Resolved
RESOLVED That the Standards and Audit Committee noted and commented on the report content.
Standards and Audit Committee noted this item on Tuesday 24 November 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the Standards and Audit Committee noted and commented on the report content.
This report is provided at the Committee’s request to have a quarterly update on the A13 project. This report and future reports will focus on the latest progress in delivery of the scheme, any changes in the agreed programme and any changes in the out turn forecast.
1. Recommendation(s)
1.1That the Standards and Audit Committee notes and comments on the report content.
2. Introduction and Background
2.1This project involves widening the A13 Stanford le Hope by-pass from 2 to 3 lanes in both directions, from the junction with the A128 (Orsett Cock roundabout) in the west to the A1014 (The Manorway) in the east and replacing four bridges. Once the project is completed, there will be a continuous three-lane carriageway from the M25 to Stanford le Hope, reducing congestion and resultant pollution, improving journey times and supporting further economic growth not only in Thurrock but across the whole south Essex corridor.
2.2There have been a number of issues with the project which has resulted in delays in the delivery and an increase in costs, the detail of which has been discussed and considered in previous reports to both this Committee and PTR O&S.
2.3This report and future reports to this committee will focus on progress in delivery and provide an update on out turn forecast and programme.
3. Issues, Options and Analysis of Options
Progress
3.1In recent weeks, the concrete bridge decks at Orsett East and West and Saffron Bridge have been poured with additional work completed to pour the parapets and diaphragms at Orsett also. Drainage work is progressing well, with the installation of the vortex separator chambers at the pond, continued installation of filter drain, carrier drain and cross-carriageway drainage and the ongoing removal of the old, redundant drainage system. A major milestone was reached in late October, with the commencement of the road surfacing with more to follow in the coming months.
3.2More than £8.2 million has been invested locally, by using regional suppliers and businesses based within 10 miles of the project – supporting the local economy at a time when this is needed more than ever.
3.3The project has employed a student engineer, who is currently studying towards a Civil Engineering degree. She is completing a ‘year out’ placement as part of her studies. Three additional individuals continue their studies in the construction management and commercial management areas, as part of their Kier Apprenticeship Degrees.
3.4The site continues to operate in accordance with the industry guidelines for working safely in COVID-19, with only one positive case recorded (occurring during a period of annual leave) across the project since the start of the pandemic. The individual followed self-isolation instructions and has now recovered fully and is back at work.
3.5Alongside the plastic screens which had previously been installed, a policy has been introduced to ensure that face coverings are worn whilst walking around the office. In addition, a thermal scanner is available to enable staff to check their own temperature on arrival and the site has been registered with the NHS Covid test and trace app, and all visitors are asked to scan the barcode.
Programme
3.6The current accepted programme has an anticipated planned completion date within the currently published period of Autumn/Winter 2021.
3.7The team continues to challenge the construction programme to look at efficiencies to see if completion can be brought forward.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
A13 Widening ProjectReport | 147 KB | DownloadRead as text |
Follow Standards and Audit Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2024 | Internal Audit Charter 20241.1 That the Standards and Audit Committee approve the (Appendix 1) and the Chair of the Standards and Audit Committe... | Approved | Open |
| 21 Mar 2024 | Internal Audit Protocol- Item to follow1.1 That the Standards and Audit Committee agree that the Internal Audit Protocol provides the Council and the Intern... | Agreed | Open |
| 21 Mar 2024 | Committee on Standards in Public Life Update1.1 Note the content of report of the Committee on Public Life’s report Leading in Practice (Appendix 1), and conside... | Noted | Open |
| 29 Feb 2024 | Internal Audit Progress Report1.1 Note the progress to 11 January 2024 against the Audit Plan 2023/24 as documented in Appendix 1. 1.2 Consider the... | Noted | Open |
| 29 Feb 2024 | Future Arrangements for the Standards and Audit Committee1.1 To consider the options set out in this report and recommend a preferred option for inclusion in the Annual Counc... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.