RESOLVED – ( i ) That the allocation of Welsh Government General Capital Funding in 2018/19 recommended by the Corporate Land and Buildings Strategy Group shown in paragraph 4.19 of report HF/52/14 be approved . (ii) That the allocation of the Heritage and Community Well Being annual capital provision shown in paragraph 4.21 of report HF/52/14 be approved. (iv) That the rolling programme for 2014/15 to 2018/19 as detailed in appendices 2 and 3 of report HF/52/14 be approved. (v) That the capital programme be next reviewed and reported to the Executive Board in February 2015. (vi) That the Semi Annual Treasury Management Activity and Prudential Indicators in Appendix 4 of report HF/52/14 be noted and the revision to the prudential indicator for Interest Rate Exposures be approved. Reasons for decisions ( i ) This report follows an earlier monitoring report in July in compliance with Financial Regulation 2.4 that requires that the Head of Finance monitors and reports to Members on the Capital Programme. (ii) Local Authorities are required under the Local Government Act 2003 to comply with the CIPFA Prudential Code for Capital Finance. The indicators presented in Appendix 4 fulfil the requirements of the Code.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To review the 2014/15 - 2018/19 non Housing Revenue Account Capital Programme and semi annual Treasury Management Activity including Prudential Indicators.
Executive summary
2.1The total capital expenditure in 2014/15 is estimated to be £27,239k. This is £1,034k more than the total approved by the Executive Board at its meeting on 8 July 2014 (HF/37/14). The main reasons for the net increase are:
• A net increase in estimated spend of £1,903k funded from Invest to Save and grants. • Slippage of spend on projects from 2014/15 to 2015/16 of £869k.
2.2The Capital Programme is fully funded by borrowing supported by the Welsh Government, grants and contributions, capital receipts and prudential borrowing.
2.3The Joint Member/Officer Corporate Land and Buildings Strategy Group has recommended projects to be allocated Welsh Government General Capital Funding in 2018/19. 3. RECOMMENDATIONS
3.1The allocation of Welsh Government General Capital Funding in 2018/19 recommended by the Corporate Land and Buildings Strategy Group shown in paragraph 4.19 is approved.
3.2The allocation of the Heritage and Community Well Being annual capital provision shown in paragraph 4.21 is approved.
3.3The rolling programme for 2014/15 to 2018/19 as detailed in appendices 2 and 3 is approved.
3.4The capital programme is next reviewed and reported to the Executive Board in February 2015.
3.5The Semi Annual Treasury Management Activity and Prudential Indicators in Appendix 4 are noted and the revision to the prudential indicator for Interest Rate Exposures is approved.
Reasons for recommendations
(i) This report follows an earlier monitoring report in July in compliance with Financial Regulation 2.4 that requires that the Head of Finance monitors and reports to Members on the Capital Programme.
(ii) Local Authorities are required under the Local Government Act 2003 to comply with the CIPFA Prudential Code for Capital Finance. The indicators presented in Appendix 4 fulfil the requirements of the Code.
4. BACKGROUND INFORMATION
Capital Programme 2014/2015
4.1The Executive Board approved the last revision of the capital programme 2013/14 to 2017/18 on 8 July 2014 (HF/37/14). Appendix 1 provides a summary of expenditure by service, the financing of that expenditure and the variance between the revised programme and the previously approved position.
4.2The revised estimate of expenditure on all capital schemes is £27,239k, a net increase of £1,034k compared with the projected expenditure reported to the Executive Board in July. The significant changes are as follows:-
Slippage of Expenditure to 2015/16
4.3Changes to the phasing of expenditure have resulted in £869k of spending originally planned in 2014/15 to be rescheduled to 2015/16. Projects where significant slippage has occurred are set out below:
• Western Gateway (-£151k). Following a review of the original highways proposals an alternative proposal has been agreed (Executive Board HAED/38/14 5 August 2014) with construction work due to commence early 2015. • Contaminated Land Investigation and Remediation (- £284k). Continuing remediation work associated with former lead smelters at the Coedpoeth and Brymbo Land Remediation Scheme will take place in 2015/16.
• Llay Landfill Site (- £418k). Awaiting a response from Welsh Water regarding the provision of an on-site leachate treatment facility. The delay in providing this facility means that funding for any future work including the possibility of an active gas management system being required will need to be carried forward into 2015/16.
Other Changes
4.4Other variations between the revised capital programme reported in July and the current estimate account for a net increase in planned spending of £1,903k. The main reasons are as follows.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.