Worcester Play Plan Priority Projects - Update Report
AgreedCommittee1 paper
Place and Economic Development Committee agreed this item on Monday 23 June 2025. Below is the council's own wording, with the papers it was decided on.
That the Committee agree to: 1. note the contents of the report and in particular the outcome of the public consultation and community engagement work undertaken in respect of the 2025/26 Worcester Play Plan Priority Projects; 2. recommend to Policy and Resources Committee the re-allocation of £70,000 of earmarked reserves to progress the installation of a pump track at Perdiswell Park; 3. delegate authority to the Corporate Director - Operations, Homes and Communities in consultation with the Chair and Vice Chair of this Committee to procure all necessary contracts and services to install a pump track at Perdiswell Park; and 4. note the intention to defer the project at Cornmeadow Lane until such time as funding is identified, and that further work will be undertaken to identify an alternative location within the Lower Wick and Pitmaston Ward to meet the gap in play provision as identified within the Worcester Play Plan.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
Report to Place and Economic Development Committee, 9 pages
Recommendation
That the Committee
1.1Note the contents of the report and in particular the outcome of the public consultation and community engagement work undertaken in respect of the 2025/26 Worcester Play Plan Priority Projects;
1.2Recommends to Policy and Resources Committee the re-allocation of £70,000 of earmarked reserves to progress the installation of a pump track at Perdiswell Park;
1.3Delegates authority to the Corporate Director - Operations, Homes and Communities in consultation with the Chair and Vice Chair of this Committee to procure all necessary contracts and services to install a pump track at Perdiswell Park; and
1.4Notes the intention to defer the project at Cornmeadow Lane until such time as funding is identified, and that further work will be undertaken to identify an alternative location within the Lower Wick and Pitmaston Ward to meet the gap in play provision as identified within the Worcester Play Plan.
Background
2.1At the Place and Economic Development Committee meeting in July 2023, Members approved the Worcester City Play Plan. The Plan sets out an ambitious commitment to investment in outdoor spaces for children and young people over a ten-year period.
2.2The Plan has mapped the gaps in provision across the city and identified locations and needs for priority investment. It recognises that local level public consultation and community engagement with users of play facilities, as well as residents and other stakeholders, is a vital component in informing the design and feasibility stage of individual projects.
2.3Progress reports on individual projects have been brought to committee since the inception of the plan and this report updates on the work undertaken of late to further progress the three 2025-26 priority projects as approved by this Committee in July 2024, which included –
• A new destination pump track at Perdiswell Park (Claines) • A refurbished play area at Cornmeadow Lane (Claines)
• A new play area at Weyburn Close (Lower Wick & Pitmaston)
Update on the Delivery of Phase 1 Priority Projects
2.4The first two priority play projects approved by Members of this Committee (July 2023) were Battenhall Park Pump Track (Battenhall / St Peters) and the ‘Play on the Way’ scheme at Cotswold Way (Warndon & Elbury Park).
2.5Battenhall Park Pump Track – Worcester’s first Pump Track opened in November 2024 and has proved to be extremely popular with a wide range of users and abilities enjoying the new facility. Feedback from children and parents has been very positive and where any issues of ASB have been reported the Council’s Youth Intervention team have work closely with the local neighbourhood policing team to address any such incidents. Comments from the local Parish Council have also been very positive.
2.6Cotswold Way ‘Play on the Way’ Project – The appointed contractor is currently on site with the installation of the six play stations starting on the 6th May and due for completion by the middle of June. From a SEND perspective station 1 contains sensory boards, whilst Station 3 has been designed as a ‘Make Space for Girls’ aspect of the project, with tree seating and a raised platform providing an opportunity for users to perform and create social media content. The intention is to link the six play stations by way of thermoplastic play features on the surface of the public footpath that runs through the space, with permission having been granted by the County Council. Despite the storage compound being fire damaged in the first week of installation, the project has progressed smoothly since, and Officers are working with various agencies to ensure this continues to be the case.
Gheluvelt Park Splash Pad
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Place and Economic Development Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.