Resolved
RESOLVED That Standards and Audit Committee noted and commented on the report content.
Standards and Audit Committee noted this item on Thursday 11 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That Standards and Audit Committee noted and commented on the report content.
This report is provided at the Committee’s request to have a quarterly update on the SLH project. This report and future reports will focus on the latest progress in delivery of the scheme, any changes in the agreed programme and any changes in the out turn forecast
1. Recommendation(s)
1.1That the Standards and Audit Committee notes and comments on the report content.
2. Introduction and Background
2.1This scheme involves the construction of new station buildings with footbridge and lifts, passenger information system, bus turnaround facility, passenger drop-off points and cycle parking.
2.2There are a number of stakeholders involved in the scheme including UK Power Networks, C2C, Network Rail and the Port of London Authority and it will be delivered under a Development Agreement with C2C, who are the principal land owner.
2.3A similar report was considered by Planning, Transport and Regeneration Overview and Scrutiny Committee on 9 February 2021
3. Issues, Options and Analysis of Options
Progress
3.1The Concept Design for both the station and the transport hub have been completed and passed Inter Disciplinary Review with very positive feedback. The planning application for the phase 1 station was considered at Planning Committee on 11 February and deferred for the following reasons:
Members wanted to see the supporting facilities for the train station, in particular, they wanted to see what provision would be made for car parking, cycle storage, EV charging and bus turnaround facilities;
Members wanted to see the plans for the phase 2 supporting facilities alongside the current application for the station after it had gone out for tender so Members could be comfortable that both schemes could be delivered as one complete project.
3.2In response to matters raised at the Planning Committee, there were many reasons for splitting the project into phases including enabling the scheme to come forward within the current programme for the station site, to phase construction making it cheaper and simpler for the contractor to deliver given the constraints of the station site and to manage budget and costs.
3.3The concept design for the Phase 2 Transport Hub has been through final development discussions and was subject to a workshop in November to select a preferred configuration acceptable to the key Stakeholders including London Gateway DPW and c2c. A submission for pre-application planning review was made on 10 February and feedback on that is awaited prior to working up a detailed application for planning permission for the Phase 2 site in the coming months.
3.4Information was sent out to 11 potential Principal Contractors within an existing Thurrock Council Framework Agreement. Of the 11, only 4 held the appropriate Network rail accreditation and 3 of those submitted Expressions of Interest, sufficient to carry out a meaningful tender. The tender documentation was progressed and ready to be issued the week commencing 22 February 2021. As a consequence of the deferral of the planning application for Phase 1, this has to be reconsidered. The intention was to let a design and build contract on a fixed price basis to ensure costs are effectively controlled and managed. As a consequence of the deferral, the risk and options of going to tender without the certainty of planning needs to be fully considered. From the lessons learned on the A13 there are concerns about going to market without the right level of detail as this affects risk and cost certainty. Further there are potential delays to the programme as a consequence of the decision to defer.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Stanford Le Hope Transport ProjectsReport | 145 KB | DownloadRead as text |
Follow Standards and Audit Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2024 | Internal Audit Charter 20241.1 That the Standards and Audit Committee approve the (Appendix 1) and the Chair of the Standards and Audit Committe... | Approved | Open |
| 21 Mar 2024 | Internal Audit Protocol- Item to follow1.1 That the Standards and Audit Committee agree that the Internal Audit Protocol provides the Council and the Intern... | Agreed | Open |
| 21 Mar 2024 | Committee on Standards in Public Life Update1.1 Note the content of report of the Committee on Public Life’s report Leading in Practice (Appendix 1), and conside... | Noted | Open |
| 29 Feb 2024 | Internal Audit Progress Report1.1 Note the progress to 11 January 2024 against the Audit Plan 2023/24 as documented in Appendix 1. 1.2 Consider the... | Noted | Open |
| 29 Feb 2024 | Future Arrangements for the Standards and Audit Committee1.1 To consider the options set out in this report and recommend a preferred option for inclusion in the Annual Counc... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.