West Midlands Combined Authority
Investment Board, Monday 23 February 2026 at 10.00am

East Birmingham Bus Depot Construction

Approved Committee 2 papers

AI summaryWest Midlands Combined Authority Investment Board approved the Business Justification Case to build a new 110-bus electric depot at Kitts Green, Birmingham, costing up to £19,930,000, subject to Birmingham City Council contributing at least £14,930,000.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedBJC and construction approved up to £19,930,000
Money£19,930,000BCC must contribute at least £14,930,000
What happens nextUpdate report to Investment BoardDue in September 2026
Who it affectsEast Birmingham bus passengersAbout 20 million journeys per year

What was decided

The Business Justification Case for construction of the East Birmingham Depot at Lea Ford Road, Kitts Green, Birmingham was approved.

Approval was given to WMCA to construct the new depot for not more than £19,930,000, subject to a funding agreement with Birmingham City Council requiring BCC to contribute at least £14,930,000.

Authority was delegated to the Director of Delivery-Transport Portfolio to negotiate design and construction contracts, and (in consultation with the Section 73 Officer) funding agreements with Birmingham City Council.

Why

Birmingham Central Depot, which currently houses 200 buses on 16 routes, will close when its lease expires in December 2027, putting around 20 million passenger journeys per year at risk. Report P5, P4

The depot will support Transport for West Midlands' transition to a zero-emission fleet, with capacity for 110 electric buses, full EV charging, and a driver training school. Report P2, P8

The economic case shows a Benefit-Cost Ratio of 10.9, described as 'very high' value for money, with social benefits of £31 million per year against whole-life public sector costs of £36 million. Report P20

What happens next

A funding agreement with Birmingham City Council must be completed, securing at least £14,930,000 from BCC, before the £5m CRSTS and £4.93m Clean Air Zone funding is accessed. Report P15, P16, P17, P27

Land acquisition from Birmingham City Council is planned for Q1 2026, with construction from September 2026 to January 2028, aiming for the depot to be operational by late 2027 or early 2028. Report P11, P28

BCC Cabinet is expected to confirm funding on 17 March 2026, and the project must report back to Investment Board in September 2026. Report P38

The money

  • £19,930,000 Total project cost (cost of construction) Report P3, P17
  • £14,930,000 Minimum contribution required from Birmingham City Council Report P19
  • £10,000,000 Levelling Up Fund via BCC (not secured, BCC approval required, deadline March 2028) Report P15
  • £5,000,000 CRSTS / Transport for City Regions (secured, WMCA Board approval September 2025) Report P16, P18
  • £4,930,000 DfT Clean Air Zone Capital Fund (not secured, awaiting DfT confirmation) Report P17
  • £31,000,000 Estimated annual social value from maintained bus services Report P10, P20
  • £36,000,000 Whole-life public sector costs including 70% optimism bias Report P20

Options considered

  • Chosen: Build new East Birmingham Depot at Kitts Green, Birmingham. Mitigates closure of Birmingham Central Depot in December 2027, supports 110 electric bus fleet and franchising, BCR of 10.9, 89% BCAT score Report P2, P20, P25

Implications

  • Financial: Approval is conditional on securing all identified funding, including confirmation of the £2.2m CAZ contribution, to avoid any funding gap. Report P27, P38
  • Risk: High-rated risk: project depends on TfWM Executive Director approval to spend £5m from the wider depot acquisition budget; outcome of Transport DSO decision on 22 January 2026 is awaited. Report P37
  • Risk: Risk that £2.2m CAZ funding may not be secured, though the appraisal team considered there to be a very strong likelihood of funds being granted. Report P38, P40
  • Climate: Depot supports WMCA's #WM2041 net zero target, with full electric bus capability, reduced emissions and improved air quality in East Birmingham. Report P58, P59, P60, P61
  • Staffing: Project expected to create 30+ local jobs with training provision. Report P10
  • Legal: Land boundary at Kitts Green is fixed with no alternative parcels offered by BCC; site is on previous industrial use. Report P47

Who and where

  • East Birmingham bus passengers, around 20 million journeys per year Report P5
  • Birmingham City Council, as landowner and funding contributor Report P2
  • Transport for West Midlands bus operators and drivers Report P2, P4
  • Local residents in East Birmingham, including underserved communities Report P10, P57

Timeline

  • Q1 2026: Land acquisition from Birmingham City Council Report P11
  • 22 January 2026: Transport DSO decision submitted (outcome awaited) Report P37
  • 17 March 2026: BCC Cabinet expected to confirm funding Report P38
  • September 2026: Construction begins; update report to Investment Board Report P11
  • December 2027: Birmingham Central Depot lease expires Report P4, P5
  • January 2028: Construction due to complete Report P11
  • Late 2027 / early 2028: Depot to be operational, ahead of December 2027 Birmingham Central Depot closure Report P5, P11
  • March 2028: Levelling Up Fund expenditure deadline Report P15

Plain English for the jargon

  • BJC: Business Justification Case, the document setting out the case for the depot investment.
  • BCAT: Business Case Assessment Tool, scored at 89% for this project.
  • BCR: Benefit-Cost Ratio, calculated at 10.9 for this project.
  • CRSTS: City Region Sustainable Transport Settlement, a government transport funding stream.
  • CAZ: Clean Air Zone, a Birmingham zone with associated DfT capital funding.
  • LuF: Levelling Up Fund, provided via Birmingham City Council.
  • TfWM: Transport for West Midlands, the regional transport body within WMCA.
  • WMCA: West Midlands Combined Authority.
  • DSO: Decision Support Officer or similar internal governance stage in the Single Assurance Framework.
  • SINC: Site of Importance for Nature Conservation, relevant to temporary access during construction.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item134

Resolved

Resolved that: 1. The Business Justification Case for the construction of the East Birmingham Depot at site Lea Ford Road, Kitts Green, Birmingham be approved. 2. Approval be given to the carrying out the construction of this new East Birmingham Depot by West Midlands Combined Authority for not more than a cost of £19,930,000 and for West Midlands Combined Authority to enter into design and construction contracts for the construction of the new East Birmingham Depot (for a cost of not more than £19,930,000) subject in each case to the condition that there has been a completion of a funding agreement with Birmingham City Council that requires Birmingham City Council to contribute a minimum of £14,930,000 towards the cost of construction of the new East Birmingham Depot. 3. Authority be given to the West Midlands Combined Authority to enter into one or more agreements with Birmingham City Council to provide for funding for the construction of the new East Birmingham Depot. 4. Authority be delegated to the Director of Delivery-Transport Portfolio to negotiate and agree the terms of any contracts for the design and construction of the new East Birmingham Depot subject to the conditions that there has been completion of a funding agreement with Birmingham City Council for Birmingham City Council to contribute to a minimum of £14,930,000 towards the cost of construction of the new East Birmingham Depot. 5. Authority be delegated to the Director of Delivery- Transport Portfolio in consultation with the Section 73 Officer to negotiate and agree the terms of any funding agreements with Birmingham City Council. 6. A report be submitted to Investment Board in September to provide an update on the progress of the project.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

Executive summary

This Business Justification Case (BJC) has been submitted by Morgan Boswell, Consultant and Project Lead for the East Birmingham Depot Project within Transport for West Midlands (TfWM).

The Investment Panel is requested to endorse, and the Investment Board is requested to decide on the approval of the acquisition of land from Birmingham City Council (BCC) and the construction of a new bus depot at Kitts Green. The facility will provide operational capacity for 110 electric buses, supporting TfWM’s transition to a zero-emission fleet.

The total estimated investment for this project is £19.93 million.

The East Birmingham Depot project will acquire land from Birmingham City Council (BCC) and construct a new bus depot at Kitts Green, providing operational capacity for 110 electric buses. The project is essential to mitigate the closure of Birmingham Central Depot (lease expires December 2027) and supports the wider bus franchising programme.

Birmingham Central Depot currently houses 200 buses serving 16 routes across East Birmingham. The landlord has issued notice with no intention to renew, placing approximately 20 million passenger journeys per annum at risk. Without this intervention, significant service disruptions would occur and could jeopardise franchising implementation.

Outputs:

New bus depot with 110+ vehicle capacity,

• Full EV charging infrastructure, engineering facilities • Driver training school • Freehold site ownership providing long-term operational certainty • Brownfield regeneration with minimum 10% biodiversity net gain

Outcomes:

• Service continuity for East Birmingham (£31m annual social value) • Fleet decarbonisation through full electric capability • Creation of 30+ local jobs with training provision • WMCA-owned infrastructure supporting franchising and reducing long-term costs • Enhanced transport connectivity for underserved communities

Timeline: Land acquisition Q1 2026, Construction September 2026 to January 2028, operational by late 2027/early 2028 to meet the December 2027 Birmingham Central closure deadline.

1|P a g e Risk & Investment Appraisal Single Assurance Framework

Finance Summary Funding Source Amount Status Conditions & Timeline

(£m)

Levelling uo Fund (LuF) via • BCC Approval Required BCC Not £10.00 • Expenditure deadline March 2028 Secured

City Region Sustainable Transport Settlement WMCA Board Approval September Secured (CRSTS)/ Transport for City £5.00 2025 Regions

DfT Clean Air Zone (CAZ) Not • Routes linked to Birmingham CAZ £4.93 Capital Fund Secured • Awaiting confirmation from DfT Total Project Cost £19.93

Secured Funding £5.00

Unsecured Funding £14.93

Value for Money: The economic case demonstrates exceptional value for money with a Benefit- Cost Ratio (BCR) of 10.9, significantly exceeding the Green Book threshold for 'very high' value for money. The social benefits of maintaining bus services (£31m per annum) substantially outweigh the whole-life public sector costs (£36m including 70% optimism bias).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Depot Construction -WMCA-SAF-RIA Report FINALReport 334 KB DownloadRead as text
PDF
East Birmingham Bus Depot ConstructionReport 360 KB Download

At this meeting

Whole meeting

Who was there

5 of 8 attended
PH
Councillor Peter HughesChair, present
BS
Councillor Bob SleighVice-Chair, apologies
MB
Councillor Mike BirdCommittee Member - Voting, present
CB
Councillor Christopher BurdenCommittee Member - Voting, present
SC
Councillor Steve ClarkCommittee Member - Voting, in attendance, virtual
MM
Councillor Majid MahmoodCommittee Member - Voting, present
JO
Councillor Jim O'BoyleCommittee Member - Voting, present
SS
Sue SummersCommittee Member - Non-Voting, apologies

On this subject at West Midlands Combined Authority

Search all
  1. East Birmingham Bus Depot ConstructionThis decision
  2. Birmingham East Mayoral Development Corporation Strategic Outline Business Case and EstablishmentNoted
  3. Mayoral Development Zone and Mayoral Development Corporation to facilitate delivery of East Birmingham / North Solihull and Priority ProjectsApproved
  4. Birmingham Eastside Extension Sections 3 & 4 Full Business Case UpdateNoted
  5. Birmingham Eastside ExtensionNoted

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... Noted Open
17 Aug 2026 Commercial Investment Fund DashboardResolved that: The report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies