: Investment in council housing through works to homes, estates and related regeneration. [P112][P113]
  • New Homes Bonus: An unringfenced grant rewarding authorities and communities where housing growth occurs. [P31]
  • Local Public Service Agreement: A government arrangement of performance targets that can attract a reward grant. [P41]
  • Section 106: A planning obligation under which a developer contributes to offset development impacts. [P27]
  • Major Repairs Allowance: Central government funding providing about £39m per year for the housing programme. [P114]
  • Outturn: The reported actual spending position for a financial year. [P12]
  • Reprofiling: Changing the timing of planned project spending. [P20][P21]
  • Prudential borrowing: A possible way to fund capital schemes, but it would require Council Assembly approval. [P123]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That the refreshed 10-year general fund capital programme 2011–2021, as detailed in appendices A and F of the report be agreed for recommendation to council assembly to be held on 6 July 2011. 2. That the Housing Investment Programme 2011–2016 as detailed in appendix B of the report be agreed. 3. That the application of New Homes Bonus over the period to 2016/17 to finance the capital programme be agreed. 4. That the application of the Local Public Service Agreement (LPSA) Reward Grant to finance the capital programme be agreed. 5. That the refreshed capital programme for 2012-22 be formally reported to cabinet in February 2012 to ensure council priorities continue to be met and following announcement of the successful Olympic legacy bids. NOTE : In accordance with overview and scrutiny procedure rule 22.1(a) (budget and policy framework) decision 1 is not subject to call-in.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 16 pages

Recommendations

That Cabinet:

1. Agree the refreshed 10-year general fund capital programme 2011–2021, as detailed in appendices A and F for recommendation to Council Assembly in July.

2. Agree the Housing Investment Programme 2011–2016 as detailed in appendix B.

3. Agree the application of New Homes Bonus over the period to 2016/17 to finance the capital programme.

4. Agree the application of the LPSA Reward Grant to finance the capital programme.

5. Agree that the refreshed capital programme for 2012-22 be formally reported to Cabinet in February 2012 to ensure council priorities continue to be met and following announcement of the successful Olympic legacy bids.

BACKGROUND INFORMATION

6. On 9 February 2010 the then Executive approved a refresh of the 10-year capital programme for 2009-19. The Executive approved a total programme for ten years of £538.1m for the general fund programme. A total programme for seven years of £592.5m was also agreed for the housing investment programme.

KEY ISSUES FOR CONSIDERATION

General Fund Capital Spend

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
General Fund Capital Programme Summary 2011-21Appendix A 4 pages Download
PDF
Housing Investment Programme Summary 2011-16Appendix B 2 pages Download
PDF
Amendments to General Fund Capital ProgrammeAppendix C 1 pages Download
PDF
Additions to General Fund Capital ProgrammeAppendix D 1 pages Download
PDF
Children's Services Capital Programme UpdateAppendix E 8 pages Download
PDF
General Fund Capital Progamme 2011-21Appendix F 3 pages Download
PDF
Report: Capital Programme 2011-2021Report 16 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
AM
Councillor Abdul MohamedCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
AS
Annie ShepperdOfficer, expected
DC
Deborah CollinsOfficer, expected

On this subject at Southwark

Search all
  1. Capital Programme 2011-2021This decision
  2. Capital Programme 2009/10 Outturn ReportNoted
  3. Capital Programme 2010/19 - Quarter 1 Monitoring ReportNoted
  4. Capital Programme 2010-19 Quarter 2 Monitoring ReportNoted
  5. Capital Programme 2010-19 Quarter 3 Monitoring ReportNoted
  6. Capital Programme 2010/11 Outturn reportNoted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies