New contract for Damp, Mould and Condensation Prevention and Remediation Services
DecidedExecutive1 paper
AI summaryWaverley Borough Council's Executive approved awarding a £1,000,000 damp, mould and condensation prevention and remediation contract to Burton Building Contracts UK Ltd, starting 1 August 2026 for two years with extension options.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedDamp, mould and condensation prevention and remediation services
Money£1,000,000Total estimated contract value including extensions
What happens next1 August 2026 startSubject to call-in, contract to be sealed
Who it affectsCouncil housing tenantsTenants in Waverley's housing stock
What was decided
The Executive approved awarding the Damp, Mould, Condensation Prevention and Remedial Services contract to Burton Building Contracts UK Ltd for an initial two-year period, with an option to extend by up to a further two years (one year plus one year), at a total contract value of £1,000,000. Report 2.2
The contract is to commence on a prospective start date of 1 August 2026, subject to any call-in period under the Constitution, after which the contract will be sealed using the Council's common seal. Report 2.2
Why
Awarding the contract allows the Council to continue meeting its statutory obligations as a landlord under the Landlord and Tenant Act 1985, the Housing Act 2004 and the Social Housing (Regulation) Act 2023, and to mitigate health risks from damp and mould for residents. Report 1.2, 3.2, 3.3
A compliant open procurement exercise was run under Part 3, Section 20 of the Procurement Act 2023, attracting 49 expressions of interest and 13 tender submissions, of which eight bids progressed to full evaluation. Report 6.3
Failure to award the contract would leave the Council without a mechanism to deliver remediation services, exposing residents to ongoing health risks and the Council to regulatory penalties and reputational damage. Report 11.1, P40
What happens next
The Council will enter into a contract with Burton Building Contracts UK Ltd for the two-year initial term with the option to extend for a further two years (one year plus one year). Report 4.1, P10
Risks will be managed through robust contract management, including KPI monitoring, performance reviews and active oversight by the Council's housing management teams. Report 10.3, P37
The contract includes provisions to allow for transfer, variation, novation or termination when service responsibilities move to West Surrey Council on Vesting Day (1 April 2027). Report 8.4, 8.2
The money
£1,000,000 (one million pounds only) Total contract value, including extensions Report 2.2
£1,000,000.00 Estimated total contract value including extensions, funded from the Housing Revenue Account planned investment works budget Report P44, P45
Options considered
Chosen: Award the contract to Burton Building Contracts UK Ltd. Ensures service continuity, value for money, statutory compliance, and proactive management of health and housing risks; secured additional social value benefits. Report 11.2, P42
Rejected: Do nothing (do not award the contract). Would leave the Council without a remediation mechanism, exposing residents to health risks, increasing compliance risks, and likely leading to higher long-term maintenance costs and possible breach of landlord duties. Report 11.1, P40
Implications
Legal: Procurement was an above-threshold open procedure under the Procurement Act 2023 and the Council's Contract Procedure Rules; failure to address damp and mould effectively could expose the Council to legal challenge, tenant claims and regulatory enforcement. Report P48, P49
Financial: Contract value of £1,000,000 is funded from the Council's Housing Revenue Account budget for planned investment works. Report P44, P45
Risk: Primary risks are tenant health harm from damp and mould exposure and compliance risk including regulatory intervention, financial penalties, legal claims and reputational damage. Report 10.1, 10.2, P36
Climate: Preventative maintenance should extend the life of housing assets, reducing material waste and associated carbon impacts; the successful bidder also committed to social value initiatives including local recruitment. Report P60, P61
Equalities: The Public Sector Equality Duty has been considered and officers have concluded there are no equality and diversity implications arising directly from this report. Report P58
Other: The Surrey (Structural Changes) Order 2026 places duties on the Council from 10 March 2026 to Vesting Day on 1 April 2027, when functions will transfer to West Surrey Council; the contract is considered necessary and proportionate for continued service delivery through that transition. Report 8.2, 8.3, P27
Who and where
Tenants in Waverley Borough Council's housing stock, including vulnerable tenants exposed to health risks from damp and mould Report 1.2, 3.2, 6.2
West Surrey Council, as the successor authority receiving transferred functions on 1 April 2027 Report 8.2, 8.3
The Council's housing management teams, who will oversee contract delivery and performance Report 10.3, P37
Timeline
10 March 2026: Surrey (Structural Changes) Order 2026 came into effect, placing duties on the Council ahead of reorganisation Report 8.2, P27
1 August 2026: Prospective commencement date for the new contract with Burton Building Contracts UK Ltd Report 2.2
1 April 2027: Vesting Day, when Council functions transfer to West Surrey Council Report 8.2
Plain English for the jargon
HRA: Housing Revenue Account, the ring-fenced account landlords use for income and spending on council housing
CPRs: Contract Procedure Rules, the Council's internal rules governing how contracts are procured
PA23 / PA2023: Procurement Act 2023, the UK legislation governing public procurement
KPI: Key Performance Indicator, a measurable target used to monitor contract performance
Vesting Day: The date on which a new local authority formally takes on its functions, here West Surrey Council on 1 April 2027
Open Procedure: A procurement route under the Procurement Act 2023 open to all interested suppliers
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 15/25
Resolved
Resolved that t he award of the Damp, Mould, Condensation Prevention and Remedial Services contract to Burton Building Contracts UK Ltd for an initial period of two years with an option to extend by up to two years (one year + one year), with a prospective commencement dated of 1 ... EXE 15/25
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1.1The purpose of this report is to seek approval, in accordance with Waverley Borough Council’s Contract Procedure Rules (CPRs) 8.6, to award a contract for Damp, Mould, Condensation Prevention and Remedial Services to Burton Building Contracts UK Ltd for a period of two years with the option to extend for a further two years (one year + one year).
1.2Awarding this contract will enable the Council to continue to meet its statutory obligations as a landlord, proactively manage risks associated with damp and mould, and ensure safe and compliant living conditions for residents.
2 Recommendation: 2.1 That the Executive resolves to:
2.2Approve the award of the Damp, Mould, Condensation Prevention and Remedial Services contract to Burton Building Contracts UK Ltd for an initial period of two years with an option to extend by up to two years (one year + one year), with a prospective commencement dated of 1 August 2026 at a total contract value of £1,000,000 (one million pounds only).
3 Reason(s) for decision: 3.1 The decision to award the contract for Damp, Mould and Condensation Prevention and Remediation Services is based on the outcome of a compliant and competitive open procurement exercise undertaken in accordance with Part 3, Section 20 of the Procurement Act 2023. The tender process attracted strong market interest, with 49 expressions of interest and 13 tender submissions received. Following compliance assessment, eight bids progressed to full evaluation.
3.2Awarding the contract will ensure the Council can continue to meet its statutory obligations as a landlord, mitigate the significant health risks associated with damp and mould in residential properties, and provide residents with safe, compliant and well-maintained homes. Failure to secure this contract would increase the Council’s exposure
2 The award of new contract for Damp, Mould and Condensation Prevention and Remediation Services
to tenant health risks, potential regulatory penalties, and reputational damage.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.