AI summarySouthwark Cabinet noted the 2010/11 capital outturn and approved general fund virements, funded variations and reprofiling [D]. The reprofiled general fund programme totals 279,958, with resources of 333,329, in £'000 [P46][P48].
Written from the decision and the officer reportPDF Pro
OutcomeNotedGeneral fund and housing investment programmes [D]
Money279,958 and 333,329 [P46][P48]Reprofiled programme expenditure and resources, £'000 [P46][P48]
What happens nextApply approved budget changes [D]Virements, funded variations and reprofiling [D]
Who it affectsCouncil capital services and housing [D]Seven general fund service areas and the housing programme [P4][P14][P45]
What was decided
The 2010/11 general fund capital outturn was noted, including the overall programme position for 2010-19 [D].
The 2010/11 housing investment outturn was noted, including the overall programme position for 2010-16 [D].
The virements and funded variations to the general fund capital programme were approved [D]. The reprofiling of expenditure and resources into the 2011-19 general fund capital programme was approved [D].
Why
The 2010/11 general fund outturn was 96,103 against a revised budget of 136,191, with a recorded variance of (40,088), in £'000 [P5]. Report P5
The 2010/11 housing investment outturn was 70,536 against a revised budget of 87,781, with a recorded variance of (17,245), in £'000 [P18]. Report P18
The fourth quarter changes include responsibility moves, added funding and adjustments across schools, social care, leisure and environmental projects [P32][P38]. Report P32, P38
What happens next
Apply the approved fourth quarter virements to the revised service budgets [D][P34][P35][P40]. Report P34, P35, P40
Apply the funded variations with their listed financing sources [D][P37][P43]. Report P37, P43
Use the reprofiled forecasts for 2011/12, 2012/13 and 2013/14+ [D][P44][P48]. Report P44, P48
The money
96,103 General fund 2010/11 outturn, £'000 [P5] Report P5
279,958 Reprofiled general fund forecast total, £'000 [P46] Report P46
333,329 Reprofiled general fund resources total, £'000 [P48] Report P48
(60,067) General fund variations approved, £'000 [D][P39] Report P39
826,721 Overall programme total after revisions, £'000 [P40] Report P40
Options considered
Chosen: Note the general fund outturn and overall 2010-19 position [D]
Chosen: Note the housing investment outturn and overall 2010-16 position [D]
Chosen: Approve virements and funded variations to the general fund programme [D]
Chosen: Approve reprofiling of expenditure and resources into the 2011-19 programme [D]
Implications
Financial: The approved general fund changes reduce the programme from 436,224 at quarter 3 to 376,157, a change of (60,067), in £'000 [D][P31][P39][P40]. Report P31, P39, P40
Financial: The reprofiled programme records forecast expenditure of 279,958 and resources of 333,329, with forecast variation (53,371), in £'000 [P46][P48][P49]. Report P46, P48, P49
Financial: For 2013/14+, forecast expenditure is 55,970 and resources are 139,026, with forecast variation (83,056), in £'000 [P45][P47][P48][P49]. Report P45, P47, P48, P49
Financial: The housing investment programme records a forecast of 107,130 and resources of 107,130, with forecast variation 0, in £'000 [P18][P20][P21]. Report P18, P20, P21
Financial: The 2010/11 outturn variance is (40,088) for the general fund and (17,245) for housing, in £'000 [P5][P18]. Report P5, P18
Financial: Southwark Schools for the Future has a total funded variation of (63,851), in £'000 [P38][P39]. Report P38, P39
Financial: The overall programme total after the fourth quarter revisions is 826,721, in £'000 [P40]. Report P40
Other: Seven general fund service areas and the housing investment programme are affected by the revised figures [P4][P14][P40][P45]. Report P4, P14, P40, P45
Who and where
Southwark Schools for the Future [P4][P45] Report P4, P45
2026-05-28: Cabinet noted the outturns and approved the budget changes [D]
2010/11: General fund and housing investment outturns were noted [D][P5][P18] Report P5, P18
2010-19: The overall general fund programme position was included in the noted outturn [D]
2010-16: The overall housing investment programme position was included in the noted outturn [D]
2011/12: First forecast year within the reprofiled general fund programme [P44][P45] Report P44, P45
2012/13: Second forecast year within the reprofiled general fund programme [P44][P45] Report P44, P45
2013/14+: Remaining forecast period within the reprofiled general fund programme [P44][P45] Report P44, P45
Plain English for the jargon
General fund capital programme: The capital programme summarised in Appendix A [P1].
HRA capital programme: The housing capital programme summarised in Appendix B [P14].
Outturn: The reported 2010/11 position for a capital programme [D][P5][P18].
Virement: A budget change listed for approval in Appendix C [P34][P35].
Funded variation: A programme change paired with listed financing in Appendix C [P36][P43].
Reprofiling: Moving expenditure and resources into later programme years [D][P44].
Forecast variation (under)/over: The difference recorded between forecast and budget [P8][P49].
Corporate Resource Pool: A financing source listed in the capital resources tables [P6][P12][P47].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
That the outturn position for 2010/11 for the general fund capital programme including the overall position of the programme from 2010-19 (appendix A of the report) be noted. 2. That the outturn position for 2010/11 for the housing investment programme including the overall position of the programme from 2010-16 (appendix B of the report) be noted. 3. That the virements and funded variations to the general fund capital programme (appendix C of the report) be approved. 4. That the reprofiling of expenditure and resources into the 2011-19 general fund capital programme (appendix D of the report) be approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.