Stanford-le-Hope Interchange Project

Decided Planning 1 paper

Planning, Transport, Regeneration Overview and Scrutiny Committee decided this item on Tuesday 6 December 2022. Below is the council's own wording, with the papers it was decided on.

Item25

Resolved

That the Planning, Transport and Regeneration Overview and Scrutiny Committee notes and comments on the information provided relating to development & delivery of the Stanford-le-Hope Interchange project. That the Planning, Transport and Regeneration Overview and Scrutiny Committee propose a Working Group be formed to investigate the S tanford-le-Hope Interchange Project.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Planning, Transport, Regeneration Overview and Scrutiny Committee

Executive summary

This report is provided at the Chair’s request to provide Members with information on progress in delivering the Stanford-Le-Hope Railway Station and Transport Hub project. The report sets the key issues that impacting on the delivery of the scheme, provides an update on the current procurement of the main contractor and funding and budget situation.

As part of the Thurrock Council’s draft Improvement and Recovery Plan 2022, this project along with others that make up the Council Capital Programme will be subject to a review as part of the objective to achieve long term financial sustainability. This review will examine the current project costings, funding and the selected procurement and project management options.

1. Recommendation(s)

1.1That the Planning, Transport and Regeneration Overview and Scrutiny Committee notes and comments on the information provided relating to development & delivery of the Stanford-le-Hope Interchange project.

2. Introduction and Background

2.1For the Members benefits the main aims of the Project are set out below:

• Develop an interchange that will connect bus, rail, cycle, taxi, and pedestrian modes of transport at Stanford le Hope station. • Expand capacity at Stanford le Hope Station. • Implement a package of works that meets the requirements of travel plans for London Gateway and unlocks the next phase of development at London Gateway. • Provide improvements to public transport infrastructure and service reliability to new housing developments and to the major employment growth sites at London Gateway/Coryton. • Help curb traffic growth and minimise growth in transport emissions in the area through this new transport interchange.

2.2There are several stakeholders involved in the project including UK Power Networks, SELEP, Train Operating Company -c2c, Network Rail and the DP World.

2.3The Stanford Le Hope Interchange scheme has been subject to significant design changes since it was originally promoted and costed using a design and build contract. This followed an assessment of the original design which identified significant project complications and financial risks. This was linked initially to a technical design solution that sought to deliver the infrastructure requirements of the scheme on a relatively small land area of land, in order not to build over the adjacent Mucking Creek and keep the station building away from neighbouring residential properties. Costs also increased as a result of significant changes being made to the design of the station following completion of site investigations (floodplain), consideration of environmental constraints and the practicalities of construction. During this period the original station buildings were demolished and temporary structures for ticketing and staff accommodation were put in place.

2.4Following concerns over the proposed design and the associated costs a project review terminated the design and build contract and an alternative procurement approach was adopted. The total projects cost incurred up to this change of delivery strategy (31/03/2020) stage were £6,534,411.

2.5The revised delivery strategy involved the Council undertaking the management of the design phase, using a team of external consultants with MACE providing the direct project management of the project. To manage the delivery of this complex scheme the new delivery strategy proposed to split the project into two stages: Phase 1 the delivery of a replacement train station and; Phase 2 covering the wider facilities including parking on the footprint to the north of London Road.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Stanford-le-Hope Interchange ProjectReport 146 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 10 attended
AA
Councillor Alex AndersonChair, present
JA
Councillor John AllenVice-Chair, absent
RG
Councillor Rob GledhillCommittee Member, apologies
TK
Councillor Tom KellyCommittee Member, present
KR
Councillor Kairen RaperCommittee Member, present
LW
Councillor Lee WatsonCommittee Member, present
SH
Councillor Shane HebbSubstitute, present as substitute
MK
Mat KielyOfficer, expected
KR
Keith RumseyOfficer, expected
NT
Navtej TungOfficer, expected

On this subject at Thurrock

Search all
  1. Stanford-le-Hope Interchange ProjectThis decision
  2. Stanford-le-Hope Station OptionsAgreed
  3. Stanford-le-Hope (SLH) Station/ Interchange Update Report (Decision: 110674)Noted
  4. Stanford-le-Hope (SLH) Station / Interchange UpdateNoted
  5. Stanford-le-Hope Interchange ReportDecided
  6. Stanford-le-Hope Interchange ReportNoted

More from Thurrock Planning, Transport, Regeneration Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
21 Feb 2024 ITB Capital Programme 2024/251.1 That the Committee provide comments on the 2024/25 Integrated Transport Block capital programme allocations and p... Agreed Open
21 Feb 2024 Tilbury and Grays Towns Fund Update - to follow1.1 That the Committee notes the proposed changes to the original programmes and the progress on delivering the Tilbu... Decided Open
21 Feb 2024 Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen... Decided Open
17 Oct 2023 Thurrock Scheduled Ancient Monuments: Assessment of Settings - April 2023That the Planning, Transportation and Regeneration Overview and Scrutiny Committee note and provide comment on the Th... Decided Open
17 Oct 2023 East Tilbury (Bata Village) & Corringham Conservation Areas Character Appraisal and Management Plans - April 2023That the Planning, Transport and Regeneration Overview and Scrutiny Committee notes and comments on the East Tilbury ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies