The status of the City Region Sustainable Transport Settlement change control application submitted to the Department for Transport set out in section 4 of the report be noted; 2. The proposal to formally re-base the CRSTS1 programme allowing fir overprogramming, ready for further consideration by WMCA Board in September 2023, working with all scheme promoters to ensure realism over scheme costs, spending and delivery profiles for schemes (this is in response to the DfT’s ‘once in a programme’ opportunity to re-baseline the programme (section 4 of the report) be noted; 3. The monitoring and evaluation reporting requirements associated with the City Region Sustainable Transport Settlement set out in Section 5 of the report be noted; 4. The programme monitoring plans set out at Section 6 of the report be noted; 5. The Quarter 4 FY22-23 progress reported at Section 7 of the report be noted; 6. The key points concerning the CRSTS1 Memorandum of Understanding updated terms and conditions that the WMCA Section 151 Officer is required to sign-off, set out at Section 8 of the report be noted; 7. The announcement from Central Government within the Spring Budget for a second round of CRSTS (‘CRSTS2’) summarised in section 9 of the report be noted and 8. The CRSTS Annual Monitoring Report for FY22-23 at Appendix 1 of the report be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Report title Update Report: City Region Sustainable Transport Settlement – Quarter 4 FY 2022-23
Portfolio Lead Councillor Bob Sleigh - Finance & Investments
Accountable Chief Anne Shaw Executive/TfWM Director (Executive Director of Transport for West Midlands) Accountable Carl Beet Employee (Head of Strategy & Intelligence) Report has been N/A considered by
Recommendation(s) for action or decision: Report for information only
The WMCA Investment Board is recommended to: Note the contents of this Report, including:
1. The status of the City Region Sustainable Transport Settlement change control application submitted to Department for Transport, set out at Section 4. 2. The proposal to formally re-base the CRSTS1 programme, allowing for over- programming, ready for further consideration by WMCA Board in September 2023, working with all scheme promoters to ensure realism over scheme costs, spending and delivery profiles for all schemes. This is in response to the DfT’s ‘once in a programme’ opportunity to re-baseline the programme (Section 4). 3. The M&E and reporting requirements associated with the City Region Sustainable Transport Settlement set out at Section 5. 4. The programme monitoring plans set out at Section 6. 5. The Quarter 4 FY22-23 progress reported at Section 7. 6. The key points concerning the CRSTS1 Memorandum of Understanding updated Terms and Conditions that the WMCA Section 151 Officer is required to sign-off, set out at Section 8. 7. The announcement from Central Government within the Spring Budget for a second round of CRSTS (‘CRSTS2’), summarised at Section 9. 8. The CRSTS Annual Monitoring Report for FY22-23 at Appendix 1. 1 Purpose 1.1 The Investment Board agreed on 14th November 2022 to receive a quarterly report on the status of the City Region Sustainable Transport Settlement (‘CRSTS’), to help set the context for any investment decisions being made by the Board. This report fulfils that requirement. 1.2 The purposes of this report are to: (a) Update Investment Board on any key events since the previous update report; (b) Outline the requirements for monitoring & evaluation (M&E) and reporting of the CRSTS programme; (c) Update Investment Board on the progress made across the programme to date; and (d) Set the context for any investment decisions being made by the Board.
2 Background 2.1 The Investment Board was established by the WMCA Board as a key element of the approvals process across the WMCA Investment Programme. 2.2 On 10 June 2022, WMCA Board approved extending the role and remit of WMCA Investment Board to cover all WMCA projects (including those within the CRSTS programme), allowing investment decisions to be made for values between £5m and £20m in line with the WMCA Single Assurance Framework. 2.3 The Investment Board considered and endorsed an enhanced Terms of Reference at its meeting on 24th July 2020. This set out an enhanced role supporting decision-making, greater post approval controls, performance management and effective delivery of monitoring & evaluation requirements. 2.4 The enhanced Terms of Reference included the following: To add conditions to any funding decision that falls within its delegated authority. Minimum conditions should specify the availability period, conditions to drawdown of funds, conditions for withdrawal of support and terms of clawback, start date and completion date for the project or programme. Where oversight of monitoring and evaluation applies to the Investment Board, to consider whether a formal review of project or programme is required, and to consider this review itself or instruct the Investment Panel to do so on its behalf.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Investment Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.