Resolved
Decision To advise the Joint Committee of the financial position to month 8 of the 2009/10 financial year, and ensure the Phase B procurement is adequately resourced.
South London Waste Partnership Joint Committee decided this item on Wednesday 13 January 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision To advise the Joint Committee of the financial position to month 8 of the 2009/10 financial year, and ensure the Phase B procurement is adequately resourced.
The Joint Committee is asked to:
1. Note the latest 2009/10 expenditure position
Reason for action proposed To advise the Joint Committee of the financial position to month 8 of the 2009/10 financial year, and ensure the Phase B procurement is adequately resourced.
INTRODUCTION
1. This is the third of the regular budget monitoring statement for the 2009/10 financial year. The information presented covers the period up to the end of November 2009 (month 8).
2. The Partnership has 2 main tasks that need to be undertaken in the current financial year. These are:
Phase B contract procurement and associated work Contract management of Phase A contracts
Table 1 - Budget Monitoring 2009/10 – Month 8
Item Spend to Proposed Budget Variance – end of Outturn 2009/10 budget to November Spend £000’s anticipated 2009 £000’s outturn £000’s PWC Consortium 168 500 500 0 Project Director 93 150 150 0 Project and Contract 0 40 115 (75) Management Other Procurement Costs – 23 99 100 (1) (Sites, JMWMS & Planning) Audit of 2008/9 Accounts 0 12 0 12 Communications 0 64 0 64 TOTAL 284 865 865 0 COST PER BOROUGH 71 216.25 216.25 0
3. At the meeting of the Joint Committee on 2 December 2009, approval was given to establish the two fixed term posts required to support the Phase B process. These Agenda Item 5 Page 26
posts are currently being recruited to and any progress will be reported verbally to the Committee.
4. The Management Group is satisfied that the costs in the current year are being managed appropriately and the Management Group will regularly scrutinise the expenditure and ensure that it remains within budget.
JOINT WASTE DPD
5. The budget for the joint waste DPD is held separately, but is included below for information. The budget is discussed regularly at the Planning Officer Working Group meetings and is taken to the Joint Waste DPD Member Group every 6 months. An annual budget for the Waste DPD was originally agreed by all boroughs’ decision making bodies at the start of the project, in the summer 2007. At that time, the budget was agreed as £120,000 (i.e. £30,000 per borough) for three years.
6. The anticipated 2009/10 year end cost is £45k per borough which represents an increase of £15,000 on top of the current level of contribution.
7. The revised budget for this and future years will be discussed at the Planning Officer Working Group in January 2010.
Table 2 – Joint Waste DPD Budget 2009/10
Item Spend to Proposed Budget Variance – end of outturn 2009/10 budget to November spend £000’s anticipated 2009 outturn £000’s Project Manager 38 55 55 0 Training & Expenses 0 5 3 2 Consultancy Support 44 82 30 52 Communications 22 38 32 6 TOTAL 104 180 120 60 COST PER BOROUGH 26 45 30 15
Background papers –
Author – Al Mawji, Royal Borough of Kingston Upon Thames [email protected]
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget Monitoring Report January 10Report | 71 KB | DownloadRead as text |
Follow South London Waste Partnership Joint Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Nov 2025 | Minutes of the previous meetingThat the minutes of the previous meeting held on 11 June 2025 were approved as a correct record. | Approved | Open |
| 26 Nov 2025 | Communications and Engagement UpdateTo Note the contents of this report and comment on any aspects of communications and engagement activities relating t... | Noted | Open |
| 26 Nov 2025 | Contracts Performance ReportNote the latest position with the ERF residual waste treatment contract related to the recent CEMS calibration issue ... | Noted | Open |
| 26 Nov 2025 | Budget Update 2025/26To note the content of this report. | Noted | Open |
| 26 Nov 2025 | Proposed Management Budget 2026/27To approve the 2026/27 SLWP Budget of £707k. This represents an annual cost of £177k per borough and an increase of j... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.