Swale Joint Transportation Board, Monday 4 March 2019 at 5.30pm

Highways Work Programme

Noted Committee 1 paper

Swale Joint Transportation Board noted this item on Monday 4 March 2019. Below is the council's own wording, with the papers it was decided on.

Item537

Resolved

(1) That the report be noted.
Word for word from the decision Swale published for this meeting. Source: democracy.swale.gov.uk

Follow this further

Built from Swale's papers

What the report saysPro

Report to Swale Joint Transportation Board

To: Swale Joint Transportation Board

By: KCC Highways and Transportation

Date: 4th March 2019

Subject: Highway Works Programme 2018/19

Classification: Information Only

Summary: This report updates Members on the identified schemes approved for construction in 2018/19

1. Introduction

This report provides an update and summarises schemes that have been programmed for delivery in 2018/19

Footway and Carriageway Improvement Schemes – see Appendix A

Drainage Repairs & Improvements – see Appendix B

Street Lighting – see Appendix C

Traffic Systems – see Appendix D

Developer Funded Works – see Appendix E

Transportation and Safety Schemes – see Appendix F

Public Rights of Way – see Appendix G

Bridge Works – see Appendix H

Member Highway Fund – see Appendix I

Pothole Blitz – see Appendix J

Conclusion

1. This report is for Members information.

Contact Officers:

The following contact officers can be contacted on 03000 418181

Kirstie Williams Highway Manager (Mid) Alan Blackburn Swale District Manager Alan Casson Road & Footway Asset Manager Earl Bourner Drainage and Structures Manager Sue Kinsella Street Lighting Manager Toby Butler Intelligent Transport Systems Manager Andrew Hutchinson Transportation, PROW and Safety Schemes Nick Abrahams Economic Development Appendix A – Footway and Carriageway Improvement Schemes

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.

Machine Resurfacing – Contact Officer Byron Lovell

Road Name Parish Extent of Works Current Status

To be reviewed once Spirit of A2 St Michael’s Rd Sittingbourne Forum to Crown Quay Lane Sittingbourne works are completed Millennium Way to junction with To be programmed A250 High St Sheerness Victoria Street from April 2019

A250 Millennium 50m each approach to High To be programmed Sheerness Way Street from April 2019 The Billet PH for a distance of To be programmed A2 London Road Sittingbourne 100m easterly towards from April 2019 Sittingbourne Town Centre Between Adelaide Drive and To be programmed A2 London Road Sittingbourne Lydbrook Close from April 2019

Footway Improvement - Contact Officer Neil Tree

Extent and Description of Road Name Parish Current Status Works Weather permitting the work is Entire length. Wickham Close Newington programmed for 25th (Footway Protection Treatment) February 2019

Surface Treatments - Contact Officer Clive Lambourne

Micro Surfacing

Road Name Parish Extent of Works Current Status

The Street Oare Oare Road To Cole Gates Road Completed

Selling Road Selling Monica Close to Sondes Court Completed

Between Kettle Hill Road and Otterden Road Eastling Completed Kettle Hill Road (Eastling) Extents Through junction to Halstow Lane Upchurch Completed Twinney Lane

From Grove Road to Selling Perry Wood Selling Completed Road

Between Napleton Road and South Road Faversham Completed Bridge Road

From Stockers Hill to Bottles Cheney Hill Rodmersham Completed Lane

From Belnor Avenue to Stickfast Parsonage Lane Bobbing Completed Lane

Hartlip M2 bridge to Old House Lane Completed Bull Lane

Bank Street Faversham Whole Length Postponed until 2019

Surface Treatments - Contact Officer Clive Lambourne

Surface Dressing

Road Name Parish Extent of Works Current Status

Ashford Road Sheldwich New House Lane to Salters Lane Completed

Whitstable Road (& Graveney Whole Length Completed Graveney Road)

Bagshill Road to Shottenden Ashford Road Badlesmere Completed Road

School Lane Borden Whole Length Completed

Selling Road Selling Vicarage Lane to Crouch Lane Completed

Plough Road Minister on Sea Whole Length Completed Appendix B – Drainage Repairs & Improvements

Drainage Repairs & Improvements - Contact Officer Katie Lewis

Road Parish Description of Works Current Status Name Re-shape driveway cleanses the Committed passed to Tunstall Swale system. Install new gullies at the contractor Half term Road junction with Woodstock road school break

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highways Work ProgrammeReport 146 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 27 attended
SA
Councillor Sarah AldridgeGuest, in attendance
MB
Councillor Mike BaldockCommittee Member, present
CB
Councillor Cameron BeartCommittee Member, present
AB
Alan BlackburnOfficer, in attendance
MB
Monique BonneyGuest, in attendance
AB
Mr Andy BoothKent County Councillor, present
AB
Mr Andrew BowlesChair, present
PB
Paul BrandOfficer, in attendance
RC
Roger ClarkGuest, in attendance
DC
Councillor Derek ConwayCommittee Member, present
CF
Colin FinchOfficer, in attendance
SG
Mrs Sue GentKent County Councillor, apologies

All 27 on the meeting page

On this subject at Swale

Search all
  1. Highways Work ProgrammeThis decision
  2. Highways Work ProgrammeNoted
  3. Highways Work ProgrammeNoted
  4. Highways Work ProgrammeNoted
  5. Verbal update from National Highways on the M2 Junction 5 Stockbury WorksNoted
  6. Highways Work ProgrammeNoted

More from Swale Swale Joint Transportation Board

All decisions
MeetingDecisionOutcome
29 Jun 2026 Presentation from Network Rail(1) That it be recommended to the relevant parties at Swale Borough Council and Kent County Council that a joint work... Decided Open
29 Jun 2026 Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructure(1) That the report be noted. Noted Open
6 Oct 2025 Highways Work Programme(1) That the report be noted. Noted Open
6 Oct 2025 Progress Update Report - including updates on Grovehurt Road junction Sittingbourne and Key Street junction Sittingbourne(1) That the update report and verbal updates be noted. Noted Open