AI summaryWaverley Borough Council Executive has approved a £2,950,000 Water Hygiene Remedial Works contract with SMS Environmental Limited for three years, extendable by up to two more years, delivering £1,275,000 in savings over five years.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedWater Hygiene Remedial Works to SMS Environmental Limited
Money£2,950,000Total contract value, £590,000 per annum
What happens nextEnter into contractWith SMS Environmental Limited for three years plus extension option
Who it affectsCouncil housing tenantsWater safety and Decent Homes Standard compliance
What was decided
The Executive approved the award of the Water Hygiene Remedial Works contract to SMS Environmental Limited for three years with the option to extend for a further one plus one years, at an annual value of £590,000 and a total contract value of £2,950,000. Report P4
The award supports the Strategic Priority of Decent and Affordable Homes and helps the Council meet health, safety, legal and regulatory requirements for housing. Report 7.1
The contract will include Key Performance Indicators on Carbon Net Zero reduction and Social Value, with the winning bidder's commitments written into the contract terms. Report 12.5, P39
Why
The contract is required so the Council can carry out remedial actions arising from Legionella Risk Assessments and planned preventative maintenance outcomes across its housing stock. Report P5
Without the contract, the Council would be at risk of failing to meet its statutory duties under the Landlord and Tenant Act 1985 and the Regulator of Social Housing Consumer Standards, potentially causing harm to tenants, financial loss and reputational damage. Report 10.1
The procurement delivered an annual saving of £255,000 against the advertised value of £845,000 per annum, a total saving of £1,275,000 over the five year maximum term. Report 6.3
What happens next
The Council will enter into a contract with SMS Environmental Limited for three years with the option to extend for a further one plus one years. Report 4.1, P6
Future procurement exercises will consider opportunities for collaboration with Guildford Borough Council to achieve economies of scale and pool resources. Report 8.2
The money
£590,000 Annual contract value for Water Hygiene Remedial Works Report P4, 6.3
£2,950,000 Total contract value over the maximum five year term Report P4, P28
£845,000 Originally advertised annual value before procurement Report 6.3
£255,000 Annual budget saving delivered by the procurement Report 6.3
£1,275,000 Total saving over the five year maximum term Report 6.3
Options considered
Rejected: Do nothing. Would have a financial impact on the Council and expose it to the risks set out in the report Report 11.1
Chosen: Award the contract to SMS Environmental Limited. Recommended option; meets statutory duties and delivers significant savings Report 11.2, P4
Implications
Legal: Procurement was conducted under the Fusion 21 Building Safety and Compliance Framework, Lot 4 Legionella, with advice from procurement officers to ensure compliance with the Procurement Act 2023, Public Contracts Regulations 2015 and the Council's Contract Procedure Rules. Legal Services have been instructed to draft the final form of contract. Report 12.3
Financial: Budget is available within the 2025/26 budget and is allocated in the 30 year business plan to cover the cost of this contract award. Report P29
Risk: Failure to award the contract would risk breaching statutory obligations under the Landlord and Tenant Act 1985 and the Regulator of Social Housing Consumer Standards, with potential harm to tenants, financial implications and reputational risk. Report 10.1
Equalities: The Public Sector Equality Duty has been considered and it is concluded that there are no equality and diversity implications arising directly from this report. Report P37
Climate: The contract includes Key Performance Indicators on Carbon Net Zero reduction and Social Value, and the winning bidder scored highly in these areas. Report P39
Who and where
Waverley Borough Council tenants in Council dwellings Report 7.1, 10.1
Waverley Borough Council as landlord Report 10.1
SMS Environmental Limited as the awarded contractor Report P4
Guildford Borough Council (future collaboration considered) Report 8.1, 8.2
Timeline
11 March 2025: Executive approved proceeding with the procurement Report 6.1, 16.1
14 October 2025: Executive approved the award of the contract to SMS Environmental Limited
Three years from commencement: Initial contract term, with option to extend for a further one plus one years Report P4, 4.1
Plain English for the jargon
PPM: Planned Preventative Maintenance
Legionella: Bacteria that can grow in building water systems and cause Legionnaires' disease, requiring risk assessment and control measures
KPI: Key Performance Indicator, a measurable target used to assess contract delivery
Decent Homes Standard: Government standard setting minimum conditions that social housing must meet
Fusion 21: A public sector procurement framework used to award building safety and compliance contracts
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 83/25
Resolved
RESOLVED that the award of Water Hygiene Remedial Works contract to SMS Environmental Limited for a period of three (3) years with the option to extend for a further one (1)+ one (1) years at an annual value of £590,000 and a total contract value of £2,950,000 be approved.
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1 The award of new contract for Water Hygiene Remedial Works
1.1The purpose of this report is to seek approval from the Executive for the award of the Water Hygiene Remedial Works contract.
Recommendations
That the Executive resolve to:-
2.1.1 Approve the award of Water Hygiene Remedial Works contract to SMS Environmental Limited for a period of three (3) years with the option to extend for a further one (1)+ one (1) years at an annual value of £590,000 and a total contract value of £2,950,000.
3 Reason(s) for recommendations: 3.1 The Water Hygiene Remedial Works contract is required to enable Waverly Borough Council to carry out a programme of remedial actions generated by the Legionella Risk Assessments and PPM outcomes.
4 Next steps
4.1To enter into a contract with SMS Environmental Limited for Water Hygiene Remedial Works for a period of three (3) years with the option to extend for a further one (1)+ one (1) years.
5 Exemption from publication
5.1This report is not exempt from publication.
6 Background and Proposal
6.1Approval to proceed with the procurement was given at the Executive meeting on the 11 March 2025.
6.2A procurement process followed and the recommendation is set out in the Recommendation to Award Report in Appendix 1.
2 The award of new contract for Water Hygiene Remedial Works
6.3It should be noted that the awarded sum of £590,000 per annum was significantly less than the advertised amount £845,000 per annum which was the anticipated annual value pre procurement. The procurement process therefore delivered an annual budget saving of £255,000, and a total saving of £1,275,000 over the five years.
7 Links to our Strategic Priorities
7.1This contract fully supports the Strategic Priority of Decent and Affordable Homes. It assists the Council in meeting its health and safety, legal and regulatory requirements for housing. The Council have a duty to meet the Decent Homes Standard, and the water hygiene remedial works contract is required to meet the standard and to deliver safe and decent homes to residents.
8 Opportunities for Collaboration and Local Government Reorganisation implications
8.1Opportunities of collaboration with Guildford Borough Council were considered. However, no need was identified by that Council at the time of going out to tender.
8.2Consideration will be given to every procurement exercise going forwards given the benefits of economies of scale and the pooling of resources to run a single tender exercise for both Councils.
Consultation
9.1None
10 Key Risks
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.