Investment Board, Monday 15 December 2025 at 10.00am

Update Report: City Region Sustainable Transport Settlement - Quarter 2 2025/26

Noted Committee 1 paper

AI summaryWest Midlands Combined Authority Investment Board noted progress on the City Region Sustainable Transport Settlement in quarter 2 of 2025/26, with £512.9m spent and £1,167.6m approved against the £1.182bn settlement.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQ2 2025/26 CRSTS programme update recorded
Money£1.182bn settlement, £512.9m spentOf the £1.182bn West Midlands CRSTS1 settlement
What happens nextJanuary 2026 WMCA Board paperRosewell Review outputs to be incorporated
Who it affectsWest Midlands transport schemes and promoters50 projects and programmes in the CRSTS1 programme

What was decided

The Investment Board noted the progress made on the City Region Sustainable Transport Settlement programme during quarter 2 of 2025/26.

Why

The West Midlands CRSTS programme is a £1.182bn government grant plus £120.1m local contribution, supporting transport infrastructure across the region until March 2027. Report 5.3, 5.1

A May 2025 rebaseline approved by the WMCA Board rephased £162m of projects into the CRSTS1 allocation, with Department for Transport approval received in August 2025. Report 6.4, 6.5

What happens next

The Rosewell Review of investment plans, led by Bridget Rosewell CBE, will be incorporated into a January WMCA Board paper alongside Transport for City Regions funding review. Report P51, P52

Work will continue with scheme promoters to accelerate delivery and mitigate delay risks, with quarterly DfT reporting to continue. Report 7.5, 6.9

The money

  • £5.7bn National CRSTS programme grant over five years (2022/23 to 2026/27) Report 5.1
  • £1.182bn West Midlands CRSTS1 capital settlement Report 5.3, 15.2
  • £120.1m Local contribution from WMCA and Local Authorities Report 5.3
  • £1.167.6m CRSTS funding approved against settlement as of 31st October 2025 Report P29
  • £512.9m Expenditure funded from CRSTS capital settlement as of 30th September 2025 Report P29
  • £699.4m Forecast expenditure funded from CRSTS up to 31st March 2026 Report P29
  • £186.5m Further forecast expenditure from October 2025 to March 2026 Report P29
  • £35.0m Additional funding approved since 30th June 2025 Report P29
  • £55.1m Additional spend since 30th June 2025 Report P29
  • £162m Projects rephased into CRSTS1 allocation under May 2025 rebaseline Report 6.4
  • c. £83.6m Local contribution achieved to date Report 7.12
  • c. £120m Expected total local match funding over five years

Options considered

  • Rejected: Consider options and evidence. Marked not applicable as report is a programme update Report 8.1
  • Rejected: Consider preferred option. Marked not applicable as report is a programme update Report P56

Implications

  • Financial: No direct financial implications from the recommendations; report confirms £1.182bn capital resources. Report P64, 15.2
  • Legal: No legal implications arising from the report. Report P66
  • Risk: Top programme risks are schedule (23%), budget (18%) and operational (12%); inflationary pressure could cause overruns or scope reductions. Report 7.3, P36
  • Other: Up to 25% overprogramming in the programme reduces risk of underspending in the five-year period to March 2027. Report 7.7

Who and where

  • West Midlands CRSTS scheme promoters and local authorities Report 5.3, 7.10
  • Department for Transport as funder Report 6.7, 6.8
  • Public transport and road users in the West Midlands Report P9, P10, P11

Timeline

  • 10 June 2022: WMCA Board extended Investment Board remit to cover all projects including CRSTS Report 4.2
  • September 2023: Initial rebaseline undertaken at DfT request to reflect inflationary cost pressures Report 6.2
  • July 2024: Further change set out capital and programme pressures, prioritising in-flight projects and deferring some Report 6.3
  • 9th May 2025: WMCA Board approved rebaseline report rephasing £162m of projects Report 6.4
  • August 2025: Department for Transport approval of the rebaseline received Report 6.5
  • 30th September 2025: Spend reporting cut-off for this update Report P29
  • 31st October 2025: Date for approved funding figures against settlement Report P29
  • 14th November 2025: Q2 FY25/26 update submitted to DfT Report 6.8
  • January 2026: Rosewell Review outputs to be incorporated into WMCA Board paper Report P51, P52
  • 31st March 2027: End of current CRSTS1 settlement period Report 7.7

Plain English for the jargon

  • CRSTS: City Region Sustainable Transport Settlement, a government grant programme for transport infrastructure in English city regions
  • WMCA: West Midlands Combined Authority
  • DfT: Department for Transport
  • RAG: Red, Amber, Green status used in project and programme reporting
  • M&E: Monitoring and Evaluation
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

The progress made on the City Region Sustainable Transport Settlement programme during quarter 2 of 2025/26 was noted.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

Background

4.1The Investment Board was established by the WMCA Board as a key element of the approvals process across the WMCA Investment Programme.

4.2On 10 June 2022, WMCA Board approved extending the role and remit of WMCA Investment Board to cover all WMCA projects (including those within the CRSTS programme), allowing investment decisions to be made for values between £5m and £20m in line with the WMCA Single Assurance Framework.

4.3The Investment Board considered and endorsed an enhanced Terms of Reference at its meeting on 24th July 2020. This set out an enhanced role supporting decision- making, greater post approval controls, performance management and effective delivery of monitoring & evaluation requirements.

4.4The enhanced Terms of Reference included the following:

• To add conditions to any funding decision that falls within its delegated authority. Minimum conditions should specify the availability period, conditions to drawdown of funds, conditions for withdrawal of support and terms of clawback, start date and completion date for the project or programme. • Where oversight of monitoring and evaluation applies to the Investment Board, to consider whether a formal review of project or programme is required, and to consider this review itself or instruct the Investment Panel to do so on its behalf.

5. Overview of the CRSTS Programme

5.1The National Infrastructure Strategy committed to investments in local transport networks to improve productivity in our largest cities. The national CRSTS programme aims to deliver transformational change through investments in public and sustainable transport infrastructure in some of England’s largest city regions through grant funding of £5.7bn over five years (2022/23 – 2026/27).

5.2The CRSTS funding is aimed at achieving the following objectives:

• Driving growth and productivity;

• Decarbonising transport; and

• Levelling up services and areas

5.3The West Midlands submitted a programme level business case consisting of 50 projects and programmes totalling an investment of over £1bn in transport improvements. This investment includes a government grant of £1.182bn, along with £120.1m as a local contribution from WMCA and Local Authorities.

5.4The CRSTS funding consolidates a number of historic funding sources (including highways maintenance) and provide a very welcome five-year planning and resourcing horizon. 6. Changes to the West Midlands Region CRSTS Programme

6.1The West Midlands CRSTS programme has continued to evolve following its establishment and subsequent approval by DfT in 2022. As to be expected with a programme of this nature, changes have been required for a number for factors which have included inflationary cost pressures, externally driven scope changes and supply chain issues.

6.2An initial re-baseline of the programme was undertaken in September 2023, which was undertaken across the programme, at the request of DfT, in order to reflect inflationary construction cost pressures.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update Report: City Region Sustainable Transport Settlement: Quarter 2 2025/26Report 410 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 8 attended
PH
Councillor Peter HughesChair, present
BS
Councillor Bob SleighCommittee Member - Voting, present
MB
Councillor Mike BirdCommittee Member - Voting, present
CB
Councillor Christopher BurdenCommittee Member - Voting, present
SC
Councillor Steve ClarkCommittee Member - Voting, in attendance, virtual
MM
Councillor Majid MahmoodCommittee Member - Voting, present
JO
Councillor Jim O'BoyleCommittee Member - Voting, apologies
SS
Sue SummersCommittee Member - Non-Voting, apologies

On this subject at West Midlands Combined Authority

Search all
  1. Update Report: City Region Sustainable Transport Settlement - Quarter 2 2025/26This decision
  2. Rosewell Review Phase 2/ Transport for City Regions UpdateNoted
  3. Update Report City Regions Sustainable Transport Settlement Quarter 4 FY 2025/26Noted
  4. Rosewell Review Phase 2 / Transport for City RegionsNoted
  5. Update Report: City Region Sustainable Transport Settlement - Quarter 3 2025/26Noted
  6. Rosewell Review/Transport for City RegionsNoted

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... Noted Open