Planning, Transport, Regeneration Overview and Scrutiny Committee decided this item on Tuesday 18 October 2022. Below is the council's own wording, with the papers it was decided on.
RESOLVED t hat the Planning, Transport and Regeneration Overview and Scrutiny Committee: 1. Notes and comments on the information provided relating to the Stanford-le-Hope Interchange project 2. Officers provide the requested information by Members at the next meeting
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Planning, Transport, Regeneration Overview and Scrutiny Committee
Executive summary
This report is provided at the Chair’s request to inform Members of progress on the Stanford-Le-Hope Railway Station and Transport Hub project.
1. Recommendation(s)
1.1That the Planning, Transport and Regeneration Overview and Scrutiny Committee notes and comments on the information provided relating to the Stanford-le-Hope Interchange project.
2. Introduction and Background
2.1This project consists of the construction of new station buildings with footbridge and lifts, passenger information system, bus turnaround facility, passenger drop-off points and cycle parking.
2.2There are several stakeholders involved in the project including UK Power Networks, SELEP, Train Operating Company -c2c, Network Rail and the Port of London Authority. A Development Agreement with c2c, who are the principal landowner will be in place.
2.3Since the last update to the PTR Overview & Scrutiny Committee in July 2022, there has been progress in resolving Station design issues but continued delay in executing the Station D&C contract. 3. Issues, Options and Analysis of Options
Progress:
3.1The Project scope comprises: • Phase 1 - the construction of new station buildings with footbridge and lifts, widened platform, passenger information system and enhanced facilities, • Phase 2 - bus turnaround facility, passenger drop-off points and cycle parking.
Phase 1 is now in the Detail Design & Construction/Implementation Stage Phase 2 is in the Concept Design Stage
3.2SLH Phase 1 (New Station) contract award for the station to the successful contractor - Volker Fitzpatrick Limited was made in early March. To ensure mobilisation as quickly as possible, a Letter of Intent (LoI) was issued pending formal contract execution.
3.3The planned Contract with VFL is NEC4 Engineering and Construction Contract June 2017 main Option A. This is a fixed priced contract with an activity schedule where the risk of carrying out the work at the agreed prices is largely borne by the contractor. Execution of the contract has been delayed due to continued concerns regarding cost inflation, national supply chain for manufactured goods issues, scope change risk with NR and c2c as design approvers and rail possession availability impacting the contractors risk liability.
3.4VFL have offered alternative means of moving into contract which TC has rejected as they are outside the procurement rules. TC and VFL have now developed a proposal that allows the parties to execute the contract and manage the risks step by step and incrementally within the existing contract terms and conditions. It is now planned to execute the contract by 31 October 2022 subject to further clarifications of detail and agreement on matters such as the treatment of inflation and possession availability.
Alternative procurement strategies are being considered and developed concurrently.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.