This report is provided at the Committee’s request to have a quarterly update on the A13 project. This report and future reports will focus on the latest progress in delivery of the scheme, any changes in the agreed programme and any changes in the out turn forecast.
1. Recommendation(s)
1.1That the Standards and Audit Committee notes and comments on the report content.
2. Introduction and Background
2.1This project involves widening the A13 Stanford le Hope by-pass from 2 to 3 lanes in both directions, from the junction with the A128 (Orsett Cock roundabout) in the west to the A1014 (The Manorway) in the east and replacing four bridges. Once the project is completed, there will be a continuous three-lane carriageway from the M25 to Stanford le Hope, reducing congestion and resultant pollution, improving journey times and supporting further economic growth.
2.2There have been a number of issues with the project which has resulted in delays in the delivery and an increase in costs, the detail of which has been discussed and considered in previous reports to both this Committee and PTR O&S.
2.3This report and future reports to this committee will focus on progress in delivery and provide an update on out turn forecast and programme.
3. Issues, Options and Analysis of Options
Progress
3.1The site continues to operate in accordance with the industry guidelines for working safely in Covid 19, with no positive cases recorded across the project. Plastic screens have been installed in the offices, to enable more office staff to return, alongside additional hygiene facilities and cleaning resources.
3.2Significant visible progress made over the course of the summer so far, with the successful installation of Saffron Gardens Bridge and the two new bridges at the Orsett junction. Work is underway to construct the surfaces and walls of each structure. Earthworks, drainage and other works continue to progress at the same time.
3.3Almost £7.5million has been invested locally, by using regional suppliers and businesses based within 10 miles of the project – supporting the local economy at a time when this is needed more than ever.
3.4The project has employed summer placement civil engineering students – currently studying at Loughborough University – helping to foster the next generation of civil engineers.
3.5Considerate Constructors Scheme assessment took place in July. We scored 43/50 and were rated ‘Excellent’ by the independent review body.
Programme
3.6Under the terms of the NEC 3 contract in place, there are four limited provisions which would enable the Council to reject changes to the programme. In rejecting the contractors programme, the Council has to give the justification and reasons why.
3.7The four provisions are:
The Contractors plans are not practicable It does not show information required by the contract It does not represent the Contractors plans realistically It does not comply with the works information.
3.8The current accepted programme No 34 has an anticipated planned completion date within the currently published period of Autumn/Winter 2021. Again it is likely that there will be further delays as a consequence of Covid 19 but as the pandemic is still a live issue, it is difficult to understand the impact at this stage.
Budget Forecast
3.9Members will recall at the last meeting, the anticipated out turn forecast including contingency was £114,675,000.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
A13 Widening ProjectReport | 146 KB | DownloadRead as text |
Follow Standards and Audit Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2024 | Internal Audit Charter 20241.1 That the Standards and Audit Committee approve the (Appendix 1) and the Chair of the Standards and Audit Committe... | Approved | Open |
| 21 Mar 2024 | Internal Audit Protocol- Item to follow1.1 That the Standards and Audit Committee agree that the Internal Audit Protocol provides the Council and the Intern... | Agreed | Open |
| 21 Mar 2024 | Committee on Standards in Public Life Update1.1 Note the content of report of the Committee on Public Life’s report Leading in Practice (Appendix 1), and conside... | Noted | Open |
| 29 Feb 2024 | Internal Audit Progress Report1.1 Note the progress to 11 January 2024 against the Audit Plan 2023/24 as documented in Appendix 1. 1.2 Consider the... | Noted | Open |
| 29 Feb 2024 | Future Arrangements for the Standards and Audit Committee1.1 To consider the options set out in this report and recommend a preferred option for inclusion in the Annual Counc... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies