Resolved
That the representations of the deputation and the comments of the strategic director of environment be noted.
AI summarySouthwark Cabinet noted the deputation's representations and comments from the Strategic Director of Environment [D]. The report covers phased refurbishment, with approximately £4.7 million spent and £1.1 million estimated for phase three if funding becomes available [P4] [P15] [P16].
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
That the representations of the deputation and the comments of the strategic director of environment be noted.
ITEM 6 – DEPUTATION REQUEST – CAMBERWELL BATHS CAMPAIGN
SUPPLEMENTARY ADVICE FROM OTHER OFFICERS
Comments of the Strategic Director of Environment
1. Camberwell Leisure Centre has been developed in phases as funding has become available. Broadly speaking, there have hitherto been two main phases:
2. Phase 1 is completed and opened to the public in March 2011. It included the following:
Reception upgrade: The reception area and entrance foyer have been renovated to ensure compliance with the Disability Discrimination Act guidelines and in addition the centre has introduced a hearing induction loop and visual impairment amendments. The entrance area features an open access café with servery and seating area.
Modification to the pool: A new boom has been built to separate the main and teaching pools and create two properly separate pools. The boom incorporates stepped access which will improve access to the pools for the elderly, young children and disabled users. A new pool-side hoist has been installed to assist people with disabilities to access the pools.
Structural and plant upgrades: The pool hall, corridor, windows and roof have been refurbished ensuring the surrounding areas of the pool-side remain energy efficient. Upgrades to the pool plant have been undertaken to ensure the long term future of the baths.
Mechanical and electrical upgrades: A new electricity supply with latest energy- saving lighting has been installed to help improve energy efficiency. New air handling and heat recovery units will make using the facility a more pleasurable experience for customers.
Changing rooms: Male and female changing rooms will be refurbished to Sport England standards. In addition, a new family changing area and two disabled changing rooms with toilets will be included alongside the pool to encourage greater participation by disabled users and families with young children.
3. Phase 2 is currently on site and due to open in September 2011. It includes the following improvements.
Gym: A fully reconfigured, expanded and renovated gym and fitness area.
Sports hall: Structural improvements to ensure the ongoing use of the hall.
Youth facility: Consisting of social spaces, workshops, training rooms and a music production room.
Warwick Hall: A fully refurbished 200 square metre area, including a new sprung floor, air handling system, exposed Victoria roof structure and a new sound system. 4. The total spend on Phases 1 and 2 is approximately £4.7 million
5. If funding becomes available the third phase of refurbishment of the leisure centre can proceed, to make significant improvements to the sports hall and increase its usefulness to players of sport and the community in general. This will be achieved by levelling and replacing the floor (with a proper sprung surface); improving the lighting and air circulation and repairing the roof and skylights as well as redecorating the area in a sympathetic fashion. Although detailed survey and design work has not been undertaken on this phase, initial costings estimate that the programme requires a budget of £1.1 million to accomplish fully.
6. A final stage of works, to improve the public realm around the centre, (Artichoke Place and Harvey Road) has been costed at approximately 0.8 million
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Deputation request: comments from strategic director of environmentReport | 2 pages | DownloadRead as text |
PDF |
Report: Deputation Request -Camberwell Baths campaignReport | 2 pages | Download |
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 May 2026 | Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. | Decided | Open |
| 28 May 2026 | Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... | Agreed | Open |
| 28 May 2026 | Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... | Decided | Open |
| 28 May 2026 | Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... | Noted | Open |
| 28 May 2026 | Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.