That Cabinet: 1. Agreed the strategy and approach to progress the scheme as set out in the report. 2. Gave approval to commence a tendering process for a main works contractor for both Phase 1 and Phase 2. 3. Delegated to the Director of Place, in consultation with the Portfolio Holder for Regeneration, authority to award the subsequent main works contract subject to compliance with the Council’s procurement rules and terms and conditions being approved by the Section 151 Officer and the Monitoring Officer Reason for decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
The Council has funding for a station and transport interchange improvement project at Stanford-le-Hope. The project will involve replacing the old outdated station with new passenger facilities including toilets and retail space more in keeping with modern traveller expectations. A new transport hub will be created on the opposite side of London Road allowing bus access, taxi rank, cycle parking and improved station car parking. This project is being delivered by the Council together with c2c, and working with key stakeholders such as Network Rail, SELEP and London Gateway.
The project has been through a pause and review process with a clear focus on deliverability and affordability within the budget envelope. This new strategy provides a high-level overview of our objectives and requests authority from Cabinet, given the likely contract value, to tender the works contracts and delegated authority to appoint a works contractor.
1. Recommendation(s)
That Cabinet:
1.1Agrees the strategy and approach to progress the scheme as set out in this report;
1.2Gives approval to commence a tendering process for a main works contractor for both Phase 1 and Phase 2; and
1.3Delegates to the Director of Place, in consultation with the Portfolio Holder for Regeneration, authority to award the subsequent main works contract subject to compliance with the Council’s procurement rules and terms and conditions being approved by the Section 151 Officer and the Monitoring Officer.
2. Introduction and Background
2.1The Stanford Le Hope Station Phase 1 Redevelopment scheme involves the construction of new, light and modern station buildings with improved operational features and refreshment outlet to improve the passenger experience, a new footbridge and accessible lifts. The design will incorporate improved safety features, low maintenance materials and construction with anti-vandalism features, some platform widening for significantly improved passenger safety, and modern passenger information systems. Phase two includes a Transport Hub, incorporating a bus turnaround facility, passenger drop-off points and cycle parking and recharging points, improved car parking for all types of vehicles and a Taxi rank and drop off points.
2.2The location of the station in Stanford Le Hope can be prone to congestion at peak times due to its location and the site being constrained by Mucking Creek, London Road, and the existing railway crossing. However, this new station and transport hub concept, based on the purchase of the additional land on the opposite side of London Road (former Daybreak Windows site), is designed to relieve much of this congestion. Developed as part of the travel plan for London Gateway DP World, the design will facilitate easy and convenient “park and ride” services for commuters and general travellers to and from London and the surrounding area. It is also hoped this facility will help satisfy the demand for parking in Stanford Le Hope generally.
2.3Works were started in March 2019 to demolish the existing station building to provide access into the remainder of the site for the delivery of the works.
2.4A new project team has been assembled and an innovative new and revised strategy has been produced based on the additional space provided by the procurement of the Daybreak Windows site. In addition, some creative design has enabled the team to maximise the use of existing foundations to mitigate the need for expensive ground works. The project will progress in two phases:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.