Resolved
That the Planning Transport Regeneration Overview and Scrutiny Committee noted and commented on the information provided relating to the Stanford le Hope Interchange project.
Planning, Transport, Regeneration Overview and Scrutiny Committee noted this item on Tuesday 5 October 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Planning Transport Regeneration Overview and Scrutiny Committee noted and commented on the information provided relating to the Stanford le Hope Interchange project.
This report is provided at the Chair’s request in order to inform Members of an update on the SLH scheme.
1. Recommendation(s)
1.1That the Planning Transport Regeneration Overview and Scrutiny Committee notes and comments on the information provided relating to the Stanford le Hope Interchange project.
2. Introduction and Background
2.1This scheme involves the construction of new station buildings with footbridge and lifts, passenger information system, bus turnaround facility, passenger drop-off points and cycle parking.
2.2There are a number of stakeholders involved in the scheme including UK Power Networks, C2C, Network Rail and the Port of London Authority and it will be delivered under a Development Agreement with c2c, who are the principal land owner.
2.3Since the last update to the PTR Overview & Scrutiny Committee in December 2020, further progress has been made to move the project forward in preparation for on-site delivery.
3. Issues, Options and Analysis of Options
Progress:
3.1The Concept Design for the station is now fully developed and has been reviewed and the principles accepted by the key stakeholders. The transport hub is currently progressing a review to align objectives with planning aspirations and place-making opportunities. The planning application for the phase 1 station was submitted and received full planning approval in July 2021.
3.2The concept design for the Phase 2 Transport Hub is undergoing further investigation and pre-planning advice. Development will be subject to further workshops with Planners and developers over the next month to select a preferred configuration acceptable to the key Stakeholders.
3.3Invitations to tender were sent out to 19 potential Principal Contractors within an existing Thurrock Council Framework Agreement. Of the 19, only 8 held the appropriate Network rail accreditation and 4 of those submitted Expressions of Interest, sufficient to carry out a meaningful tender. It is anticipated that the Invitation to Tender to the 4 Companies will be issued on 17 September 2021.
3.4The project steering group is continuing to meet on a monthly basis, to share information and ideas and obtain feedback on progress to ensure this infrastructure is coming forward with the agreement of stakeholders and local residents. So far, all the feedback has been very positive.
Budget
3.5High level “estimated project” cost evaluation exercises have been carried out at two “checkpoints” through the design process, once when the full concept was agreed and a further check for pre-tender approval, to give further certainty and to give some indicative numbers in support of the tender evaluation process. It is proposed to carry out a further check, using independent estimators to carry out a pricing exercise in parallel with the tender, to provide a benchmark against which to evaluate the tender submissions.
Programme
3.6A detailed programme has been developed to reflect the revised baseline and is currently being maintained to track the time required to deliver the scheme including a fully compliant tender process. This includes the preparation of tender documentation, prequalification of bidders, the tender process, through to tender evaluation and award.
3.7Subject to the procurement process, it is anticipated that Phase 1 of the works will be delivered first with the Phase 2 works following in succession with the
opportunity to award this work as a Variation Order to the successful Contractor/designer.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Stanford-le-Hope Interchange ReportReport | 142 KB | DownloadRead as text |
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Feb 2024 | ITB Capital Programme 2024/251.1 That the Committee provide comments on the 2024/25 Integrated Transport Block capital programme allocations and p... | Agreed | Open |
| 21 Feb 2024 | Tilbury and Grays Towns Fund Update - to follow1.1 That the Committee notes the proposed changes to the original programmes and the progress on delivering the Tilbu... | Decided | Open |
| 21 Feb 2024 | Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen... | Decided | Open |
| 17 Oct 2023 | Thurrock Scheduled Ancient Monuments: Assessment of Settings - April 2023That the Planning, Transportation and Regeneration Overview and Scrutiny Committee note and provide comment on the Th... | Decided | Open |
| 17 Oct 2023 | East Tilbury (Bata Village) & Corringham Conservation Areas Character Appraisal and Management Plans - April 2023That the Planning, Transport and Regeneration Overview and Scrutiny Committee notes and comments on the East Tilbury ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.