RESOLVED that the Executive considers the findings of this report and recommends to Council: 1. that a capital budget of £19.95m be allocated to deliver a low carbon new-build Cranleigh Leisure Centre, to a minimum of Passivhaus standard; 2. that officers appoint a project manager and specialist energy consultant as ... EXE 59/21
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
It is recommended that the Executive considers the findings of this report and recommends to Council:
2.1that a capital budget of £19.95m be allocated to deliver a low carbon new-build Cranleigh Leisure Centre, to a minimum of Passivhaus standard;
2.2that officers appoint a project manager and specialist energy consultant as part of the professional technical services team, to be supported by an in-house client team and to approve an associated budget of £250,000;
2.3to approve a new-build leisure centre on Village Way car park, subject to planning, (Option 1, to the north of the existing centre) as the preferred location, as set out within Annexe 1 of the report; and
2.4to ask officers to report back to members when final costs, design, preferred contractor, and precise funding arrangements are known.
Reason for the recommendations
Project background
3.1Following Council commitment to a multi-million-pound investment in leisure facilities in Cranleigh, the Sport, Leisure and Culture Consultancy (‘SLC’) were appointed to conduct an Options Appraisal to explore the alternative site options for development of a new leisure facility for Cranleigh.
3.2In March 2020 the Council put all corporate projects on hold due to the Covid-19 pandemic.
3.3In September 2021 a Feasibility Update Report was undertaken by SLC to test the conclusions from the earlier, pre-pandemic Options Appraisal. The report can be found in Exempt Annexe 1.
Leisure centre background
3.4Cranleigh Leisure Centre was built in 1969 with an expected lifespan of 40 years. The Centre was refurbished in 2009 at a total cost of £1.67m. The works did not include any structural work or the replacement of any mechanical and electrical plant or any structural work to the pool tanks.
3.5Cranleigh Leisure Centre is one of five leisure centres within the Waverley contract and runs at an annual deficit with a payment of c£150,000 p.a. paid to the contractor to operate the centre.
3.6Due to the age of the leisure centre (52 years) major maintenance and repair costs, on the mechanical plant and structure, are now unavoidable. There have been several unforeseen closures due to the failure of plant and roofing. A high risk of further issues and plant failure is likely to impose partial facility closure. The longer the delay before further investment is made, the greater the investment required to simply maintain and keep the centre open.
3.7Independent building surveys have concluded that to sustain the current building and facilities as they are (with no improvements) will cost the Council c£6m over the next 5 years. It is important to note that this maintenance work will offer no return on investment and further significant investment would be required to retain provision.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.