School Capital Programme Update 2019/20 (Decision 110508)

Approved Executive 2 papers

Cabinet approved this item on Wednesday 13 March 2019. Below is the council's own wording, with the papers it was decided on.

Item118

Resolved

That Cabinet (excluding Councillor Johnson): 1. Approved a £2.2m budget for the expansion of Benyon Primary School to be funded from the School’s Basic Need capital funding 2019/20 2. Approved a budget of up to £1m for works to be undertaken to enable construction of additional classrooms in current secondary schools. 3. Progressed the procurement process to secure design and construction for the expansion of Benyon Primary School to take forward the proposed schemes. Councillor Johnson stated that now recommendations had been agreed, in which he had not voted , he felt the school was excellent and the staff worked very hard. He felt that the school had an excellent reputation in Ockendon and local residents cared about its wellbeing Reason for Decision – as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Appendix 1

HUGGINS BROMAGE FERGUSON LTD CHARTERED ARCHITECTS AND CDM COORDINATORS

EXTENSIONS AND ALTERATIONS TO CREATE A TWO FORM ENTRY PRIMARY SCHOOL , BENYON PRIMARY SCHOOL, TYSSEN PLACE, SOUTH OCKENDON, RM156PG

APPROXIMATE COSTING – EXTENSION ONLY Approximate costing calculation based on extension floor area based on SPONS Price book rates.

Excluding external works (front and rear), Canopy, Kitchen, fitted furniture allowance per classroom, Internal alterations to existing building and Contingency/ Provisional Sums.

Gross floor area = 731 m2

SPONS rate £1600 per m2

731 x 1600 = £1,169,600.00;

Say £1,200,000.00 (plus vat if applicable)

As a cross-check on the ‘ Approximate’ costs of the extension, we have also calculated the building cost for building elements.

ELEMENTAL COSTING – EXTENSION ONLY ITEM DESCRIPTION COST

1. Strip/ Clear the site £30,000.00

2. Foundation. £80,000.00

3. Site set up and management £100,000.00

4. Brickwork/ Blockwork £90,000.000

5. Windows and Doors. £40,000.00

6. Milbank ground Floor £43,800.00 (complete) 7. Steelwork/ steel frame £80,000.00

8. Floor Plank Roof £58,480.00

9. Flat Roof (complete) £73,100.00

0. Internal Walls £20,000.00

1. Internal Doors £22,000.00

2. Plastering £50,000.00 Appendix 1 13. Toilets & Cubicles £40,000.00

14. Ceiling £50,000.00

15. Floor £60,000.00

16. Decorations £30,000.00

17. Mechanical and electrical £200,000.00 Installations SUB-TOTAL £1,067,380.00

Elemental cost; £1,067,380.00

Contractors profit and overhead 12% of £1,067,380.00 = £128,085.60

£1,067,380.00 +£128,085.60 = £1,195,465.60

Say £1,200,000.00 (plus vat if applicable)

OTHER COSTS (NOT INCLUDED IN EXTENSION COST)

Including contractors profit and overhead

ITEM DESCRIPTION COST

1. Rear Playground, fire tender £120,000.00 road, paving , fencing and drainage 2. Front car park, fencing paving and £160,000.00 service upgrades 3. Entrance canopy and foundations £40,000.00

4. Kitchen upgrade/ fitted furniture £100,000.00

5. Internal alterations (existing £100,000.00 building) SUB TOTAL £520,000.00

PROVISIONAL SUMS/ CONTINGENCY (NOT INCLUDED IN EXTENSION COST) Including contractors profit and overhead

ITEM DESCRIPTION COST

1. Contingency £80,000.00

2. Building regulation amendments £10,000.00

3. Service Upgrades £20,000.00

4. Consequential upgrades £30,000.00 Appendix 1 5. Asbestos removal £20,000.00

6.. Additional groundworks £20,000.00

7. IT wiring £10,000.00

SUB TOTAL £190,000.00

COST SUMMARY ITEM DESCRIPTION COST

1. Extension costs £1,200,000.00

2. Other costs £520,000.00

3. Provisional Sums/ £190,00.00 Contingency GRAND TOTAL £1,910,000.00

APPROXIMATE PROJECT COST

£1,910,000.00 (plus vat if applicable) Appendix 1

HUGGINS BROMAGE FERGUSON LTD.

OUTLINE PROJECT PROGRAMME 5584 EXTENSIONS AND ALTERATIONS TO CREATE A TWO FORM ENTRY PRIMARY SCHOOL , BENYON PRIMARY SCHOOL, TYSSEN PLACE, SOUTH OCKENDON, RM15 6PG STAGE COMPLETED BY

First draft of proposal drawings Friday 7th December 2018

Revised layout and budget costing Tuesday 18th December 2018

Pre-planning application based on floor plan ? Monday 31st January 2019

Consultant tender invitation Friday 11th January 2019

Consultant tender returns Friday 8th of February 2019

Consultant tender evaluation and consultant Friday 1st of March 2019 appointment. Plan and elevation drawings finalised Friday 29th March 2019

Survey existing building, check existing plans Friday 12th April 2019

Prepare Planning application documents and submit a Friday 12th April 2019 planning application (Including sub-consultant reports/ surveys etc. Planning application decision (10 weeks application Friday 21st June 2019 period) delegated powers decision assumed. Discharge of planning conditions – prior to start of works Monday 18th November 2019

Prepare building regulation drawings and submit a Friday 19th July 2019 building regulation application

Preparation of Pre-contract H&S plan and specification Friday 2nd August 2019 ready to invite tenders PQQ process and contractor selection (3 weeks) Friday 23rd August 2019

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
School Capital Programme Update: Appendix 1: Huggins Brommage Ferguson Feasibility Study for Benyon PrimaryAppendix 99 KB DownloadRead as text
PDF
School Capital Programme Update 2019/20 (Decision 110508)Decisions 82 KB Download

At this meeting

Whole meeting

Who was there

6 of 9 attended
RG
Councillor Rob GledhillChair, present
SH
Councillor Shane HebbDeputy Chair, apologies
GC
Councillor Gary CollinsCommittee Member, present
MC
Councillor Mark CoxshallCommittee Member, apologies
JH
Councillor James HaldenCommittee Member, apologies
DH
Councillor Deborah HuelinCommittee Member, present
BJ
Councillor Barry JohnsonCommittee Member, present
SL
Councillor Susan LittleCommittee Member, present
AW
Councillor Aaron WatkinsCommittee Member, present

On this subject at Thurrock

Search all
  1. School Capital Programme Update 2019/20 (Decision 110508)This decision
  2. School Capital Programme Update 2023/24 (Decision: 110714)Approved
  3. School Capital Programme Update 2023/24Approved
  4. School Capital Programme Update 2022/23 (Decision: 110647)Approved
  5. School Capital Programme Update 2022/23Approved
  6. School Capital Programme Update 2020/21 (Decision: 110545)Approved

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies