Elephant and Castle Regeneration - Shopping Centre
AgreedExecutive1 paper
AI summaryLondon Borough of Southwark Cabinet agreed to enter agreements with Lend Lease (Elephant and Castle) Ltd and KPI III SARL on principal terms in the closed report, and vary the Elephant and Castle Regeneration Agreement. [D] The report creates no immediate council resource requirement. [P18] [P24]
Written from the decision and the officer reportPDF Pro
OutcomeAgreedThis reflects a change in delivery approach. [D]
MoneyNo immediate resource implications arise from this report. [P18] [P24]
What happens nextFinalise and complete agreements [P9]Lawyers will settle wording before the Regeneration Agreement is amended. [P9]
Who it affectsNot stated
What was decided
Cabinet agreed to enter agreements with Lend Lease (Elephant and Castle) Ltd and KPI III SARL to take forward the Shopping Centre regeneration. [D]
The principal terms for the agreements are in Appendices A and B of the closed report. [D]
Cabinet agreed to vary the Elephant and Castle Regeneration Agreement to reflect the change in delivery approach. [D]
Why
Negotiations with KPI III SARL and Lend Lease have concluded and are recorded in Heads of Agreement at Appendices A to B of the closed report. [P9] Report P9
KPI SARL's board will not release funding for detailed design work until the agreement is signed. [P26] Report P26
A delay in completing the contract by the council would mean design works begin three months later than programmed, with a knock on effect on the regeneration programme. This is contrary to the council's aspiration to bring forward the regeneration as soon as possible. [P26] Report P26
What happens next
Respective lawyers are to agree the final wording of documents giving effect to the agreements, subject to Cabinet approval. Once the agreements are concluded, the Regeneration Agreement between the council and Lend Lease will be amended. [P9] Report P9
KPI's target submission dates are 30 September 2012 for the outline planning application and 30 November 2014 for the full application. The dates depend on satisfactory resolution of current transport issues, including the tube network and northern roundabout. [P11] [P12] [P13] Report P11, P12, P13
The recommendations will result in additional consultation, and the previously completed full equalities impact assessment will be reviewed at the planning application stage. [P16] Report P16
Options considered
Chosen: Agreement with KPI III SARL for Shopping Centre regeneration. KPI is the Shopping Centre owner and will provide for its regeneration. [P5] Report P2, P5
Chosen: Co operation agreement with KPI III SARL and Lend Lease. They will co operate to bring forward the overall regeneration of the area. [P5] Report P2, P5
Chosen: Variation of the Elephant and Castle Regeneration Agreement. The variation will reflect the change in delivery approach. [P2] [P9] Report P2, P9
Implications
Financial: The recommendations do not require resources over and above those already identified for the regeneration project. [P18] Report P18
Financial: KPI SARL's board will not release funding for detailed design work until the agreement is signed. [P26] Report P26
Legal: The agreements will be documented after lawyers agree wording, subject to Cabinet approval, and the Regeneration Agreement will then be amended. [P9] Report P9
Equalities: The recommendations will result in additional consultation. The previously completed full equalities impact assessment will be reviewed when the overall regeneration planning application is made. [P16] Report P16
Risk: The target application dates depend on satisfactory resolution of current transport issues and issues affecting the tube network and northern roundabout. [P13] Report P13
Risk: Regeneration will commence only after the full planning application is approved and conditions such as funding and viability have been satisfied. [P14] Report P14
Risk: Delay in completing the contract would begin design works three months later than programmed and have a knock on effect on the regeneration programme. [P26] Report P26
Other: Any development schemes emerging later from the Shopping Centre regeneration will be subject to separate reports. [P18] [P24] Report P18, P24
Who and where
Elephant and Castle Shopping Centre Report P2, P12
Overall Elephant and Castle regeneration area Report P5, P16
KPI III SARL, the Shopping Centre owner Report P5, P9
Lend Lease (Elephant and Castle) Ltd, the council's principal partner Report P5
Community involved in regeneration consultation Report P16
Timeline
17 May 2011: Cabinet resolved to enter two agreements and vary the Regeneration Agreement for the change in delivery approach. Report P4, P31
15 November: A Lend Lease board decision needed to finalise the report. Report P29
17 November 2011: The final report was dated and sent to the Constitutional Team. Report P34
30 September 2012: KPI's target date for submitting the outline planning application. Report P12
30 November 2014: KPI's target date for submitting the full planning application. Report P12
Once the full planning application has been approved: Regeneration will commence when conditions such as funding and viability have been satisfied. Report P14
Plain English for the jargon
KPI: KPI III SARL, the Elephant Shopping Centre owner, associated with St Modwen PLC. [P5] [P9]
Lend Lease: Lend Lease (Elephant and Castle) Ltd, the council's principal partner in Elephant and Castle. [P5]
Heads of Agreement: The record of concluded negotiations with KPI III SARL and Lend Lease. [P9]
Regeneration Agreement: The agreement between the council and Lend Lease, which will be amended for the changed approach. [P9]
Equalities impact assessment: The completed assessment for the overall regeneration, to be reviewed at the planning application stage. [P16]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
Cabinet agrees to enter into agreements with Lend Lease (Elephant and Castle) Ltd and KPI III SARL to take forward the regeneration of the Elephant and Castle Shopping Centre on the principal terms set out in Appendices A and B of the closed version of the report and to vary the Elephant and Castle Regeneration Agreement to reflect the change in delivery approach as a result.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 4 pages
Recommendation
That cabinet agrees:
1. To enter into agreements with Lend Lease (Elephant and Castle) Ltd and KPI III SARL to take forward the regeneration of the Elephant and Castle Shopping Centre on the principal terms set out in Appendices A and B of the closed version of this report and to vary the Elephant and Castle Regeneration Agreement to reflect the change in delivery approach as a result.
1 BACKGROUND INFORMATION
2. At its meeting on 17 May Cabinet resolved that the council shall enter into two agreements and vary the Elephant and Castle Regeneration Agreement to reflect the change in delivery approach as a result. The agreements were
(i) With KPI III SARL (a company in which St Modwen Properties plc has a major interest) the owner of the Elephant Shopping Centre to provide for its regeneration (ii) With KPI III SARL and Lend Lease the council’s principle partner in the Elephant and Castle to co-operate to work together to bring forward the overall regeneration of the area
3. As well as approving the agreements mentioned cabinet also resolved that a report back shall be made after the conclusion of negotiations in respect of those agreements. This report is in furtherance of that resolution.
KEY ISSUES FOR CONSIDERATION
Conclusion of negotiations
4. Negotiations concluded with KPI III SARL [KPI] (a company associated to St Modwen PLC) and Lend Lease [LL] and are recorded in Heads of Agreement at Appendices A to B of the closed version of this report. Respective lawyers are currently instructed to agree the wording of the documentation to effect these agreements subject to the cabinet’s approval. Once these agreements are concluded, the Regeneration Agreement between the council and Lend Lease will be amended to reflect changes in approach.
Indicative timetable
5. The agreement will provide for the target dates set out below:
a) KPI submitting the outline planning application by 30 September 2012. b) KPI submitting a full planning application by 30 November 2014.
6. These dates are subject to achieving a satisfactory resolution of the current transport and issues relating to the tube network and northern roundabout.
7. Once the full planning application has been approved the regeneration of the centre will commence once conditions such as funding and viability have been satisfied.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.