That (1) the spend at Quarter 1 of £4.8 million, with 25% of the financial year having elapsed be noted and that this is suppressed by the inclusion of amounts that were charges against 2016/17 in accord with accounting practice; (2) the revised Capital Programme of £88.0 million be agreed and referred to the Council; and (3) agreement be given to the Growth Fund scheme being amended to provide a combination of business loans and grants rather than just loans.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
1 To note the spend at Quarter 1 of £4.8 million, with 25% of the financial year having elapsed and that this is suppressed by the inclusion of amounts that were charged against 2016/17 in accord with accounting practice
2 To agree and refer to Council the revised Capital Programme of £88.0 million (Table 1). 3 To agree that the Growth Fund scheme is amended so to provide a combination of business loans and grants rather than just loans. SUPPORTING INFORMATION
Reasons for recommendations
1.1Regular monitoring and reporting of the Capital Programme enables decisions to be taken faster which may produce revenue benefits and will improve financial control of the Programme.
2.0OTHER OPTIONS CONSIDERED
2.1No other options have been considered.
3.0BACKGROUND INFORMATION
OVERALL POSITION AT THE END OF QUARTER 1 (JUNE 2017)
3.1The actual spend against the Capital Programme is summarised in Table 1.
Chart 1: Capital Programme spend below line of best fit
Capital Programme 2017/18
100 90 80 70 60 50 £m
Re vise d Prog ramme Actua l spen d
40 30 20 10 0 P0 P3 P6 P9 P12
Months
ORIGINAL AND PROPOSED CAPITAL PROGRAMME FOR 2017/18
3.2The Programme for 2017/18 is subject to change. It presently reflects the following changes which are then detailed in Tables 1 and 2.
£000 Programme agreed by Cabinet on 20 February 2017 77,519 Year end re-profiling for 2016/17 6,203 Additional grants and contributions 7,242 Re-profiling to 2018/19 (2,950) Revised 2017/18 Programme 88,014 Table 1: Capital Programme 2017/18 at 30 June 2017
Capital Revisions Revised Actual Strategy Since Capital Spend Budget Programme June 2017 £000 £000 £000 £000 Business 32,760 5,506 38,266 1,893 Environment 16,769 259 17,028 634 People 12,250 4,730 16,980 239 Transformation 15,740 - 15,740 2,000 Total expenditure 77,519 10,495 88,014 4,766
3.3The spend figures at this stage of the year are suppressed by the inclusion of a number of credits for capital accruals charged against the 2016/17 year in accord with accounting practice. The significant variances which have arisen since the Budget was set are shown in Table 2.
Table 2: Significant Variations (> £0.2m) to the 2016/17 Programme
Scheme £000 Business Bridges - a combination of re-profiling £0.3m; additional 938 grant £0.15m and transfer from Unclassified/residential Streets” £0.5m Dock bridges – re-profiling £0.4m; additional grant £0.5m 935 STEP schemes - re-profiling £0.1m and grant confirmation 3,155 £3.1m Transport for Growth/Integrated Transport - re-profiled 878 Growth Fund - re-profiled 300 Unclassified/residential Streets - transfer to Bridges -500
Environment Aids/adaptations/disabled Facilities Grants- re-profiling 1,370 £0.4m; additional grant £1.0m West Kirby Flood alleviation - additional grant £1.2m and re- -1,750 profiled until 2018/19 -£3.0m Cemetery extensions and improvements - re-profiled 260
People Citizen and Provider Portal/Integrated I.T – re-profiled 944 Assistive Technology - re-profiled 615 Extra Care Housing - re-profiled 600 School condition allocation – re-profiling £0.8m; and grant 1,874 funding £1.1m School remodelling (Primary Places) – re-profiled 325
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring Quarter 1 2020/21That (1) the Cabinet recommends to the Council the approval of additional funding for the schemes referred to in para...
Financial Monitoring Outturn 2019-20That (1) Revenue (a) it be noted that the gross expenditure has been balanced to gross income with the appropriate al...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.