Resolved - That: (1) Cabinet recommends to Council the approval of additional funding for the schemes referred to in paragraph 3.3 of the report. (2) Cabinet recommends to Council the approval of the revised Capital Programme of £55.889 million for 2019-20. Reasons for decision: Regular monitoring and reporting of the Capital Programme enables decisions to be taken faster which might produce revenue benefits and would improve financial control in Wirral Council .
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
Councillor Janette Williamson, Cabinet Member for Finance and Resources, said:
“We are making major investments in Wirral this year – improving infrastructure, supporting business growth and improving the public realm and local environment which residents are rightly proud of.
This report demonstrates this investment, it provides a helpful overview of our progress, and makes it clear that we are using the resources available to us to their best effect to help improve services, environment and opportunities for local people”.
REPORT SUMMARY
The report provides an update on the progress of the Capital Programme 2019/20 at the end of September 2019. It recommends that Cabinet agree the 2019/20 Capital Programme of £52.889 million which takes account of re-profiling, additional funding requirements and grant variations identified since June.
This matter is a key decision which affects all Wards within the Borough.
RECOMMENDATION/S
Capital
1 That Cabinet recommend to Council the approval of additional funding for the schemes referred to in paragraph 3.3.
2 That Cabinet recommend to Council the approval of the revised Capital Programme of £55.889 million for 2019-20. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1Regular monitoring and reporting of the Capital Programme enable decisions to be taken faster which may produce revenue benefits and will improve financial control in Wirral Council.
2.0OTHER OPTIONS CONSIDERED
2.1No other options have been considered.
3.0BACKGROUND INFORMATION
3.1Capital Programme 2019/20 Position by Directorate
Table 1: Wirral Council 2019/20 Full Year Capital Budget and Forecast Position Full Year Budget Forecast Variance £m £m £m %
Adult Care & Health 6.747 2.114 4.633 69% Children 6.255 7.837 (1.582) -25% Business Management 12.915 10.895 2.020 16% Economic Housing Growth 27.712 6.076 21.636 78% Delivery 36.454 25.967 10.487 29%
Organisational Total 90.083 52.889 37.194 41% NB: the full detail of scheme performance is in Appendix 1
3.1.1 Table 1 provides an update on the 2019/20 capital Programme. A number of significant variations have arisen since the programme was agreed in March 2019. These include the inclusion of additional grant funded schemes, variations to spend forecasts and the re- profiling of expenditure into and out of the 2019/20 financial year. Further detail is provided below.
3.1.2 Adult Care and Health Alcohol Treatment (£0.406m increase): Part of an overall grant of £6 million allocated to 23 authorities. The aim is to assist local authorities to prioritise alcohol treatment, invest in equipment and facilities and ensure that treatment expertise is enhanced to better meet the needs of people with alcohol problems. Learning Disability Extra Care Housing (£3.0m decrease): Demand is less than expected due to the private sector finding alternative funding sources to back their developments such as through the supported living regime. Extra Care Housing (£2.11m decrease): Two Extra Care developments which have been awarded Council grant are on currently on site. Barncroft is scheduled for completion in January 2020 and will provide 21 units of Extra Care and the Woodpecker Close site is scheduled for completion in September 2020, providing 78 units. No other developments are planned for this year. 3.1.3 Children Basic Needs (£1.133m increase): An additional grant allocation was notified in May.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring Quarter 1 2020/21That (1) the Cabinet recommends to the Council the approval of additional funding for the schemes referred to in para...
Financial Monitoring Outturn 2019-20That (1) Revenue (a) it be noted that the gross expenditure has been balanced to gross income with the appropriate al...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.