That: (1) The expenditure at Quarter 3 of £26.0 million be noted; (2) The new bid of £0.18 million (Mobile I.T. equipment for Social Workers, paragraph 3.3.1 of the report) be approved for inclusion in the programme and referred to Council; (3) The revised Capital Programme of £59.4 million (Table 1 of the report) be agreed and referred to Council.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
1 To note the expenditure at Quarter 3 of £26.0 million;
2 To approve for inclusion in the programme and refer to Council the new bid of £0.18 million (Mobile I.T. equipment for Social Workers, paragraph 3.3.1);
3 To agree and refer to Council the revised Capital Programme of £59.4 million (Table 1). SUPPORTING INFORMATION
Reasons for recommendations
1.1Regular monitoring and reporting of the Capital Programme enables decisions to be taken faster which may produce revenue benefits and will improve financial control of the Programme.
2.0OTHER OPTIONS CONSIDERED
2.1No other options have been considered.
3.0BACKGROUND INFORMATION
OVERALL POSITION AT THE END OF QUARTER 3 (DECEMBER 2017)
3.1The actual spend against the Capital Programme is summarised in Table 1.
Chart 1: Capital Programme spend below line of best fit
Capital Programme 2017/18
100 80 £m
60 Revised Programme Actual spend
40 20 0 P0 P3 P6 P9 P12
Months
ORIGINAL AND PROPOSED CAPITAL PROGRAMME FOR 2017/18
3.2The Programme for 2017/18 is subject to change. It presently reflects the following changes which are then detailed in Tables 1 and 2.
£000 Programme agreed by Cabinet on 6 November 2017 67,546 Re-profiling to 2018/19 and beyond (8,986) New bids 180 Grant variations 551 Other variations 80 Revised 2017/18 Programme 59.371 Table 1: Capital Programme 2017/18 at 31 December 2017
Capital Revisions Revised Actual Strategy Since Capital Spend Budget Programme Dec 2017 £000 £000 £000 £000 Business 32,760 1,563 34,323 12,108 Environment 16,769 (11,394) 5,375 2,648 People 12,250 (5,127) 7,123 4,194 Transformation 15,740 (3,190) 12,550 7,034 Total expenditure 77,519 (18,148) 59,371 25,984
3.3The significant variances which have arisen since the Quarter 2 report are:-
3.3.1 New Bids
Mobile I.T. Equipment for Social Workers (£0.18m) Following the 2016 Ofsted report Children’s Services have embarked on an improvement plan to address a number of issues raised. Caseload management was a key factor in the review and a Proof of Concept exercise has demonstrated the benefits of using mobile devices. They will increase the timeliness of case management work delivered by social workers through increased flexibility in working patterns and behaviours resulting in more intelligent and effective decisions being made for children and their families.
Estimated cost is £0.18 million in 2017/18 with the proposed funding being from Capital Receipts.
3.3.2 Table 2 : Re-profiling and other variations (significant > £0.2m)
Scheme £000 Business Sustainable Transport (STEP) - a number of schemes are (2,248) programmed for future years; 2018/19 East Float, Wirral Waters, A41; 2019/20 Duke St Phase 2; 2020/21 Carlett Park Re-profiled.
Business Investments Grants - based on the current level of (205) applications it is unlikely that all of the funding will be required this financial year. Re-profiled.
Growth Fund - same comment as the above. Re-profiled. (280) Environment Aids, adaptations and DFGs - spend is influenced by a (800) number of external factors such as the extent, complexity and value of the adaptations required. Re-profiled.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring Quarter 1 2020/21That (1) the Cabinet recommends to the Council the approval of additional funding for the schemes referred to in para...
Financial Monitoring Outturn 2019-20That (1) Revenue (a) it be noted that the gross expenditure has been balanced to gross income with the appropriate al...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.