CONTRACT A PERFORMANCE MONITORING

Decided Committee 1 paper

South London Waste Partnership Joint Committee decided this item on Wednesday 13 January 2010. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision To enable the Joint Committee to comment on the performance of the three contracts.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to South London Waste Partnership Joint Committee

Summary

The current position on the following three contracts is set out in this report: • Contract 1: Landfill and Transportation (Viridor Waste Management Ltd) • Contract 2: Management of Household Reuse & Recycling Centres (Environmental Waste Controls) • Contract 3:Materials Recycling Services, Composting, and Additional Treatment Services (Viridor Waste Management Ltd)

Recommendations

The Joint Committee is asked to note the contents of this report and to comment on any aspects of the performance of the Partnership’s Phase A contracts.

Reason for recommendation

To enable the Joint Committee to comment on the performance of these contracts.

INTRODUCTION

1. This report details the performance relating to the three Phase A contracts awarded by the Partnership during 2008.

Contract 1 - Landfill and Transportation (Viridor Waste Management Ltd)

2. The contract is operating effectively with municipal solid waste now delivered to Viridor’s Beddington Farmlands Landfill by Croydon, Kingston, Merton and Sutton local authorities.

3. Viridor have now been granted planning permission for the temporary waste tipping pad and the opening of the facility on bank and public holidays.

4. Viridor are now waiting for a decision from Sutton Council in respect of the out of normal operating hours opening for receiving specific types of waste from the partnership. The planning application was originally submitted in August 2009.

5. Arrangements are in place with Viridor to receive the Partnership’s deliveries of municipal waste during the forthcoming Christmas & New Year period.

6. There are no performance or complaints issues relating to this contract, however there is an on-going issue with weighbridge discrepancies which is being investigated by Kingston Internal Audit team with the support of Partnership offices and Viridor representatives. Agenda Item 6 Page 28

Contract 2 - Management of Household Reuse & Recycling Centres (Environmental Waste Controls)

7. EWC continue to perform well in respect of the diversion of household waste from landfill for reuse and recycling.

8. Table 1 shows the recycling diversion rates for each of the seven HRRC’S during the period August to November 2009, the year 1 contract target for each facility, actual performance of each facility prior to the commencement of the contract with EWC, and the first contract year performance for each facility. These rates exclude inert material delivered to the facilities.

9. The recycling performance as shown in Table 1 is exceeding the contract targets, and the recycling rate submitted by EWC within their tender rates for each facility.

Table 1

Facility Pre contract Year 1 First Aug 09 Sept 09 Oct 09 Nov 09 performance target contra ct year perfor m-ance Croydon Factory 41% 45% 75.25% 75.84% 76.30% 74.99% 73.99% Lane Fishers 52% 60% 73.84% 75.11% 75.62% 78.15% 74.39% Farm Purley Oaks 58% 70% 84.08% 84.12% 85.95% 83.85% 86.25% Kingston Villiers 45% 47% 74.93% 76.91% 78.15% 77.10% 74.16% Road Merton Garth Road 32% 34% 69.24% 70.40% 73.45% 74.08% 72.95% Weir Road 85% 90% 98.16% 98.98% 98.90% 98.80% 98.63% Sutton Kimpton 34% 45% 74.59% 75.77% 76.74% 77.35% 76.86% Park Way **

Partnership 49.57% 55.86% 78.58% 79.59% 80.73% 77.54% 76.47% average (2009) Partnership n/a n/a n/a n/a 72.12% 74.27% 74.79% average (2008)

** Performance period summarised as February to October 2009.

EWC were prepared for handling all recyclable material and waste delivered to the seven sites during the recent Christmas and New Year period. Page 29 Agenda Item 6

10. All complaints received by SLWP officers regarding the seven HRRC’S are brought to the attention of EWC management, who have on each occasion investigated the complaints promptly and effectively.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Phase A contract performance: January 2010Report 98 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Sutton

Search all
  1. CONTRACT A PERFORMANCE MONITORINGThis decision
  2. Contracts Performance ReportNoted
  3. Contract Performance ReportNoted
  4. Waste Collections and Street Cleansing Contract performanceNoted
  5. Update on the publication of performance data relating to the waste collection and street cleaning contract with VeoliaNoted
  6. Update on the publication of performance data relating to the waste collection and street cleaning contract with VeoliaNoted

More from Sutton South London Waste Partnership Joint Committee

All decisions
MeetingDecisionOutcome
26 Nov 2025 Minutes of the previous meetingThat the minutes of the previous meeting held on 11 June 2025 were approved as a correct record. Approved Open
26 Nov 2025 Communications and Engagement UpdateTo Note the contents of this report and comment on any aspects of communications and engagement activities relating t... Noted Open
26 Nov 2025 Contracts Performance ReportNote the latest position with the ERF residual waste treatment contract related to the recent CEMS calibration issue ... Noted Open
26 Nov 2025 Budget Update 2025/26To note the content of this report. Noted Open
26 Nov 2025 Proposed Management Budget 2026/27To approve the 2026/27 SLWP Budget of £707k. This represents an annual cost of £177k per borough and an increase of j... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies