Resolved
That (1) the spend to date at Month 6 of £18.2 million, with 50% of the financial year having elapsed, be noted. (2) the revised Capital Programme of £50.2 million be agreed and referred to Council for approval.
Cabinet noted this item on Thursday 5 November 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That (1) the spend to date at Month 6 of £18.2 million, with 50% of the financial year having elapsed, be noted. (2) the revised Capital Programme of £50.2 million be agreed and referred to Council for approval.
1.1This report provides an update on the progress in delivering the Capital Programme 2015/16 at the end of September 2015. The report recommends that Cabinet agrees the rephasing of the 2015/16 Capital Programme down to £50.2 million and reports expenditure to date of £18.2 million.
2 OVERALL POSITION AT END OF SEPTEMBER 2015
2.1The actual spend against the Capital Programme is summarised in Table 1.
Chart 1: Capital Programme spend below line of best fit
Capital Programme 2015/16
80 70 60 50 40 Revised Programme Actual spend £m
30 20 10 0 P0 P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12
Months
3 ORIGINAL AND PROPOSED CAPITAL PROGRAMME FOR 2015/16
3.1The Programme for 2015/16 is subject to change and reflects the Programme agreed by Cabinet on 10 February 2015 together with subsequent amendments. Broadly these reflect any re-profiling identified since the 2015/16 Budget Cabinet and changes regarding external financial support, primarily the latest grant notifications. 3.2 To aid the monitoring process, schemes are categorised against five gate points being Conception, Approval, Start Up, Delivery and Completion.
Table 1: Capital Programme 2015/16 at 30 September 2015
Capital Revisions Revised Actual Strategy Since Capital Spend Budget Programme September Cabinet 2015 £000 £000 £000 £000 Universal & Infrastructure 8,956 -5,032 3,924 1,671 Families – Children 8,517 2,287 10,804 3,083 Families – Adults 8,263 -2,946 5,317 517 Families – Sport & Rec 1,865 810 2,675 1,164 R&E– Env & Regulation 12,633 -147 12,486 4,698 R&E– Hsg & Comm Safety 6,412 -984 5,428 1,308 R& E – Regeneration 1,808 4,736 6,544 5,018 Transformation Resources 1,600 1,404 3,004 735 Total expenditure 50,054 128 50,182 18,194
3.3As outlined above a number of schemes within the Programme have been reprofiled to reflect updated project delivery forecasts and to take account of changes in available funding and costs. Variances since June are in Table 2.
Table 2: Variations to the 2015/16 Programme Scheme £000 Universal & Infrastructure Building refurbishment to increase occupancy -519 Cleveland St. Transport Depot -2,800 Park depot rationalisation -750 Demolish Bebington Town Hall and Liscard Municipal -378 Demolish former Rock Ferry High -395
Families & Wellbeing – Children Private Finance Initiative (PFI) -150 Wirral Youth Zone 100
Families & Wellbeing – Adults Transformation of day service -500
Families & Wellbeing – Sport & Recreation West Kirby Marine Lake -590 Bidston Tennis Centre re-roofing -325
Reg & Env – Environment & Regulation Energy schemes (LED Street Lighting) -1,074 Coast Protection -134 West Kirby Flood alleviation -1,400 Highway Maintenance -30 Scheme £000 Reg & Env – Housing Aids, adaptations and DFGs -1,235 LIFT -296 Clearance -1,324 Home Improvements -434 Empty Property interventions -76
Reg & Env – Regeneration LEP Regional Growth Fund 985
Overall variation since Quarter 1 -11,325
3.4Universal and Infrastructure Services
Building refurbishment to increase occupancy. Pending resolution over the future occupation of Old Market House there is an impact on other planned works which include the Wallasey South Annexe and Bebington Town Hall demolition. These form part of the accommodation review and are temporarily on hold.
A further eight schemes are either underway or have been completed (e.g. Wallasey Town Hall, Cheshire Lines) that will lead to significantly improved use of the Council’s asset base.
With the Cleveland Street Transport Depot being permanently occupied and operational this has resulted in the works being re-phased.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Monitoring 2015/16 Quarter 2 (To September 2015)Report | 114 KB | DownloadRead as text |
Follow Cabinet at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2020 | MinutesThat the Minutes of the meetings of the Cabinet held on 17 and 24 February 2020 be confirmed as a correct record. | Decided | Open |
| 27 Jul 2020 | Executive Key Decisions Taken Under Delegated PowersThat the following Key Decisions taken under delegated authority for the period 21 February 2020 to the date of publi... | Noted | Open |
| 27 Jul 2020 | Capital Monitoring Quarter 1 2020/21That (1) the Cabinet recommends to the Council the approval of additional funding for the schemes referred to in para... | Approved | Open |
| 27 Jul 2020 | Financial Monitoring Outturn 2019-20That (1) Revenue (a) it be noted that the gross expenditure has been balanced to gross income with the appropriate al... | Noted | Open |
| 27 Jul 2020 | Treasury Management Annual Report 2019/20That (1) the 2019/20 Treasury Management Annual Report be agreed and recommended to the Council for approval at its m... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.