It was agreed that all budgetary matters would be considered in detail at the subsequent Budget meeting of the Cabinet on 13 February 2014. RECOMMENDED: That confirmation be given to the action taken in endorsing the following for consideration by the Overview and Scrutiny Committee: (1) the Capital Plan (List A) position as shown in Annex 2 to the report; (2) the amendment of List C as detailed in paragraph 1.5.1 of the report; (3) the selection for evaluation of those List C schemes shown in paragraph 1.6.3 of the report; (4) the transfer of the schemes listed in paragraph 1.7.3 of the report from List C to List B and in the case of the river wall, Wouldham scheme a specific earmarked reserve be established in the sum of £700,000 and this scheme sit outside the annual allowance of £320,000 with an implementation date for Capital Plan purposes of 2015/16; and (5) endorsement of the draft Capital Strategy, as set out at Annex 5 to the report, for adoption and publication on the Council's website.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
Report of the Director of Finance and Transformation Part 1- Public
Matters for Recommendation to Cabinet - Council Decision
1 CAPITAL PLAN REVIEW 2013/14
This report reviews the current position of the existing Capital Plan (List A), recommends new schemes for adding to List C, recommends some existing List C schemes be deleted, recommends schemes from List C for evaluation over the coming year and recommends schemes for inclusion on List B from those List C schemes selected for evaluation. Members are reminded however, that any aspirations in respect of capital schemes need to be set within the context of the significant financial challenge facing the Council.
NOTE: ANNEXES 1 to 4 TO THIS REPORT ARE CONTAINED IN A SEPARATE BOOKLET CIRCULATED WITH THE AGENDA
1.1Introduction
1.1.1 The capital plan process, as outlined below, provides a means of maintaining a pool of schemes (List C) from which schemes can be selected for evaluation and possible implementation. It also provides an opportunity to review the provisions for schemes which are already in the Capital Plan (List A).
1.1.2 A few years ago Members agreed a set of criteria to guide the inclusion of new schemes to List C (wish list) and ultimately the inclusion of schemes on List A (schemes assigned budget provision). The criteria are:
• to meet legislative requirements including health and safety obligations;
• funded from external resources; and
• generate income or reduce revenue expenditure.
1.1.3 For Members awareness, the subsequent recommendations where appropriate have regard to these criteria.
Finance,Inv&PropertyAB-C-Part 1 Public 08 January 2014 2
1.1.4 The review takes place within the context of the revenue estimates, reflecting the fact that capital schemes have an impact on revenue. Positive impacts may include potential to increase income or reduce operating costs. Negative impacts may include loss of income during construction and will include loss of investment income where the project costs are met from the Council’s resources.
1.2Capital Plan Funding
1.2.1 Members will be aware that the Council continues to face a significant financial challenge as a result of the Coalition Government’s budget deficit reduction programme which has resulted in a reduction in the financial support it can offer to local government and the current economic climate.
1.2.2 Capital expenditure is currently funded from the revenue reserve for capital schemes, grants from government and other bodies, developer contributions and from capital receipts derived from the sale of assets. The revenue reserve for capital schemes provides the main source of funding for existing and any new schemes that are introduced into the Capital Plan.
1.2.3 It is important to ensure that the revenue reserve for capital schemes can continue to fund capital expenditure at least until we reach a position where the annual contribution to the reserve matches the funding required for the replacement of our assets which deliver services as well as recurring capital expenditure.
1.2.4 In order to get to this position there is now an annual capital allowance for all other capital expenditure. Any ‘bids’ for capital schemes or discretionary capital grants are to be assessed in the context of the annual allowance. Members are reminded that in setting the budget for 2013/14 that allowance was set at £320,000. It should be noted that the Council in due course will need to borrow to fund such expenditure.
1.3Capital Plan Review Process
1.3.1 The Capital Plan consists of three main elements:
• List C is a holding list of schemes which ordinarily have not been fully worked up. List C schemes can be in two states – schemes which have been retained on List C for possible future adoption and schemes which have been selected for evaluation, effectively short-listed for adoption.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budgetary Control 2026/27 to July 2026RESOLVED : That (1) the net favourable variance of circa £66,093 as at the end of July 2026, when compared to the pro...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.