That Cabinet (excluding Councillor Johnson): 1. Approved a £2.2m budget for the expansion of Benyon Primary School to be funded from the School’s Basic Need capital funding 2019/20 2. Approved a budget of up to £1m for works to be undertaken to enable construction of additional classrooms in current secondary schools. 3. Progressed the procurement process to secure design and construction for the expansion of Benyon Primary School to take forward the proposed schemes. Councillor Johnson stated that now recommendations had been agreed, in which he had not voted , he felt the school was excellent and the staff worked very hard. He felt that the school had an excellent reputation in Ockendon and local residents cared about its wellbeing Reason for Decision – as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
HUGGINS BROMAGE FERGUSON LTD CHARTERED ARCHITECTS AND CDM COORDINATORS
EXTENSIONS AND ALTERATIONS TO CREATE A TWO FORM ENTRY PRIMARY SCHOOL , BENYON PRIMARY SCHOOL, TYSSEN PLACE, SOUTH OCKENDON, RM156PG
APPROXIMATE COSTING – EXTENSION ONLY Approximate costing calculation based on extension floor area based on SPONS Price book rates.
Excluding external works (front and rear), Canopy, Kitchen, fitted furniture allowance per classroom, Internal alterations to existing building and Contingency/ Provisional Sums.
Gross floor area = 731 m2
SPONS rate £1600 per m2
731 x 1600 = £1,169,600.00;
Say £1,200,000.00 (plus vat if applicable)
As a cross-check on the ‘ Approximate’ costs of the extension, we have also calculated the building cost for building elements.
ELEMENTAL COSTING – EXTENSION ONLY ITEM DESCRIPTION COST
17. Mechanical and electrical £200,000.00 Installations SUB-TOTAL £1,067,380.00
Elemental cost; £1,067,380.00
Contractors profit and overhead 12% of £1,067,380.00 = £128,085.60
£1,067,380.00 +£128,085.60 = £1,195,465.60
Say £1,200,000.00 (plus vat if applicable)
OTHER COSTS (NOT INCLUDED IN EXTENSION COST)
Including contractors profit and overhead
ITEM DESCRIPTION COST
1. Rear Playground, fire tender £120,000.00 road, paving , fencing and drainage 2. Front car park, fencing paving and £160,000.00 service upgrades 3. Entrance canopy and foundations £40,000.00
4. Kitchen upgrade/ fitted furniture £100,000.00
5. Internal alterations (existing £100,000.00 building) SUB TOTAL £520,000.00
PROVISIONAL SUMS/ CONTINGENCY (NOT INCLUDED IN EXTENSION COST) Including contractors profit and overhead
3. Provisional Sums/ £190,00.00 Contingency GRAND TOTAL £1,910,000.00
APPROXIMATE PROJECT COST
£1,910,000.00 (plus vat if applicable) Appendix 1
HUGGINS BROMAGE FERGUSON LTD.
OUTLINE PROJECT PROGRAMME 5584 EXTENSIONS AND ALTERATIONS TO CREATE A TWO FORM ENTRY PRIMARY SCHOOL , BENYON PRIMARY SCHOOL, TYSSEN PLACE, SOUTH OCKENDON, RM15 6PG STAGE COMPLETED BY
First draft of proposal drawings Friday 7th December 2018
Revised layout and budget costing Tuesday 18th December 2018
Pre-planning application based on floor plan ? Monday 31st January 2019
Consultant tender invitation Friday 11th January 2019
Consultant tender returns Friday 8th of February 2019
Consultant tender evaluation and consultant Friday 1st of March 2019 appointment. Plan and elevation drawings finalised Friday 29th March 2019
Survey existing building, check existing plans Friday 12th April 2019
Prepare Planning application documents and submit a Friday 12th April 2019 planning application (Including sub-consultant reports/ surveys etc. Planning application decision (10 weeks application Friday 21st June 2019 period) delegated powers decision assumed. Discharge of planning conditions – prior to start of works Monday 18th November 2019
Prepare building regulation drawings and submit a Friday 19th July 2019 building regulation application
Preparation of Pre-contract H&S plan and specification Friday 2nd August 2019 ready to invite tenders PQQ process and contractor selection (3 weeks) Friday 23rd August 2019
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.