Planning, Transport, Regeneration Overview and Scrutiny Committee noted this item on Tuesday 5 October 2021. Below is the council's own wording, with the papers it was decided on.
Planning, Transport and Regeneration Overview and Scrutiny Committee were requested to: 1.1 Note the content contained within the report and; 1.2 To provide Cabinet with any relevant observations or recommendations to aid their consideration of this proposed procurement.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Planning, Transport, Regeneration Overview and Scrutiny Committee
Executive summary
The Council is required to purchase vehicle fuel, in order to operate our front line services. That includes Refuse, Highways Maintenance, Environment and Grounds Maintenance Services, Enforcement Services, Welfare and Youth Services, ICT and Facilities Management. The current fuel contract was procured in 2016 through the Crown Commercial Services Framework. This was a 4 year contract that was due to end on 1st March 2020, but with the option of extending for a further 2 years. We are now 17 months into this extension.
1. Recommendation(s)
Planning, Transport and Regeneration Overview and Scrutiny Committee are requested to:
1.1Note the content contained within the report and;
1.2To provide Cabinet with any relevant observations or recommendations to aid their consideration of this proposed procurement.
2. Introduction and Background
2.1Our current fleet consists of 156 vehicles, supporting services such as, but not limited to, refuse collection, highways maintenance, street sweeping and grounds maintenance, In addition there are approximately 500 items of plant equipment, including tractors, ride on mowers and hand held power tools. All vehicles and equipment run on standard diesel or petrol and where necessary, ad blue which is a fuel additive required by some vehicle types.
3. Issues, Options and Analysis of Options
3.1Fuel for all the above currently costs Thurrock Council approximately £900,000 per year.
3.2There are a number of fuel card suppliers available, some of which are linked with different fuel suppliers and in some cases restricted to certain geographical regions. The Tender process will determine those that enable the most effective and efficient service for the day to day front line operations delivered by the Council.
3.3Discounted rates for the fuel are not offered. The benefit of tendering a contract is to obtain the best price for the management of the card services, such as accurate purchase records and efficient weekly invoicing. The back office costs to the fuel card suppliers can vary which will make some suppliers more or less competitive than others.
3.4There are no hidden or unexpected charges with using fuel cards. Each supplier will have an initial charge per card supplied and beyond that there are no charges payable other than for the fuel that is purchased. A contract length of 10 years is therefore preferable to avoid repetition with procurement.
3.5An alternative method of procuring fuel for large fleets is to bulk buy the fuel and store within the operational depot. This option is not currently viable due to the limited space available in the current depot site. This option also incurs additional expenditure for purchasing / installing the necessary tanks and equipment. The purchase price of the fuel however, would be the same. Therefore, there are no benefits in adopting / moving towards this as a fuel procurement method.
3.6Whilst there is a long term plan to move away from fossil fuels, this will take a number of years as this will involve numerous external factors along with funding and analyses of options of alternatively powered vehicles available that are fit for each operational use. Until the council is at the point of being able to support alternative fuels or powertrains, fossil fuels in the main, are currently the only option.
Reasons for recommendation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.