Local Electric Vehicle Infrastructure Capital Fund Project

Agreed Committee 1 paper

AI summaryWest Midlands Combined Authority Investment Board approved the £14.5m drawdown of LEVI capital funding to deliver an electric vehicle charging network across the West Midlands, with contracts to be awarded from April 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreed£14.5m LEVI drawdown agreed, authority delegated
Money£14.5m LEVI Capital FundFrom OZEV, total project ~£70m with private match
What happens nextContract award from April 2026Subject to DfT approval of final contracts
Who it affectsWest Midlands residents and 7 LAsEspecially households without off-street parking

What was decided

The Board agreed to draw down £14.5m of Local Electric Vehicle Infrastructure Capital Funding to enable contract award and installation of an EV charging network across the West Midlands. Report P2, P4

Authority was delegated to the Executive Director of Transport for the West Midlands, in consultation with the Section 73 Officer and Monitoring Officer, to approve the full business case and to negotiate and agree all contract terms, subject to Programme Assurance and Appraisal processes, a positive recommendation, and Department for Transport approval of the final contracts, with political oversight. Report P2, 9.1

WMCA Officers were asked to continue to formally engage with Local Authority Officers on the project. Report 2.12

Why

Central Government has committed to phasing out new petrol and diesel vehicles from 2030 with a full ban by 2035, and the £343m LEVI Capital Fund was set up in 2023 to accelerate local, mainly low-power, on-street EV charging, primarily for residents without off-street parking. Report 2.3, 2.4, 2.5, 2.6

The Office for Zero Emission Vehicles allocated £14.5m to WMCA as a Tier 1 authority, with 90% received in March 2024 and 10% in May 2025, and the project aims to meet forecast demand of around 18,385 charging spaces by 2030, against about 4,000 existing public on-street chargers. Report 2.7, 2.29, 2.30, P35

Officers warn that, without swift approval, contracts could be delayed by 6 months or more, suppliers may withdraw, and the West Midlands would fall behind other areas that have already awarded LEVI contracts, with reputational and net-zero consequences. Report 11.4, 11.5, 11.6, 11.8

What happens next

Tender evaluation runs from 13 January to February 2026, with the Full Business Case due to Programme Assurance and Appraisal in February 2026 and Contract Approval Report in March 2026. Report P64

Final draft contracts must be submitted to the Department for Transport for approval in March 2026 before contracts can be awarded from April 2026, with installations to start as soon as possible afterwards. Report 2.10, 2.20, 2.23, P64

WMCA will be the named party in concession contracts; all seven West Midlands local authorities have signed an Inter-Authority Agreement to commit to delivery and share in revenue. Report 9.1, 9.2

The money

  • £14.5m LEVI Capital Funding drawdown to facilitate contract award and EV infrastructure installation Report P1, 7.2
  • £14.5M OZEV LEVI Capital Grant awarded to WMCA as Lead authority under Section 31 of the Local Government Act 2003 Report 2.7, 7.2
  • £343M Total Local Electric Vehicle Infrastructure Capital Fund established by Government in 2023 Report 2.3
  • ~80% Expected private sector share of installation costs
  • approximately £70M Anticipated total project value including private sector match
  • 90% Share of LEVI funds received by WMCA in March 2024 Report 2.7

Options considered

  • Rejected: Option 1: Business as usual, do nothing. Would leave EV charging gap unaddressed ahead of 2030 phase out Report P38, P39, P37
  • Rejected: Option 2: Do the minimum, low-power lamppost chargers only over 5-year delivery within 16-year contract. Increases access to low-power EVI only; BCR 5.84 Report P40, P41
  • Chosen: Option 3: Preferred, mix of pedestal, lamppost, flat/flush and high-powered chargers over 5-year delivery within 16-year contract. Best meets forecast West Midlands demand for 2030/1 with predominantly low-power on-street plus higher-powered options; BCR 5.22 Report P42, P43, P46, P47
  • Rejected: Option 4: Same mix but delivered over 10 years within 16-year contract. Delivery would run past the 2030 phase-out date; BCR 4.66 Report P44, P45

Implications

  • Financial: Project is funded by OZEV grant and expected private sector match of around 80%, with a Concession contract giving WMCA an annual charging space fee and revenue share, apportioned by location, expected to produce a sustainable surplus over the contract life. Report 8.1, 11.1
  • Legal: WMCA will be the named party in concession contracts; the supplier takes consents, operational and maintenance risk; an Inter-Authority Agreement commits all seven LAs and gives them a share of revenue. Report 9.1, 9.2, 9.4
  • Equalities: A Health Equity Impact Assessment has been completed and approved; the project targets an equitable spread across LA areas, multiple payment methods, prioritisation of areas with limited off-street parking, and 1 in 5 chargepoints to be PAS 1899 compliant. Report 2.28, 10.6, 10.7, 10.8, P69, P70, P71, P72
  • Climate: By 2035, cumulative emissions mitigated by the project are expected to be 500244 tonnes of CO2, 982 tonnes of NOx and 19 tonnes of particulate matter, with around 609.6 gWh dispensed and a projected 1987.8 million miles reduction in ICE vehicle miles. Report P49, P75
  • Risk: Not approving risks 6 months or more of delay, loss of supplier interest, reputational damage, disadvantage to deprived communities and households without off-street parking, and possible rise in unsafe trailing three-pin cables. Report 11.4, 11.5, 11.6, 11.7, 11.8

Who and where

  • West Midlands residents without off-street parking, estimated at 31% of households Report 2.27
  • The seven partner local authorities working with WMCA on the project Report 2.7, 2.12
  • Disabled drivers, who currently find accessible chargepoints scarce (2.3% of UK public chargepoints considered fully accessible) Report 2.28
  • Residents in less affluent areas with lower current EV uptake Report 2.26, P71
  • Commuters, tourists, taxi and commercial vehicle users where provision complements the resident focus Report 2.4

Timeline

  • May 2023: Stage 1 expression of interest submitted for LEVI funding Report 2.9
  • March 2024: WMCA received 90% of allocated LEVI funds Report 2.7
  • March 2025: Outline Business Case approved with 79% appraisal score
  • May 2025: WMCA received remaining 10% of allocated LEVI funds Report 2.7
  • 14 October 2025: Invitation to Tender published to shortlisted suppliers Report P64, 2.16
  • 12 January 2026: Deadline for tender submissions Report P64
  • 13 January 2026 to February 2026: Tender evaluation period Report P64
  • February 2026: Full Business Case scheduled for submission to Programme Assurance and Appraisal Report P64
  • March 2026: Contract Approval Report, submission of final contract to OZEV and LEVI Programme Board approval (possible delays due to elections) Report P64, 2.21
  • April 2026: Publish Contract Details Notice, issue Award Decision Letters and award contracts Report P64, 2.23
  • 2030: Government phase-out date for new petrol and diesel vehicles Report 2.27
  • 2035: All new vehicles required to be 100% zero emissions; project cumulative emissions mitigation figures measured Report P49, P75

Plain English for the jargon

  • LEVI: Local Electric Vehicle Infrastructure, the central Government capital fund supporting local on-street EV charging
  • OZEV: Office for Zero Emission Vehicles, the Government body that allocated the LEVI grant
  • DfT: Department for Transport, which must approve final contracts before award
  • EVI: Electric Vehicle Infrastructure
  • ICE: Internal Combustion Engine, referring to petrol and diesel vehicles
  • CPO: Charge Point Operator, the supplier installing and running charge points
  • ITT: Invitation to Tender, the procurement document issued to shortlisted suppliers
  • FBC / OBC: Full Business Case and Outline Business Case, the WMCA project approval stages
  • BCR: Benefit-Cost Ratio, the appraisal score for each project option
  • IAA: Inter-Authority Agreement, signed by all seven LAs to support the project
  • PAA: Programme Assurance and Appraisal, WMCA's internal review of the Full Business Case
  • CAR: Contract Approval Report, the internal step before contracts are awarded
  • PAS 1899: Accessibility standard for public EV chargepoints
  • HEIA: Health Equity Impact Assessment, completed and approved for this project
  • EVPC: EV Pavement Channel, a cross-pavement cable solution being trialled in Coventry
  • PSQ: Procurement Specific Questionnaire, the first stage of the competitive flexible procurement
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item135

Resolved

Resolved that: 1. The drawdown of £14.5m Local Electric Vehicle Infrastructure Capital Funding to facilitate contract award with the successful supplier(s) and the subsequent installation of an electric vehicle infrastructure network across the West Midlands be agreed. 2. Authority be delegated to the Executive Director of Transport for the West Midlands, in consultation with the Section 73 Officer and Monitoring Officer, the approval of the full business case for the project subject to the completion of Programme Assurance and Appraisal processes and a positive recommendation and with political oversight. 3. Authority be delegated to the Executive Director of Transport for the West Midlands, in consultation with the Section 73 Officer and Monitoring Officer, the negotiation and agreement of all contract terms and conditions subject to securing approval of the final contracts by the Department for Transport and with political oversight. 4. WMCA Officers continue to formally engage with Local Authority Officers on the project.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

Recommendations

The Investment Board is recommended to:

1. Agree to the drawdown of £14.5M LEVI Capital Funding to facilitate contract award with the successful supplier(s) and the subsequent installation and operation of an electric vehicle infrastructure network across the West Midlands, 2. Delegate to the Executive Director of Transport for West Midlands, in consultation with the Section 73 Officer and Monitoring Officer, the approval of the full business case for the project subject to the completion of Programme Assurance and Appraisal processes and a positive recommendation, 3. Delegate to the Executive Director of Transport for West Midlands, in consultation with the Section 73 Officer and Monitoring Officer, the negotiation and agreement of all contract terms and conditions subject to securing approval of the final contracts by the Department for Transport.

Voting Requirements A majority of voting members, in attendance in the meeting room and indicating their preference, are required to vote in favour of any recommendations for it to become a decision of the board. 1. Executive Summary 1.1 The purpose of this report is to seek agreement for the immediate drawdown of £14.5M of funding to enable the delivery of an electric vehicle infrastructure (EVI) network for the West Midlands. Members of the Investment Board are recommended to endorse the delegation of authority to the Executive Director of Transport for West Midlands to approve the full business case for the project following internal assurance and appraisal processes, and to approve the delegation of authority to the Executive Director of Transport for West Midlands in consultation with the Section 73 Officer and Monitoring Officer to enter into concession contracts on behalf of the organisation. This delegation will enable timely procurement and ensure that contractual obligations are fulfilled without unnecessary delays, thereby supporting the efficient delivery of projects and services.

2. Matters for Consideration

Background 2.1 As part of central Government’s commitment to transitioning to zero emission vehicles, the sale of all new petrol and diesel vehicles or Internal Combustion Engine (ICE) vehicles will be phased out from 2030, with a full ban in 2035. All new vehicles will have to be 100% zero emissions by 2035.

2.2Government has laid out its plan to manage this transition, and the need for urgent action has been outlined in several key documents, including: the Electric vehicle infrastructure strategy and the Transition to zero emission cars and vans: 2035 delivery plan.

2.3To support this transition, £343M of Local Electric Vehicle Infrastructure (LEVI) Capital Fund was established in 2023 to accelerate the deployment of local, primarily low power (<22kW) electric vehicle (EV) charging infrastructure ahead of demand.

2.4The funds must be used to primarily benefit residents without off-street parking, whilst also allowing some provision for other groups such as tourists, customers, commuters, taxis, and commercial vehicles – provided that residents are the primary beneficiaries and it increases scale and commerciality.

2.5The main aims of the grant fund are to deliver a step-change in the deployment of local, primarily low power, on-street electric vehicle (EV) charging infrastructure across England, and accelerate commercialisation and investment in the local charging infrastructure sector.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Electric Vehicle Infrastructure Capital Fund ProjectReport 307 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 8 attended
PH
Councillor Peter HughesChair, present
BS
Councillor Bob SleighVice-Chair, apologies
MB
Councillor Mike BirdCommittee Member - Voting, present
CB
Councillor Christopher BurdenCommittee Member - Voting, present
SC
Councillor Steve ClarkCommittee Member - Voting, in attendance, virtual
MM
Councillor Majid MahmoodCommittee Member - Voting, present
JO
Councillor Jim O'BoyleCommittee Member - Voting, present
SS
Sue SummersCommittee Member - Non-Voting, apologies

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... Noted Open
17 Aug 2026 Commercial Investment Fund DashboardResolved that: The report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies