Resolved
RESOLVED t hat the Planning, Transportation and Regeneration Overview and Scrutiny Committee: 1. Notes and comments on the report content. 2. Officers provide the requested information by Members at the next meeting
Planning, Transport, Regeneration Overview and Scrutiny Committee decided this item on Tuesday 18 October 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED t hat the Planning, Transportation and Regeneration Overview and Scrutiny Committee: 1. Notes and comments on the report content. 2. Officers provide the requested information by Members at the next meeting
This report is provided at the Committee’s request for an update on the A13 project. This report and future reports will focus on the latest progress in delivery of the project, any changes to the agreed programme or significant events.
1. Recommendation(s)
1.1That the Planning, Transportation and Regeneration Overview and Scrutiny Committee notes and comments on the report content.
2. Introduction and Background
2.1The project scope involves widening the A13 Stanford le Hope by-pass from 2 to 3 lanes in both directions, from the junction with the A128 (Orsett Cock roundabout) in the west to the A1014 (The Manorway) in the east and replacing four bridges. On completion of the project there will be a continuous three-lane carriageway from the M25 to Stanford le Hope, reducing congestion and resultant pollution, improving journey times and supporting further economic growth not only in Thurrock but across the whole south Essex corridor.
2.2There have been several issues on the project which has resulted in delays in the delivery and an increase in costs, the detail of which has been discussed and considered in previous reports to both this Committee and Standards and Audit Committee. 2.3 This report and future reports to this committee will focus on progress in delivery.
3. Issues, Options and Analysis of Options
Progress
3.1Progress on site in 2022 has been good with the road open with all Lanes running on the main carriageway at 50mph on 2nd May. Orsett Cock Roundabout was opened at 30mph until the traffic lights were commissioned on 26th May and currently operates at 50mph. The road is running very well, and the main benefits of the project are being realised by creating additional capacity to reduce congestion, improve journey times, facilitate growth and improve access to key strategic economic hubs.
SIGNIFICANT MILESTONES IN 2022 ITEM DATE
Environmental Barrier Complete May 13-22 All Lanes Running A13 Mainline May 2-22 Orsett Cock roundabout traffic signals operational May 26-22 Pond Liner installation complete Aug 5-22
REMAINING MILESTONES Balancing Pond completion Nov-22 Seasonal planting complete Nov-22 Defects rectification Nov-22 Full street lighting Commissioned Jan-23
• All 3 lanes in both directions running very well. Some complaints/enquiries re when national speed limit will apply.
• Handover to TC Operations and Maintenance continues.
• All lanes running at 70mph requires all lighting commissioned. This requires replacement of power feeder pillars and connections for the street lighting at the eastern extent of the works. This is now forecast for Jan 23 due to national supply chain delays for manufactured equipment. Mitigations being explored including rolling speed restriction. Derogation to standards to run at 70mph examined – but tight geometry has ruled this out for safety reasons in past but is being re-evaluated & could be accepted by TBC on a risk basis? • Environment Agency Abstraction license granted for Balancing Pond in July after over 12 months delay. Balancing Pond works progressing very well with excavation complete, liner installed, topsoil being placed and planting progressing. Headwalls under construction also. 3.2 More than £13 million has been invested locally, by using regional suppliers and businesses based within 10 miles of the project – supporting the local economy at a time when this is needed more than ever.
Safety
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
A13 Widening ProjectReport | 3.9 MB | DownloadRead as text |
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Feb 2024 | ITB Capital Programme 2024/251.1 That the Committee provide comments on the 2024/25 Integrated Transport Block capital programme allocations and p... | Agreed | Open |
| 21 Feb 2024 | Tilbury and Grays Towns Fund Update - to follow1.1 That the Committee notes the proposed changes to the original programmes and the progress on delivering the Tilbu... | Decided | Open |
| 21 Feb 2024 | Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen... | Decided | Open |
| 17 Oct 2023 | Thurrock Scheduled Ancient Monuments: Assessment of Settings - April 2023That the Planning, Transportation and Regeneration Overview and Scrutiny Committee note and provide comment on the Th... | Decided | Open |
| 17 Oct 2023 | East Tilbury (Bata Village) & Corringham Conservation Areas Character Appraisal and Management Plans - April 2023That the Planning, Transport and Regeneration Overview and Scrutiny Committee notes and comments on the East Tilbury ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.