Resolved
That the Planning, Transportation and Regeneration Overview and Scrutiny Committee noted and commented on the report content.
Planning, Transport, Regeneration Overview and Scrutiny Committee noted this item on Tuesday 5 October 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Planning, Transportation and Regeneration Overview and Scrutiny Committee noted and commented on the report content.
This report is provided at the Committee’s request to have a quarterly update on the A13 project. This report and future reports will focus on the latest progress in delivery of the scheme, any changes in the agreed programme and any changes in the out turn forecast.
1. Recommendation(s)
1.1That the Planning, Transportation and Regeneration Overview and Scrutiny Committee notes and comments on the report content.
2. Introduction and Background
2.1This project involves widening the A13 Stanford le Hope by-pass from 2 to 3 lanes in both directions, from the junction with the A128 (Orsett Cock roundabout) in the west to the A1014 (The Manorway) in the east and replacing four bridges. Once the project is completed, there will be a continuous three-lane carriageway from the M25 to Stanford le Hope, reducing congestion and resultant pollution, improving journey times and supporting further economic growth not only in Thurrock but across the whole south Essex corridor.
2.2There have been a number of issues with the project which has resulted in delays in the delivery and an increase in costs, the detail of which has been discussed and considered in previous reports to both this Committee and Standards and Audit Committee.
2.3This report and future reports to this committee will focus on progress in delivery and provide an update on out turn forecast and programme.
3. Issues, Options and Analysis of Options
Progress
3.1Progress report to end of July 2021
3.2Since the last report progress on site has been very good.
3.3Horndon and Saffron bridges have been completed and opened for use.
3.4The drainage and other earthworks on the verges were completed and the traffic was switched to the verges to allow access to the Central Reservation. Works to install drainage and the concrete vehicle restraint barrier has progressed ahead of programme.
3.5Both new bridges at the Orsett Cock roundabout were completed and traffic has been switched on to them allowing the demolition of the 2 old bridges. Works are currently underway to realign the roundabout and finish works in the area.
3.6More than £12 million has been invested locally, by using regional suppliers and businesses based within 10 miles of the project – supporting the local economy at a time when this is needed more than ever.
3.7There has now been more than 850 000 hours since the last RIDDOR and more than 1.3 million hours worked on the project in total. The Project Accident Incident Rate is currently 0 which is a significant achievement.
Programme
3.8The current accepted programme has an anticipated planned completion date of January 2022.
Budget
3.9The team worked closely with Aecom and Kier during the first 6 months of 2021 to produce, agree and sign a Deed of Variation and a Settlement Agreement. These agreements encompass all of the risks and outstanding Compensation Events up until the end of 2020 (including Covid in 2020) and provide a revised Target Cost for the scheme. These agreements are considered to be hugely beneficial for the Council in that they reduce risk and provide more programme and cost certainty. . 4. Reasons for Recommendation
4.1To respond to the Committee’s request for quarterly updates on the A13 project.
5. Consultation (including Overview and Scrutiny, if applicable)
5.1A communication plan has been prepared and agreed.
5.2Member briefing sessions are held periodically at the A13 Site Offices and provide an opportunity for Members to receive a presentation from the contractor and raise issues on behalf of local residents.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
A13 Widening ProjectReport | 142 KB | DownloadRead as text |
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Feb 2024 | ITB Capital Programme 2024/251.1 That the Committee provide comments on the 2024/25 Integrated Transport Block capital programme allocations and p... | Agreed | Open |
| 21 Feb 2024 | Tilbury and Grays Towns Fund Update - to follow1.1 That the Committee notes the proposed changes to the original programmes and the progress on delivering the Tilbu... | Decided | Open |
| 21 Feb 2024 | Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen... | Decided | Open |
| 17 Oct 2023 | Thurrock Scheduled Ancient Monuments: Assessment of Settings - April 2023That the Planning, Transportation and Regeneration Overview and Scrutiny Committee note and provide comment on the Th... | Decided | Open |
| 17 Oct 2023 | East Tilbury (Bata Village) & Corringham Conservation Areas Character Appraisal and Management Plans - April 2023That the Planning, Transport and Regeneration Overview and Scrutiny Committee notes and comments on the East Tilbury ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.