Disposal of 1-11 (odd) Pytchley Road, East Dulwich SE22 8DG
AgreedExecutive2 papers
AI summarySouthwark Cabinet authorised the freehold sale of 1 to 11 Pytchley Road and approved using the receipt to replenish housing investment for East Dulwich Estate refurbishment. [D][P2] The purchaser has agreed to contribute 0.5% of the purchase price towards surveyors and legal costs. [P32]
Written from the decision and the officer reportPDF Pro
OutcomeAgreedTerms may be agreed with the purchaser, or under bidders. [D]
MoneyCapital receipt and 0.5% contributionReceipt replenishes housing; purchaser pays 0.5% of purchase price. [P3][P32]
What happens nextSale terms to be finalisedTerms may be agreed if the original offer fails. [D]
Who it affectsHousing, tenants and estate regenerationSale reduces lettings but no tenants are displaced. [P24][P26]
What was decided
Cabinet authorised disposal of the council's freehold interest in the Property on the terms set out in the closed report. [D][P2] Report P2
The capital receipt was authorised to replenish the housing investment programme, which had forward funded the East Dulwich Estate refurbishment programme. [D][P3][P45] Report P3, P45
The head of property may agree precise sale terms with the purchaser and, if the original offer does not progress, with under bidders, subject to best consideration. [D][P4] Report P4
Why
The property was a derelict and empty block of six residential units, declared surplus on 05/07/2011. [P7][P8][P14] Report P7, P8, P14
Informal tender produced eighteen bids from ten bidders. The highest bidder was identified, and the price equates to current market value. [P11][P16][P17] Report P11, P16, P17
The sale was expected to bring the site quickly back into beneficial use and help fund refurbishment costs that rose from £25.1m to £30.9m. [P18][P19] Report P18, P19
What happens next
The head of property will agree precise sale terms with the purchaser. [D][P4] Report P4
If the original offer fails to progress to completion, which the decision describes as unlikely, terms may be agreed with under bidders, subject to best consideration. [D][P4] Report P4
The transaction requires planning consent. Completion was expected to take in the region of 9 to 12 months, with the receipt placed in 2012/2013. [P34][P35] Report P34, P35
The money
0.5% Purchaser contribution towards the council's surveyors and legal costs, based on the purchase price. [P32][P46] Report P32, P46
£30.9m Total capital cost after costs rose during the estate refurbishment project. [P19] Report P19
£25.1m Initial total capital cost for the estate refurbishment project. [P19] Report P19
Options considered
Chosen: Dispose of the freehold to the purchaser. The property was properly marketed by informal tender, and the highest bidder was identified. [P17] Report P17
Chosen: Agree terms with under bidders if the original offer fails. The decision allows this unlikely contingency, subject to best consideration requirements. [D][P4] Report P4
Rejected: Include the site in the wider estate planning application. The peripheral site was removed from the scheme, with no expected impact on the other developments. [P13] Report P13
Implications
Financial: The receipt will replenish the housing investment programme and contribute to East Dulwich Estate refurbishment and other affordable housing priorities. [P3][P19][P21][P45] Report P3, P19, P21, P45
Financial: The sale has no impact on subsidy, rent budgets or future HRA self financing debt. [P31][P46] Report P31, P46
Financial: Disposal management and legal charges, sales and marketing costs are reimbursed from receipts, and implementation costs sit within existing budgeted resources. [P33][P46] Report P33, P46
Legal: Section 32 of the Housing Act 1985 applies. General Consent E3.1 permits disposal for best consideration because the dwelling is vacant, will not be used as housing accommodation and will be demolished. [P39][P40][P41][P42] Report P39, P40, P41, P42
Risk: The transaction depends on planning consent. The report states that no other risks or costs are involved. [P34][P36] Report P34, P36
Equalities: Investment in warm, dry and safe homes is expected to benefit disadvantaged and minority communities, who are statistically more likely to be council tenants. [P25] Report P25
Other: The sale reduces the number of council properties available to let, but this is offset by investment in retained stock. [P24] Report P24
Other: No tenants will be displaced. Refurbishment or redevelopment is likely to benefit the wider community. [P26][P29] Report P26, P29
Who and where
Council tenants Report P24, P25
People in disadvantaged and minority communities Report P25
People living in retained Southwark housing stock Report P25
The wider East Dulwich community Report P29
Timeline
31 May 2011: Cabinet gave in principle agreement to disposal to a third party, with detailed terms left for later. [P6] Report P6
05/07/2011: The property was declared surplus to the council's requirements. [P14] Report P14
9 July and 30 July: Advertisements for the property were placed in the Estates Gazette. [P9] Report P9
23 September 2011: Most bids in the informal tender were received by the bid date. [P11] Report P11
2007/08: Six former HRA flats were deleted from subsidy and rent listings pending sale. [P31] Report P31
in the region of 9 to 12 months: Completion was expected after planning consent, with the receipt placed in 2012/2013. [P34][P35] Report P34, P35
11 November 2011: The officer report was marked as final. [P51] Report P51
2026-05-28: Cabinet authorised the freehold disposal. [D]
Plain English for the jargon
HRA: Housing Revenue Account. [P12] The Property is held in this account. [P12]
EDERPT: East Dulwich Estate Regeneration Project Team, which has supported delivery of the estate regeneration. [P28]
General Consent E3.1: A General Housing Consent allowing disposal for best consideration where the dwelling is vacant, will not be used as housing accommodation and will be demolished. [P39][P40][P41][P42]
Best consideration: The disposal requirement that the price achieved equates to the property's current market value. [P16]
Informal tender: The council's sales process that produced eighteen bids from ten bidders and led to the highest bidder being identified. [P11][P17]
Property: The council's freehold interest in 1 to 11 Pytchley Road, SE22 8DG. [P2]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
That the head of property be authorised to dispose of the council’s freehold interest in 1-11 Pytchley Road, SE22 8DG (“the Property”), on the terms outlined in the closed version of the report. 2. That the capital receipt to replenish the housing investment programme from which the East Dulwich Estate refurbishment programme was forward funded be authorised. 3. That the head of property be authorised to agree the precise terms of the sale, with the purchaser, and to agree terms with any of the under bidders subject to best consideration requirements in the unlikely event the original offer fails to progress to completion.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 5 pages
Recommendations
That the cabinet authorises
1. The head of property to dispose of the council’s freehold interest in 1-11 Pytchley Road, SE22 8DG (“the Property”), on the terms outlined in the closed version of this report.
2. The capital receipt to replenish the housing investment programme from which the East Dulwich Estate refurbishment programme was forward funded.
3. The head of property to agree the precise terms of the sale, with the purchaser, and to be able to agree terms with any of the under bidders subject to best consideration requirements in the unlikely event the original offer fails to progress to completion.
BACKGROUND INFORMATION
4. Following consideration of a report dated the 31 May 2011 entitled ‘East Dulwich Estate Regeneration Scheme Update and Proposals for Revision’, cabinet resolved that ‘in principle’ agreement be given to the disposal of the property to a third party and the detailed terms to be considered at a later date. The report gives a comprehensive history of the funding arrangements underlying the refurbishment of the estate.
5. The property is a broadly square site on which currently stands a derelict three
1 storey block arranged as six residential units. The entire block is empty, bricked up and fenced off. The Property is identified in bold outline on the attached Ordnance Survey extract, at appendix 1.
6. Following the cabinet decision on the 31 May, the property has been marketed for sale by the council’s property team. Following the preparation of both a brochure together with a relevant sales pack and after undertaking adequate due diligence, advertisements were placed in the Estates Gazette on the 9 July and 30 July. A sales board was also erected at the Property during the period of marketing.
7. A list of property contacts including, developers, architects, investors, registered providers and housebuilders were all sent a brochure detailing the development opportunity arising from the proposed sale. These marketing actions generated a healthy response by those that sought further information and the sales pack that detailed the informal tender process.
8. The informal tender exercise generated eighteen bids from ten bidders. The majority of the bids were received by the bid date of the 23 September 2011. These are detailed in the spreadsheet contained in the closed version of this report.
9. The Property is held in the housing revenue account (HRA).
10. Housing regeneration initiatives had originally planned to submit a planning application on the site in conjunction with other sites on the estates. The removal of this peripheral site form the scheme is not considered to have an impact on the other developments moving forward.
11. The Property was declared surplus to the council’s requirements by the then strategic director of regeneration and neighbourhoods on 05/07/2011.
KEY ISSUES FOR CONSIDERATION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.