Sprint Purchase of Vehicles Full Business Case

Decided Committee 2 papers

AI summaryWMCA Investment Board endorses Sprint vehicles business case for up to £31.46m, subject to two conditions including a separate ticketing case.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedSubject to two conditions
MoneyUp to £31.46m£26.0m WMCA CRSTS, £5.46m DfT
What happens nextWMCA Board 13 March 2026Final decision on £26.0m spend
Who it affectsWalsall to Solihull bus corridor24 zero emission articulated buses

What was decided

The Investment Board endorsed the Sprint Purchase of Vehicles Full Business Case for submission to the WMCA Board on 13 March 2026.

The endorsement is conditional on funding options for replacement vehicles and vehicle lifecycle being developed and included in the programme.

A separate Sprint Ticketing Solution Full Business Case must also be submitted to the Investment Board.

Why

The appraisal recommended approval based on an independent assessment of the risks and opportunities, subject to six conditions set out in the report. Report P12, P13, P14, P15, P16, P17, P18

The case covers 24 zero emission articulated buses on a Walsall to Solihull corridor, with depot infrastructure and on-board systems. Report P2, P4

WMCA Assurance rated overall business case maturity at 76%, classed as Green Amber, meaning successful delivery appears probable but needs constant attention. Report P50, P51

What happens next

Submit the Full Business Case to the WMCA Board for a decision on 13 March 2026. Report P6

Develop funding options for replacement vehicles and vehicle lifecycle within the programme.

Submit a separate Sprint Ticketing Solution Full Business Case to the Investment Board.

The money

  • £31.46m Total expenditure sought across the Full Business Case Report P2
  • £26.0m Procurement of vehicles, extended warranty, maintenance and depot infrastructure Report P2, P6
  • £5.46m Capital investment in ticketing equipment, subject to a second business case Report P2, P6
  • £5.46m DfT ZEBRA bus grant for ticketing, not yet secured Report P6
  • £26.00m WMCA funding from CRSTS-1 for fleet and charging infrastructure, not yet secured Report P6

Options considered

  • Chosen: Approve the Sprint Purchase of Vehicles Full Business Case. Independent appraisal recommended approval subject to six conditions; assurance maturity rated 76% Report P12, P50

Implications

  • Financial: Up to £31.46m of expenditure is sought, with both the £26.0m WMCA CRSTS allocation and the £5.46m DfT ZEBRA grant not yet secured. Report P6
  • Climate: 24 zero emission articulated buses will support WMCA's 2041 net zero target and improve local air quality, with Birmingham having among the highest air pollution levels in the UK. Report P4, P45, P47
  • Risk: A34 and A45 Sprint corridor infrastructure delays and bus franchising delays are flagged as strategic risks requiring active management through to operationalisation. Report P24, P25
  • Staffing: A dedicated full-time Senior Responsible Officer is to be appointed to oversee the Sprint Programme and hold accountability for delivery. Report P13
  • Other: Monitoring and evaluation plans must cover Sprint vehicles and ticketing benefits and link with the wider Bus Transformation and Franchising Programme. Report P14, P28

Who and where

  • Passengers on the Walsall to Birmingham to Solihull corridor Report P4
  • Transport for West Midlands as the delivery body Report P1
  • The Bus Transformation and Franchising Programme, due to interdependencies Report P16, P17, P25
  • Residents of Birmingham exposed to road transport air pollution Report P47

Timeline

  • 2026-02-23: WMCA Investment Board endorsed the Full Business Case
  • 2026-03-13: WMCA Board to make decision on the £26.0m CRSTS spend Report P6
  • 2041: WMCA's target date for net zero regional emissions Report P45

Plain English for the jargon

  • FBC: Full Business Case
  • TfWM: Transport for West Midlands
  • WMCA: West Midlands Combined Authority
  • CRSTS: City Region Sustainable Transport fund
  • ZEBRA: Zero Emission Bus Regional Areas grant
  • SRO: Senior Responsible Officer
  • M&E: Monitoring and Evaluation
  • SAF: Single Assurance Framework
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item136

Resolved

Resolved that: The Sprint Purchase of Vehicles Full Business Case be endorsed for submission to the WMCA Board on 13 March 2026 subject to the following being included as part of the report recommendations (1) Funding options for replacement vehicles/vehicle lifecycle to be developed and included within the programme (2) Sprint Ticketing Solution Full Business Case to be submitted to Investment Board.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

Executive summary

This Full Business Case (FBC) has been submitted by Martin Pyne, Bus Transformation Manager from Transport for West Midlands, (TfWM), West Midlands Combined Authority, (WMCA).

This project is to specify, procure and commission ready for operation bus vehicles (including on-board systems) and associated depot and ticketing infrastructure for the Sprint Service. This business case seeks approval of up to £31.46m expenditure; £26.0m procurement for Vehicles, extended warranty/maintenance commitments and associated depot infrastructure to facilitate the operation, maintenance and charging of the vehicles. A further £5.46m of capital investment for ticketing equipment would be subject to a second business case. Sprint is a bus based rapid transit mode of transport with journey times and comfort levels that are based on those of a light rail system while maximising the flexibility and lower costs associated with bus technology. Sprint means faster journeys, improved reliability, higher quality public transport environment, greener environment, and easier access to transport and communities.

The Sprint Programme will deliver significant benefits to the West Midlands including: • Providing a significant transformational effect on the image of public transport in the Metropolitan area. • Meeting the mobility needs of the West Midlands conurbation as outlined in the Transport Prospectus, Birmingham’s Mobility Action Plan (BMap), HS2 Growth packages, and emerging West Midlands Strategic Transport Plan. • Generating a significant uplift in public transport patronage. • Providing a high capacity and low emission vehicle resulting in less environmental pollution; and • Delivering a tram-like vehicle while maximising the flexibility and lower costs associated with bus technology compared to that of a tram.

The Sprint service will operate on a corridor from Walsall to Solihull via Birmingham City Centre. • 24 zero emission Sprint Articulated Buses with multi-door boarding. • Zero emission at tailpipe. • Fully accessible vehicle. • Modern on-board systems providing audio/visual next stop announcements, connecting service information and high-quality CCTV. Financial Summary:

Funder Amount % of Total Status Details of Funding

DfT £5.46m 17.35% Not secured ZEBRA bus grant for ticketing WMCA £26.00m 82.65% Not secured CRSTS (for Fleet & Charging Infrastructure) Total: £31.46M WMCA Board are required to make a decision on this business case to spend £26.0m from City Region Sustainable Transport (CRSTS-1) on the procurement of Sprint Vehicles noting the allocation of £5.46m ZEBRA Bus Grant for ticketing systems subject to a separate business case.

The FBC has been reviewed by, or had input from, the following stakeholders: • Paul Atkins, [on behalf of] Programme Appraisal • Marzena Kubiak, Programme Assurance • Ann Stokes, Finance Business Partner

1|P a g e Risk & Investment Appraisal Single Assurance Framework

• Martin Wong, Legal Representative • Will Pemberton, Procurement ____________________________

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AppC_RIA Report_Sprint Purchase of VehiclesReport 346 KB DownloadRead as text
PDF
Sprint Purchase of Vehicles Full Business CaseReport 217 KB Download

At this meeting

Whole meeting

Who was there

5 of 8 attended
PH
Councillor Peter HughesChair, present
BS
Councillor Bob SleighVice-Chair, apologies
MB
Councillor Mike BirdCommittee Member - Voting, present
CB
Councillor Christopher BurdenCommittee Member - Voting, present
SC
Councillor Steve ClarkCommittee Member - Voting, in attendance, virtual
MM
Councillor Majid MahmoodCommittee Member - Voting, present
JO
Councillor Jim O'BoyleCommittee Member - Voting, present
SS
Sue SummersCommittee Member - Non-Voting, apologies

On this subject at West Midlands Combined Authority

Search all
  1. Sprint Purchase of Vehicles Full Business CaseThis decision
  2. Sprint Purchase of Vehicles Full Business CaseApproved

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... Noted Open
17 Aug 2026 Commercial Investment Fund DashboardResolved that: The report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies