Resolved 1. That £232,000 from the Council’s approved overall scheme allocation be committed to the following schemes as recommended by Overview and Scrutiny Committee: – Reference 2 Leys Road Harvington – Reference 3 Plough Road Tibberton – Reference 7 Broad Lane/Main Street Bishampton – Reference 8 Cheltenham Road Little Beckford . 2. That Officers submit a supplementary estimate request if additional funding is required for these schemes. 3. That a feasibility study be undertaken for Evendene Road Hampton as recommended by the Overview and Scrutiny Committee. 1. That Bouts Lane Inkberrow be removed from the Flood Alleviation projects list and action is taken to clarify roles and responsibilities of the various agencies such as the Environment Agency, Highway Authority and to clarify the legal position over possible private contributions, with a report back to a future Board dealing with the issues. 2. That the remaining recommendations from Overview and Scrutiny Committee be supported and approved (paragraphs 2.3 to 2.8 of the report) as set out below:- a. That the Capital Flood Alleviation Programme be extended to include second tranche schemes at Bishampton , Harvington ... view the full minutes text for item 106.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
1.1Members will have already had a copy of the abridged version of the feasibility report to the O&S Committee and are requested to bring it along to the meeting. If members would like another copy of the report they are advised to contact the committee section.
1.2At its meeting on 27th September 2005 the Overview and Scrutiny Committee considered the report on the flood alleviation programme 2nd tranche schemes and resolved to make recommendations to the Executive Board as detailed below.
Recommendations
2.1That the original Priority List shown in Table 1 of the report on 2nd Tranche Capital Flood Alleviation Schemes be re-prioritised and amended as follows:-
2.2That a feasibility study be undertaken for flood alleviation at Evendene Road, Hampton Evesham. 2.3. That the Capital Flood Alleviation Programme be extended to include second tranche schemes at Bishampton, Harvington, Little Beckford and Tibberton as prioritised in 2.1. To be commenced in April 2006 and over a two year period, subject to the completion of the first tranche schemes and sufficient funding being made available through programme options.
2.4That any residual funds from the first tranche schemes and second tranche feasibility studies remaining in the Capital Flood Alleviation Programme be used to carryout a final flood study on the remaining locations shown in table 1. Should insufficient sums be available, a Programme Option be submitted at an appropriate time. That the sum of £200,000 allocated to the 2nd Tranche Schemes be released into the programme in April 2006.
2.5That a copy of the full Flood Study report be sent to the Worcestershire County Council’s Highways Partnership Manager with the request to apply for and provide synchronised or suitably staged funding for those schemes where the County Councils is required to assist in the provision of a flood alleviation scheme at Harvington and Beckford.
2.6That progress on the schemes be reported to the Executive Board on at least a quarterly basis.
2.7That, where schemes are proposed, Parish Councils be requested to make a contribution in line with existing policy and no scheme shall commence until the Parish Council has agreed in writing to make such a contribution which shall become payable at the contract award stage of the scheme.
2.8That, where it is not possible to carryout any viable scheme, homeowners at risk of flooding be offered advice on how to better protect their homes.
3. Implications & Impact
3.1Council Priorities and Community Plan Themes
3.1.1 The Capital Flood Alleviation Programme supports Priority 2 Healthy and Safe Communities with a good quality environment and Priority 3 Reaching out to everyone. In accordance with Council’s Flood Defence Policy Manual.
Financial implications
3.2.1 The Authority’s approved capital expenditure programme contains a total allocation of some £1m to support flooding alleviation works. From this allocation the Council has so far committed some £733k of its own resources in undertaking the works identified in the first tranche of schemes. Parish Council contributions to certain schemes totalling a further £22k have also been received. 3.2.2 A further £35k has now been committed to fund the feasibility studies for tranche 2 as set out in paragraph 1 of this report. As a consequence of the tranche 2 feasibility it is estimated that the schemes identified would cost some £295k to complete.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr...
Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.