CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Gateway 1 Procurement Strategy Approval - Supply of gas to sites consuming less than 25,000 therms

Approved Executive 1 paper

AI summarySouthwark Cabinet approved consortium procurement for gas to sites consuming under 25,000 therms, with supply from October 2012 for four years [D] [P2]. LASER and Buying Solutions will be evaluated for a contract with an estimated value of £28,450,000 [P3] [P105].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedLASER and Buying Solutions will be evaluated [P3]
Money£28,450,000 estimated value [P105]Billed costs depend on wholesale market prices [P101]
What happens nextGateway 2 approval required [P106]Officers will recommend the least risk buying option [P55]
Who it affects132 Council estate sites [P7]Housing estates, schools and municipal offices [P7]

What was decided

Cabinet approved the procurement strategy for supplying gas to all sites consuming less than 25,000 therms [D].

Cabinet approved use of a consortium to award the supply for a four year period from October 2012 [D].

Cabinet approved evaluation of LASER and Buying Solutions [D].

Why

The Council was buying again for an existing gas supply requirement [P23]. The proposed buying method was intended to ensure best value [P24]. Report P23, P24

Consortium purchasing would give access to wholesale prices rather than retail prices and avoid settling all gas costs on one day [P41]. Report P41

A flexible framework spreads buying decisions across the contract period and reduces the risk from gas price volatility [P65]. Report P65

What happens next

The Energy Team will evaluate LASER and Buying Solutions with Procurement, Corporate Finance and Legal Services against the ordered criteria [P49] [P51]. Report P49, P51

A council representative group will review detailed risk and buying analysis, and estimated values will be updated for disposals and new sites, before Gateway 2 [P16] [P54] [P100]. Report P16, P54, P100

Officers will recommend the least risk purchasing option, and Gateway 2 will seek approval for the consortia and contract award [P55] [P106]. If a leaseholder service charge would exceed £100, the Council must carry out section 20 consultation [P110]. It may seek tribunal dispensation for requirements it cannot meet [P111]. Report P55, P106, P110, P111

The money

  • £28,450,000 Estimated value of this procurement Report P105
  • £100 Annual service charge consultation threshold for any leaseholder Report P110
  • £100 per annum Cap on annual service charges if section 20 is not complied with and no dispensation is obtained Report P112
  • £30,000 Estimated Office of Government Commerce cost of going through the OJEU process Report P37
  • £12 tonne equivalent Carbon allowance purchase price for emissions from financial year 2011/2012 Report P20
  • £44 tonne Potential fine for failing to present data for sites under Council control Report P20

Options considered

  • Chosen: Procure through a consortium under a Central Purchasing Body. It gives access to wholesale prices and is the recommended best practice approach [P41] [P48]. Report P41, P48
  • Chosen: Evaluate LASER and Buying Solutions. Both consortiums offer solutions, and Gateway 2 will assess their best value options [P45] [P49]. Report P45, P49
  • Chosen: Gateway 2 selection between Purchase in Advance and Purchase Within Period. Officers will recommend the option presenting the least risk using the stated performance, market and risk criteria [P55] [P56]. Report P55, P56
  • Rejected: Fixed price contracts lasting one or two years. They fix the whole contract price on one day, add procurement costs and officer time, and are not offered by either consortium [P59] [P60] [P62]. Report P59, P60, P62
  • Rejected: Do nothing and leave each site to negotiate. This would leave sites off contract, create financial risk and significantly increase gas supply costs [P63]. Report P63
  • Rejected: Separate publicly advertised OJEU tender by the Council. The consortia already use compliant framework processes, and gateway one approval allows use of a consortium contract without a separate advertised tender [P38] [P40] [P106]. Report P38, P40, P106

Implications

  • Financial: Estimated contract costs are based on current wholesale costs [P99]. Actual billed costs depend on the purchasing option and prices secured in the wholesale market [P101]. Report P99, P101
  • Legal: If any leaseholder's annual service charge would exceed £100, statutory consultation under section 20 is required [P110]. If the Council does not comply, service charges could be capped at £100 per annum and the Housing Revenue Account could lose significant money [P112]. Report P110, P112
  • Risk: Gas prices are highly volatile, and the greatest buying risk is deciding when and how much gas to purchase [P34] [P65]. Report P34, P65
  • Climate: The Carbon Reduction Commitment requires carbon emissions from electricity and gas consumption to be reported at all Council operational sites, including schools and academies [P20]. Report P20
  • Risk: The flexible framework is not awarded on the lowest gas price, because wholesale market conditions and buying decisions set the price [P81]. Report P81
  • Climate: Natural gas has no sustainable alternative for this form of heating supply [P85]. The SELCHP district heating network may provide a long term solution for sites within its locality [P86]. Report P85, P86
  • Staffing: Client departments will pay and monitor their invoices [P94] [P98]. The Energy Team will be the single contact for supplier queries [P94] [P98]. Report P94, P98
  • Equalities: The report says all sections of the community are equally affected by rising energy prices [P83]. Report P83

Who and where

  • All sites consuming less than 25,000 therms Report P7, P24
  • Smaller centrally heated housing estates Report P7, P83
  • Schools Report P7
  • Municipal offices Report P7
  • Leaseholders Report P110, P112
  • Tenants using communal heating systems Report P83
  • Client departments responsible for paying energy bills Report P24, P94
  • The Housing Revenue Account Report P112

Timeline

  • 21/06/2011: Gateway 1 procurement strategy approval report [P75]. Report P75
  • 30th June 2011: Southwark must provide its intended procurement approach to the consortia [P18]. Report P18
  • 26/08/2011: Council evaluation of the consortia and purchasing solution [P76]. Report P76
  • September 2011: If a flexible managed solution is used, the Council will enter a contract with the chosen consortia [P18]. Report P18
  • 23/09/2011: Gateway 2 approval for the consortia and contract award [P76]. Report P76
  • 30th September 2012: Existing LASER and British Gas framework agreement ends [P9]. Report P9
  • 01/10/2012: Start of Southwark's buy in to the new contract [P76]. Report P76
  • 31/09/2016: Contract completion [P76]. Report P76

Plain English for the jargon

  • Therm and kilowatt hour, kWh: Units of gas energy [P7]. 25,000 therms are equivalent to 732,500 kWh [P7].
  • Central Purchasing Body, CPB: A body that buys aggregated energy volumes through wholesale markets for local authorities [P37] [P42].
  • LASER and Buying Solutions: The two consortiums evaluated for the contract [P45]. LASER is part of Kent County Council [P46]. Buying Solutions is in the Cabinet Office [P47].
  • Purchase Within Period and Purchase in Advance: Two flexible buying choices [P11] [P13]. PWP buys before and during the contract, with six monthly reconciliation [P11]. PIA buys before supply and locks an average price for each supply year [P13].
  • Gateway 2: The approval stage for selecting a consortium and awarding the contract [P55] [P76] [P106]. Officers will present the recommended purchasing solution [P55].
  • OJEU: Official Journal of the European Union, where the contract is publicly advertised [P75] [P118].
  • Carbon Reduction Commitment, CRC: A requirement to report carbon emissions from electricity and gas consumption at all Council operational sites [P20].
  • Section 20: Landlord and Tenant Act 1985 consultation rules for leaseholders [P110]. There are two notice stages, each with a thirty day observation period [P110].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item21

Resolved

That the procurement strategy outlined in the report for the supply of gas to all sites consuming less than 25,000 therms at an estimated value outlined in the closed version of the report be approved. 2. That the use of a Consortium to award the supply of gas to all sites consuming less than 25,000 therms for a four year period from October 2012 be approved. 3. That the evaluation of the two buying consortia for the award of the contract proposed in the report, namely LASER and Buying Solutions be approved.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 13 pages

Recommendations

1. That the Cabinet approves the procurement strategy outlined in this report for the supply of gas to all sites consuming less than 25,000 therms at an estimated value outlined in the closed version of this report.

2. That the Cabinet approves the use of a Consortium to award the supply of gas to all sites consuming less than 25,000 therms for a four year period from October 2012.

1 3. That the Cabinet approves the evaluation of the two buying consortia for the award of the contract proposed in this report, namely LASER and Buying Solutions.

BACKGROUND INFORMATION

4. The Council has seven contracts for electricity and gas supplies to municipal sites, schools and housing estates. Four of these cover electricity supplies to over 3500 sites. Three are for supplies of gas to over 200 sites.

5. The contracts are set up in such a way to provide best value for the Council through the length, duration and the specification. Contracts have sites, schools and housing assigned to them dependant on their energy usage and spend. A result of this is that 5 of the contracts run concurrently with LASER (a non-profit making organisation managed by Kent County Council’s Commercial Services Department) and expire in September 2012 (see background document – energy contracts schedule).

6. This report relates to the contract that covers the supply of gas to sites consuming less than 25,000 therms (equivalent to 732,500 kWh). These are small to medium sized sites including smaller centrally heated housing estates, schools and municipal offices. There are 135 supplies of gas to 132 sites in the Council estate. A list of sites currently utilising this contract is attached in the appendix.

7. The current flexible contract removes the wholesale cost of energy from the competitive tender process. An EU compliant tender process was used by LASER on behalf of a consortium of authorities including Southwark in 2009.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Gateway 1 Procurement Strategy Approval: Supply of gas to sites consuming less than 25,000 thermsReport 13 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
AM
Councillor Abdul MohamedCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
AS
Annie ShepperdOfficer, expected
DC
Deborah CollinsOfficer, expected

On this subject at Southwark

Search all
  1. Gateway 1 Procurement Strategy Approval - Supply of gas to sites consuming less than 25,000 thermsThis decision
  2. Gateway 1 – Procurement Strategy Approval -The NestApproved
  3. Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers FrameworkApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies