Waverley Borough Council
Executive, Tuesday 2 June 2026 at 7.00pm

New contract for Roof Repair Services

Decided Executive 1 paper

AI summaryWaverley Borough Council Executive withdrew the item on a proposed £1,100,000 roof repair services contract before the meeting, so no award was made.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedRemoved from the agenda before the meeting
MoneyNot stated
What happens nextNot stated
Who it affectsCouncil housing tenants and stockReport covered roof repairs and replacements

What was decided

The Executive withdrew this item before the meeting, so no decision was taken on the proposed award of a roof repair services contract.

The money

  • £1,100,000 (One million one hundred thousand pounds) Proposed total contract value for roof repair services; not approved because the item was withdrawn Report 2.2, P40

Options considered

  • Not chosen: Award the contract to Cardo (South) Limited for one year, with an option to extend by up to one further year. Item withdrawn before the meeting, so the Executive did not vote on it Report 11.2, 2.2
  • Rejected: Do nothing. Report said this would risk asset deterioration, higher long-term repair costs, and non-compliance with statutory housing standards Report 11.1, 3.2

Implications

  • Financial: Report proposed funding from the Housing Revenue Account Capital Programme at a total contract value of £1,100,000. Report 2.2, P40, P41
  • Legal: Report noted obligations under the Landlord and Tenant Act 1985, the Housing Act 2004, and the Procurement Act 2023, and that the contract is above threshold. Report 3.3, P42, P43, P44
  • Equalities: Report concluded there are no equality and diversity implications arising directly from the proposed contract. Report 12.3, P52
  • Climate: Report said the works would improve thermal performance, support the EPC Band C by 2030 target, and reduce the carbon footprint of the housing stock. Report 12.4, P54, P55, P57
  • Risk: Report flagged deterioration of roofing assets, water ingress, damp, and non-compliance with the Decent Homes Standard as primary risks. Report 10.1, 10.2
  • Other: Report said the Surrey (Structural Changes) Order 2026 requires contracts to allow transfer, variation, novation, or termination when functions move to West Surrey Council on 1 April 2027. Report 8.2, 8.3, 8.4

Who and where

  • Council housing tenants Report 1.2, 6.1, 6.3
  • Waverley Borough Council housing stock Report 3.3, 6.2
  • Cardo (South) Limited, identified as Most Advantageous Tender Report 2.2, 11.2

Timeline

  • 10 March 2026: Surrey (Structural Changes) Order 2026 came into effect Report 8.2
  • 1 August 2026: Proposed commencement date for the contract (not approved) Report 2.2
  • December 2026: Decent Homes Standard target referenced in the report Report 6.3
  • 1 April 2027: Vesting Day for transfer of Waverley's functions to West Surrey Council Report 8.2, 8.3
  • 2030: Government target for social housing to achieve EPC Band C Report 3.3, 6.3

Plain English for the jargon

  • Most Advantageous Tender (MAT): The bidder with the highest overall evaluation score in a procurement.
  • Open Procedure: A procurement route open to all interested bidders, used here under the Procurement Act 2023.
  • Housing Revenue Account (HRA) Capital Programme: The ring-fenced account councils use for capital spending on their own housing stock.
  • Decent Homes Standard: Statutory minimum condition standard for social housing.
  • EPC Band C: An Energy Performance Certificate rating of 69 to 80, a government target for social housing by 2030.
  • Novation: Transferring contractual rights and obligations to a third party.
  • West Surrey Council: The new unitary authority set to take over Waverley's functions from 1 April 2027.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 14/25

Resolved

This item was withdrawn prior to the meeting
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1.1The purpose of this report is to seek approval, in accordance with Waverley Borough Council’s Contract Procedure Rules (CPRs) 8.6, to award a contract for Roof Repair Services to Cardo (South) Limited for a period of one year with the option to extend for a further one year.

1.2Awarding this contract will enable the Council to maintain the structural integrity, safety, and energy performance of its housing stock, ensure compliance with statutory housing standards, and respond effectively to resident priorities regarding weathertight and energy-efficient homes.

2 Recommendation: 2.1 That the Executive resolves to:

2.2Approve the award of the Roof Repair and Replacement Services contract to Cardo (South) Limited for an initial period of one year with an option to extend by up to one additional year, with a prospective commencement date of 1 August 2026 at a total contract value of £1,100,000 (One million one hundred thousand pounds).

3 Reason(s) for decision: 3.1 The decision to award the contract is based on the outcome of a compliant and competitive open procurement exercise undertaken in accordance with Part 3, Section 20 of the Procurement Act 2023. The tender process attracted strong market interest, with 61 expressions of interest and 15 tender submissions received. Following evaluation, Cardo (South) Limited achieved the highest overall score and was identified as the Most Advantageous Tender (MAT).

3.2Awarding the contract will ensure the Council can effectively maintain and improve the condition of its housing stock. Roofing works are essential to ensuring homes remain weathertight, safe, and energy efficient. Failure to secure this contract would increase the risk of property deterioration, higher long-term repair costs, and negative impacts on resident wellbeing.

2 The award of new contract for Roof Repair Services

3.3The Council has statutory obligations to maintain its housing stock under the Landlord and Tenant Act 1985 and the Housing Act 2004, including ensuring properties are free from hazards and meet the Decent Homes Standard. In addition, government targets require all social housing to achieve an EPC rating of Band C by 2030. Procuring a specialist roofing contractor is therefore necessary to support compliance with these legal and regulatory requirements.

4 Next steps

4.1To enter into a contract with Cardo (South) Limited for Roof Repair and Replacement Services for a period of one year with the option to extend for a further one year.

5 Exemption from publication

5.1The Appendix to this report is exempt from publication by virtue of paragraph 3 of Part 1 of Schedule 12A to the Local Government Act 1972.

6 Background and Proposal

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New contract for Roof Repair ServicesReport 902 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
PF
Councillor Paul FollowsChair, present
LT
Councillor Liz Townsend BEMVice Chair, present
JC
Councillor Janet CroweCommittee Member, apologies
AD
Councillor Adam DuceCommittee Member, present
TF
Councillor Tony FaircloughCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, apologies
PR
Councillor Paul RiversCommittee Member, present

On this subject at Waverley

Search all
  1. New contract for Roof Repair ServicesThis decision
  2. New Contract for Communal Block Cleaning ServicesDecided
  3. New Contract for Roof Repair ServicesDecided
  4. New contract for Damp, Mould and Condensation Prevention and Remediation ServicesDecided
  5. New contract for the Doors and Windows Capital investment programApproved
  6. New contract for the Water Hygiene Risk Assessments and Planned Preventative Maintenance ServicesDecided

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies