Resolved
That (1) the spend at Quarter 3 of £16.4 million, with 75% of the financial year having elapsed be noted; and (2) the revised Capital Programme of £30.7 million be agreed and referred to the Council.
Cabinet noted this item on Monday 20 February 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That (1) the spend at Quarter 3 of £16.4 million, with 75% of the financial year having elapsed be noted; and (2) the revised Capital Programme of £30.7 million be agreed and referred to the Council.
1. Note the spend at Quarter 3 of £16.4 million, with 75% of the financial year having elapsed;
2. Agree and refer to Council the revised Capital Programme of £30.7 million (Table 1). SUPPORTING INFORMATION
1.1Regular monitoring and reporting of the Capital Programme enables decisions to be taken more efficiently and effectively, which may produce revenue benefits and will improve the financial control of the Programme.
2.0OTHER OPTIONS CONSIDERED
2.1No other options have been considered.
3.0BACKGROUND INFORMATION
OVERALL POSITION AT END OF DECEMBER 2016
3.1The actual spend against the Capital Programme is summarised in Table 1.
Chart 1: Capital Programme spend below line of best fit
Capital Programme 2016/17
70 60 50 40 £m
Re vise d Prog ramme Actua l spen d
30 20 10 0 P0 P3 P6 P9 P12
Months
ORIGINAL AND PROPOSED CAPITAL PROGRAMME FOR 2016/17
3.2The Programme for 2016/17 is subject to change. Presently it reflects;
£000 Programme agreed by Cabinet on 22 February 2016 48,107 Year end re-profiling from 2015/16 6,364 Additional grant funding 1,750 Variations identified to September 2016 -18,134 Variations identified since September 2016 (see Table 2) -7,353 Revised 2016/17 Programme 30,734 Table 1: Capital Programme 2016/17 at 31 December 2016
Capital Revisions Revised Actual Strategy Since Capital Spend Budget Programme Dec 2016 Themes £000 £000 £000 £000 Business 15,093 -2,562 12,531 7,118 Environment 13,574 -6,293 7,281 3,855 People 19,440 -8,518 10,922 5,415 Total expenditure 48,107 -17,373 30,734 16,388
3.3PROGRESS TO DATE
3.3.1 Business
The investment in I.T. is focussed on migrating all servers and applications to the core domain and, where possible, upgrading applications to the latest version; upgrading all Windows Server operating systems to a supported operating system and reducing the server footprint by virtualising all servers where possible.
Works to increase building occupancy have mainly focused on Wallasey Town Hall, Moreton Municipal, and Solar Campus. Works are underway at Bebington Civic Centre where a new gas main has been installed in preparation for new efficient boilers to replace the oil fired system.
Works have commenced at Leasowe Millennium Centre to construct a new 70 space car park which will be complete by the end of March. Internal works will then commence to alter and improve the layout of the building which should significantly increase the occupancy of the building.
With the technical approval procedures completed the start on site for the Dock Bridges scheme is now March 2017. The large value equipment orders (i.e. hydraulic cylinders for moving the bridges) are being placed in February 2017. The grant funding received in 2016/17 will be fully utilised in Month 1 of 2017/18. The grant funding scheduled for 2017/18 remains sufficient and the overall scheme completion is still within the original timescales.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Monitoring 2016/17 Quarter 3Report | 132 KB | DownloadRead as text |
Follow Cabinet at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2020 | MinutesThat the Minutes of the meetings of the Cabinet held on 17 and 24 February 2020 be confirmed as a correct record. | Decided | Open |
| 27 Jul 2020 | Executive Key Decisions Taken Under Delegated PowersThat the following Key Decisions taken under delegated authority for the period 21 February 2020 to the date of publi... | Noted | Open |
| 27 Jul 2020 | Capital Monitoring Quarter 1 2020/21That (1) the Cabinet recommends to the Council the approval of additional funding for the schemes referred to in para... | Approved | Open |
| 27 Jul 2020 | Financial Monitoring Outturn 2019-20That (1) Revenue (a) it be noted that the gross expenditure has been balanced to gross income with the appropriate al... | Noted | Open |
| 27 Jul 2020 | Treasury Management Annual Report 2019/20That (1) the 2019/20 Treasury Management Annual Report be agreed and recommended to the Council for approval at its m... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.