What was decided
Cabinet approved an EU procurement to identify development partners for mixed tenure housing, commercial units and schools in Lot A. The estimated gross development value is £278,300,000 over up to five years. The report classifies this as a key decision. Report P2, P75, P175
Cabinet approved the indicative mix of 161 social rented, 83 intermediate rented and 342 market sales. The report states approximately 586 units across nine sites. Cabinet also approved six sub lots: A1 Manor Place and Braganza; A2 Civic Centre and Albion School land; A3 Southwark Park Road; A4 Cherry Garden School; A5 South Dock Marina; and A6 Beormund School and the former Bellenden School site. Report P3, P4, P35, P36, P59
Cabinet delegated Gateway 2 award decisions for lots A1 to A4 to the chief executive, in consultation with the cabinet member for regeneration and homes. Gateway 2 reports for lots A5 and A6 will go to Cabinet. Every necessary Education Consent, including section 77, must be obtained before any contract. Report P5, P6, P68, P69, P70
Why
The EU competitive procedure with negotiation was chosen because it allows early bidder selection or later limited negotiations to clarify initial bids. It is intended to widen access for small and medium developers, including those outside approved frameworks. Report P52, P53, P57, P58
Smaller packages should give small and medium developers better access and let the council select the best value for each site. They may also prevent land banking and allow more than one developer to start work in 2018. Report P39, P60
Development appraisals indicated an overall positive net capital return, and officers anticipate no net capital cost on completion. The programme has a minimum 35% affordable units overall and is expected to provide 161 social rented council homes. Report P32, P37, P157, P171, P172
What happens next
The council will publish one OJEU notice and use Procontract 3 for registrations. Bidders will complete a Standard Selection Questionnaire, be shortlisted for each lot, and then receive an Invitation to Tender, intended for all six sub lots at once. Report P63, P64
Tender evaluation will be phased by lot. Awards for lots A1 to A4 are delegated to the chief executive, while lots A5 and A6 go to Cabinet. Final scores use 70% financial and 30% quality criteria. Report P67, P68, P69, P70, P100, P115
The Housing Regeneration and Delivery Team will develop tender documents with Trowers and Hamlins. Architectural, valuation, financial, legal and joint venture support will be procured before the tender starts. Every necessary Education Consent, including section 77, must be obtained before entering any contract. Report P6, P88, P156
The money
- £278,300,000 Estimated total Gross Development Value to development partners for up to five years Report P2, P175
- £1m Programme target of one apprentice for every £1m spent Report P133
Options considered
- Chosen: OJEU procurement. The estimated value means the full Public Contract Regulations 2015 and Public Sector Directive 2014/24/EU requirements apply. The route should maximise competition and value for money. Report P51, P176
- Chosen: EU competitive procedure with negotiation. It allows early bidder selection or limited later negotiations to clarify bids. It also opens the route to developers outside approved frameworks. Report P52, P53, P57, P58
- Rejected: Greater London Authority London Development Panel framework. Previous use found a provider for Lot B but no suitable development partner for Lot A. It also restricts access to small and medium developers. Report P54, P55
- Rejected: Other existing development frameworks. They contain the same or very similar developers and would restrict access to small and medium developers. Report P55
- Rejected: Restricted procedure. It was judged not flexible enough for this procurement. Report P58
- Rejected: Competitive dialogue procedure. Its costs and bidder perceptions could deter bids. Report P58
Implications
- Financial: The council expects to contribute the land but no capital injection. Development appraisals indicate an overall positive net capital return, and officers anticipate no net capital cost on completion. Report P41, P157, P171
- Financial: The council will retain commercial units across all sites to provide higher long term revenue. The appraisals exclude grant input and planning or sales overage, and the final financial position will be clearer at award. Report P38, P158, P173
- Legal: A Development Partnership Agreement will cover all lots. Stamp Duty Land Tax at day one is charged only on the bare site, the developer will forward fund construction, and the developer will retain specified third party risks. Report P61, P62
- Legal: Redevelopment of the Beormund School site is subject to council consultation and Secretary of State Consent under Section 77 and Schedule 1 of the Academies Act 2010. Every necessary Education Consent, including section 77, must be obtained before entering any contract. Report P6, P24
- Equalities: Officers will complete an equalities impact assessment during consultation and collate a community impact statement. Consultation will include service users, internal stakeholders, affected businesses and targeted marginalised local groups. Report P117, P120, P121, P164
- Climate: All homes will have to achieve Code for Sustainable Homes Level 5, or its new equivalent. The partnership will work towards a 15% reduction rate for new council build homes by 2022. Report P142, P147, P148
- Risk: Risks include insufficient developer interest, weak employer requirements, poor viability, low competitiveness, cost control and programme slippage. Controls include early engagement, viability testing, cost ceilings, phased reporting, community engagement and planning support. All report timetable dates are indicative. Report P72, P73, P84
- Staffing: The Housing Regeneration and Delivery Team will manage contract administration and monitoring. Architectural, valuation, financial, legal and joint venture support must be procured before the tender starts. Report P152, P156
- Other: The programme is expected to deliver 586 housing units, including 161 social rented homes retained as council homes. Section 106 will cover employment and training, education, health, public realm, transport, community facilities and community safety. Report P35, P129, P130, P135
Who and where
- Southwark residents needing affordable and market homes Report P32, P35, P85
- People living, accessing or working close to the development Report P118
- Beormund Primary School pupils and Porlock Hall PRU users Report P21
- School pupils and staff affected by school reorganisation Report P21, P31
- Local businesses and suppliers Report P120, P131
- Small and medium development partners Report P39, P55, P57
- Council services and the capital programme Report P152, P173
- Groups with protected characteristics and people displaced by proposals Report P117, P121, P122
Timeline
- 21/03/2017: Gateway 1 procurement strategy approval. The report labels all timetable dates as indicative. Report P83, P84
- 31/03/2017: Publication of the OJEU notice. Report P83, P84
- 08/05/2017: Closing date for expressions of interest. Report P83, P84
- 08/06/2017: Invitation to tender. Report P83, P84
- August 2017: Closing date for return of tenders. Report P83, P84
- November/2017: Gateway 2 approval and contract award. Report P83, P84
- December/2017: Contract start, contract register entry and award notices. Report P83, P84
- June 2019: Contract completion if extension(s) are exercised. Report P83, P84
Plain English for the jargon
- Gateway 1: Approval of the procurement strategy before tender documentation and advertising. [P2] [P82] [P83]
- Gateway 2: Approval point for the contract award report for each lot. [P67] [P83]
- OJEU: Official Journal of the European Union, where the contract notice will be published. [P63] [P93]
- GDV: Gross Development Value, the estimated value of the development programme. [D] [P2]
- Development Partnership Agreement: The proposed contract under which the council contributes land and the developer funds construction. [P61] [P62] [P92]
- Section 77: Secretary of State Consent required for disposal of school playing field land and redevelopment of the Beormund School site. [P24] [P73] [P165]
- SME: Small and medium size developer that could otherwise be excluded by existing frameworks. [P39] [P55]
- Education Consent: Necessary consent, including section 77, required before a contract is entered. [P6]