NEWTON ABBOT - 17/00618/MAJ Western House, 10 Howton Road, Outline - erection of 32 dwellings including incidental open space, landscaping and an area of strategic green infrastructure (all matters reserved for future consideration)
RefusedPlanning1 paper
Planning Committee refused this item on Tuesday 20 February 2018. Below is the council's own wording, with the papers it was decided on.
Resolved Permission refused for the following reason: 1. Road unsuitable for level of traffic generated by 32 dwellings. (15 votes for and 2 against) Note: The refusal of the application was contrary to the advice of the Business Manager. The Committee considered the application unacceptable for reasons set out above.
Word for word from the decision Teignbridge published for this meeting.Source: democracy.teignbridge.gov.uk
Subject to the completion of a Section 106 Agreement to provide: 20% affordable housing 5% custom build plots Financial contribution towards provision of Community facilities (£1,617 per dwelling) Financial contribution towards provision of Employment development (£3,179 per dwelling) Financial contribution towards provision of Main road through NA1 (£5,565 per dwelling) Financial contribution towards provision of Green Infrastructure (£2,235 per dwelling) or on-site provision Financial contribution towards provision of walking and cycling links within the NA1 allocation (£3,383 per dwelling) Traffic Regulation Order for the closure of Howton Road to through traffic prior to commencement (including contribution of £5,000 towards this)
PERMISSION BE GRANTED subject to the following conditions:
1. Requirement for reserved matters submissions 2. Timing of submission of reserved matters 3. Compliance with approved plans/documents 4. No dwelling to be occupied until junction of Howton Road and Mile End Road has been improved 5. No development to take place until further intrusive phase 2 contaminated land assessment has been submitted to and approved in writing by the Local Planning Authority 6. Submission of a Tree Constraints Plan 7. A 20 metre exclusion zone to be retained around badger sett on site 8. Submission of Construction Management Plan prior to commencement of development 9. Prior to commencement, detailed design of proposed temporary and permanent surface water drainage system, including adoption and maintenance arrangements and avoidance of surface water draining onto highway, to be submitted for approval by the Local Planning Authority. Design to be informed by a programme of percolation tests and a groundwater monitoring programme undertaken over a period of 12 months 10. Compliance testing in respect to noise levels will be undertaken on completion of the development 11. Compliance with the required mitigation as set out in pages 14-16 of the approved Ecological Report (Ecological Surveys Ltd: Bat activity Report, dated November 2016 including provision of a 20 metres exclusion zone 12. Submission of Landscape Ecological Management Plan 13. Submission of a Construction Ecological Management Plan 14. Prior to submission of reserved matters, a lighting modelling assessment shall be carried out and details submitted to the Local Planning Authority for approval 15. Ongoing lighting regulation, with no external lighting shall be installed unless otherwise agreed with the Local Planning Authority
3. DESCRIPTION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEWTON ABBOT: 17/00618/MAJ Western House, 10 Howton Road, Outline: erection of 32 dwellings including incidental open space, landscaping and an area of strategic green infrastructure (all matters reserved for future consideration)Report
325gNEWTON ABBOT - 17/00618/MAJ Western House, 10 Howton Road, Outline - erection of 32 dwellings including incidental open space, landscaping and an area of strategic green infrastructure (all matters reserved for future consideration)This decision
NEWTON ABBOT - 17/00618/MAJ Western House, 10 Howton Road, Outline - erection of 32 dwellings including incidental open space, landscaping and an area of strategic green infrastructure (all matters reserved for future consideration)This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.