Investment Board, Monday 15 December 2025 at 10.00am

Investment Programme Update

Noted Committee 3 papers

AI summaryWest Midlands Investment Board notes no new approvals and an Investment Programme limit of £871 million, with £844.3 million committed and £730.8 million spent to 31 October 2025.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThree items noted by the Investment Board
Money£871 million affordable limitGrant funding cap since 19 March 2021
What happens nextOfficers reviewing Autumn Budget impactAssessing effect on the Investment Programme
Who it affects84 committed projects, 7 RED statusSeven schemes need completion date extensions

What was decided

The board noted that no business cases had been approved under delegated authority by officers since the last meeting. Report 4.8

The board noted the Investment Programme funding status and the current affordable limit of £871 million. Report 4.5

The board noted the regional Investment Programme delivery update. Report 4.12, 4.13

Why

The report is part of a regular series of updates on the Investment Programme, which is underpinned by the Annual Devolution Deal grant from the Department for Levelling Up, Housing and Communities. Report P29, 11.1

Approved grant funding awarded totals £844.3 million as at 31st October 2025, unchanged from the previous board meeting on 17th November 2025, with £730.8 million used on eligible expenditure. Report 4.6, 4.10, 4.8

What happens next

The Programme Assurance and Appraisal team will work with project sponsors to bring forward extension requests for the seven RED status schemes, with several Change Requests already submitted. Report 4.17, P27

Officers are reviewing the UK Government Autumn Budget statement to assess any impact on the region's Investment Programme. Report P47

The money

  • £871 million Current WMCA Investment Programme affordable limit of grant funding Report 4.5
  • £801 million Previous affordable limit before the £70 million increase in March 2021 Report 4.5
  • £844.3 million Total approved grant funding awarded and administered by WMCA as at 31st October 2025 Report 4.6
  • £730.8 million Investment Programme funding used up to 31st October 2025 against commitments Report 4.10
  • £14.95m Rail Walsall to Wolverhampton Local Enhancements Package 1, April to October 2025 Report P20
  • £9.10m Coventry City Centre South Regeneration, April to October 2025 Report P20
  • £5.98m Rail Camp Hill Line Local Enhancements Package 2, April to October 2025 Report P20

Options considered

  • Chosen: Note the report (no decision required). Report is a regular update with no recommendations requiring approval Report P29, P30

Implications

  • Financial: No direct financial implications arise from the recommendations; key financial information is in Section 4 of the report. Report 10.1
  • Legal: Funding must be used by WMCA in accordance with the terms and conditions of the Annual Devolution Deal grant from DLUHC; legal support is obtained as appropriate. Report 11.1, 11.2
  • Risk: Investment Programme delivery is subject to macro and local economic risks, but funding is capped and sponsors must manage cost escalations. Officers are reviewing the Autumn Budget for impact. Report 13.2, P47
  • Staffing: Executive Directors and Deputy Section 73 officer were consulted before clearance of the report. Report 8.1, P38
  • Other: No procurement, equalities, inclusive growth, or local authority impact implications arise from this report. Report P48, P49, P50, P51

Who and where

  • Project sponsors of the seven RED status schemes, including Accelerated Housing Delivery, Playing Pitch, Middlewood House, Rowood Drive, Balsall Common, Solihull Town Centre, and Chelmsley Wood Report P27
  • Constituent and non-constituent member local authorities of the WMCA Report 9.1, P51
  • The Department for Levelling Up, Housing and Communities as grant provider Report 11.1

Timeline

  • 20th April 2020: Investment Board endorsed enhanced Terms of Reference (approved by WMCA Board 24th July 2020) Report 4.2
  • 19th March 2021: WMCA Board approved increase to affordable limit from £801 million to £871 million Report 4.5
  • 10th June 2022: WMCA Board extended Investment Board remit to all WMCA projects including CRSTS, for values £5 million to £20 million Report 4.4
  • 27th January 2025: Change Request for UKC Infrastructure Programme approved Report P26
  • 31st October 2025: Date of programme commitment and expenditure figures cited in the report Report 4.6, 4.10
  • 17th November 2025: Previous full meeting of the WMCA Investment Board Report 4.8
  • 15th December 2025: Meeting at which this report was noted
  • 31st December 2029: Proposed new completion date for Balsall Common Multimodal Transport Package, aligning with Local Plan implementation Report P27

Plain English for the jargon

  • WMCA: West Midlands Combined Authority
  • CRSTS: City Region Sustainable Transport Settlement, a major transport funding programme
  • SAF (Single Assurance Framework): WMCA's framework for assuring investment decisions and project approvals
  • RED status: Projects whose planned completion date has passed or requires a time extension
  • OBC: Outline Business Case, a stage in the project assurance process
  • UKC Infrastructure: A programme within the WMCA Investment Programme covering infrastructure schemes including housing, transport, and public realm
  • Co-Invest Equity fund: A recoverable or recyclable commitment approved by WMCA Board on 23rd July 2021, excluded from the affordable limit figure
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

(1) It was noted that since the last meeting of the board, there had been no approvals of any business cases under delegated authority by officers. (2) The Investment Programme funding status and current affordable limit was noted. (3) The regional Investment Programme delivery update was noted.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

Background

4.1The Investment Board was established by the WMCA Board as a key element of the approvals process across the Investment Programme.

4.2The Investment Board considered and endorsed an enhanced Terms of Reference at its meeting on 20th April 2020 (approved by WMCA Board 24th July 2020). This set out an enhanced role supporting decision-making, greater post approval controls, performance management and effective delivery of monitoring & evaluation requirements.

4.3The enhanced Terms of Reference included the following:

• To oversee and monitor all investments made through the Investment Programme.

• To add conditions to any funding decision that falls within its delegated authority. Minimum conditions should specify the availability period, conditions to drawdown of funds, conditions for withdrawal of support and terms of clawback, start date and completion date for the project or programme.

• Where oversight of monitoring and evaluation applies to the Investment Board, to consider whether a formal review of project or programme is required, and to consider this review itself or instruct the Investment Panel to do so on its behalf.

4.4On the 10th of June 2022, WMCA Board approved extending the role and remit of WMCA Investment Board to cover all WMCA projects (including the CRSTS programme), allowing investment decisions to be made for values between £5 million and £20 million in line with the Single Assurance Framework.

Investment Programme Affordable Limit & Gateway Status

4.5At the WMCA Board meeting on 19th March 2021, WMCA Board approved an increase to the current WMCA Investment Programme affordable limit of £70 million, from £801 million to £871 million. This remains the current limit of grant funding1 that can be provided by WMCA from the Investment Programme.

1 Excluding part of the anticipated recoverable/recyclable commitment to the West Midlands Co-Invest Equity

fund approved by WMCA Board on 23rd July 2021. Investment Programme Assurance Summary

4.6Approved grant funding awarded and administered by the WMCA to programmes within the Regional Investment Programme totals £844.3 million as 31st October 2025. which is unchanged from the amount reported at the previous sitting of Board.

4.7These commitment values above exclude the provisional ‘ear-marked’ allocations agreed by WMCA Board in March 2021 that are yet to obtain formal approval. Commitments for some of these ear-marked items will be confirmed via the approval of further reports to WMCA Board.

4.8Since the previous full meeting of the WMCA Investment Board on 17th November 2025, no business case submissions for grant funding from the Investment Programme have been approved under delegated authority.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IP Update Report Dec-25 (Final)Appendix 1 535 KB Download
PDF
Investment Programme UpdateReport 207 KB DownloadRead as text
PDF
November 2025 IP Dashboard (Final)Report 726 KB Download

At this meeting

Whole meeting

Who was there

5 of 8 attended
PH
Councillor Peter HughesChair, present
BS
Councillor Bob SleighCommittee Member - Voting, present
MB
Councillor Mike BirdCommittee Member - Voting, present
CB
Councillor Christopher BurdenCommittee Member - Voting, present
SC
Councillor Steve ClarkCommittee Member - Voting, in attendance, virtual
MM
Councillor Majid MahmoodCommittee Member - Voting, present
JO
Councillor Jim O'BoyleCommittee Member - Voting, apologies
SS
Sue SummersCommittee Member - Non-Voting, apologies

On this subject at West Midlands Combined Authority

Search all
  1. Investment Programme UpdateThis decision
  2. Investment Programme UpdateApproved
  3. Investment Programme Dashboard- Red Rated Projects UpdateNoted
  4. Investment Programme UpdateApproved
  5. Investment Programme UpdateApproved
  6. Investment Programme UpdateApproved

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... Noted Open