That: (1) Cabinet notes the spend to date at Month 3 of £2.7 million, with 25% of the financial year having elapsed, a period when a number of payments relate to the 2015/16 accounts. (2) Cabinet agrees and RECOMMENDS to Council, for approval, the revised Capital Programme of £58.97 million, as referred to in Table 1 of the report.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
To note the spend to date at Month 3 of £2.7 million, with 25% of the financial year having elapsed, a period when a number of payments relate to the 2015/16 accounts.
To agree and refer to Council the revised Capital Programme of £58.97 million (Table 1). SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S 1.1 Regular monitoring and reporting of the Capital Programme enables decisions to be taken faster which may produce revenue benefits and will improve financial control of the Programme.
2.0OTHER OPTIONS CONSIDERED 2.1 No other options have been considered.
3.0BACKGROUND INFORMATION
OVERALL POSITION AT END OF JUNE 2016 3.1 The actual spend against the Capital Programme is summarised in Table 1.
Chart 1: Capital Programme spend below line of best fit
Capital Programme 2016/17
70 60 50 40 £m
Re vise d Prog ramme Actua l spen d
30 20 10 0 P0 P3 P6 P9 P12
Months
ORIGINAL AND PROPOSED CAPITAL PROGRAMME FOR 2016/17
3.2The Programme for 2016/17 is subject to change. Presently it reflects;
£000 Programme agreed by Cabinet on 22 February 2016 48,107 Variations identified Month 10 monitoring 2015/16 2,750 Year end re-profiling 6,364 Additional grant funding 1,750 Revised 2016/17 Programme 58,971 Table 1: Capital Programme 2016/17 at 30 June 2016
Capital Revisions Revised Actual Strategy Since Capital Spend Budget Programme June 2016 Cabinet £000 £000 £000 £000 Transformation Resources 7,863 1,755 9,618 637 Families – Children 9,185 3,766 12,951 564 Families – Adults 10,255 794 11,049 167 Families – Sport & Rec 2,871 368 3,239 351 R&E– Env & Regulation 10,016 2,635 12,651 551 R&E– Hsg & Comm Safety 7,317 847 8,164 430 R& E – Regeneration 600 699 1,299 4 Total expenditure 48,107 10,864 58,971 2,704
3.3As outlined above a number of schemes within the Programme have been re- profiled to reflect updated project delivery forecasts and changes in available funding. These are reflected in Table 1. The expenditure figures are suppressed by the inclusion of a number of credits for capital accruals charged against the 2015/16 year in accordance with accounting practice. The significant variances which have arisen since Budget Cabinet are shown in Table 2 below.
Table 2: Significant Variations (> £0.2m) to the 2016/17 Programme
Scheme £000 Transformation & Resources Building refurbishment to increase occupancy – schemes -202 proceeding ahead of schedule Park depot rationalisation – re-profiled 252 Energy efficiency initiatives – re-profiled 218 I.T. Development – re-profiled 1,423
Families & Wellbeing – Children School Place Planning – re-profiled 1,617 Condition/Modernisation – re-profiled 1,028 Basic Needs – re-profiled 1,096 Wirral Youth Zone (The Hive) – scheme proceeding ahead -500 of schedule
Capital Monitoring Quarter 1 2020/21That (1) the Cabinet recommends to the Council the approval of additional funding for the schemes referred to in para...
Financial Monitoring Outturn 2019-20That (1) Revenue (a) it be noted that the gross expenditure has been balanced to gross income with the appropriate al...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.