Children and Young People's Services and Advisory Panel noted this item on Thursday 7 December 2006. Below is the council's own wording, with the papers it was decided on.
Members considered a report which informed them of the likely out-turn position of the 2006/07 Capital Programme, based on the spend profile and information to the end of September 2006. Updates on, and variations to, the schemes in the programme were outlined in paragraphs 5 to 24 of the report. Those variations had produced a gross capital programme for 2006/07 of £12.879m, of which £11.792m was funded externally, resulting in a net cost to the City of £1.087m. In regard to the York High School Scheme, Members noted the increased costs and the need to identify further capital funding to meet the revised figures. It was recognised that the prudential borrowing mechanism was the only way forward. Members noted that there was no slippage in the capital programme and thanked Officers for their work in achieving that, and in producing the report. Advice of the Advisory Panel: That the Executive Member be advised: (i) To note the capital programme forecast out-turn for 2006/07, as shown in Annex A to the report. (ii) To approve the additions and amendments to the programme, as summarised in Annex A. (iii) To approve the use of prudential borrowing to increase the available funding for the York High School scheme, subject to the approval of the Schools forum and the Executive. (iv) Agree the revised capital programme as shown in Annex A, subject to the approval of the Executive. Decision of the Executive Member:
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Children and Young People's Services and Advisory Panel
Executive Member for Education and Children’s Services and 7 December 2006 Advisory Panel
Report of the Director of Children’s Services and the Director of Resources
CAPITAL PROGRAMME MONITORING 2006/07 - REPORT 2
Summary 1 This report is to:
• inform Members of the likely out-turn position of the 2006/07 Capital Programme based on the spend profile and information to the end of September 2006
• advise Members of changes to existing schemes and reprofiling of expenditure to allow the more effective management and monitoring of the Capital Programme
• inform Members of any new schemes and seek approval for their addition to the Capital Programme.
Background 2 The original capital programme for the financial year 2006/07 was approved at Council on 1 March 2006. A number of amendments to the programme have been approved as part of the 2005/06 out-turn report and also at first monitor. This results in a current approved Education capital programme for 2006/07 which shows gross capital expenditure of £12.879m with £11.792m of other funding which gives a net capital programme cost to the authority of £1.087m.
3 The table below details the approved changes to the 2006/07 capital programme since the original programme was approved in March 2006.
Table 1 - Current Approved Children’s Services Capital Programme 2006/07
Gross Other Net Spend Funding Spend £m £m £m Original Capital Programme 2006/07 13.132 (12.266) 0.866 Slippage and Adjustments from the 2005/06 1.345 (1.157) 0.188 Outturn report Monitor 1 adjustments (1.598) 1.631 0.033 Current Approved Capital Programme 2006/07 12.879 (11.792)) 1.087 Consultation 4 Not applicable.
Options and Analysis
Scheme Progress Reports and Updates 5 The following section provides an update on all the major schemes in the capital programme with a brief summary of progress to date and any issues arising.
Condition Led Projects 6 The funding for this programme was provided via a DfES grant which ended in August 2004. The minor expenditure in 2006/07 represents a retention on the one remaining outstanding scheme.
Devolved Capital 7 This scheme represents the devolved capital which has been allocated to schools in 2006/07, net of any contributions which the schools have agreed towards LEA led schemes.
Fulford Secondary Targeted Capital (Scheme Cost £3.518m) 8 This scheme is now complete with only retention payments outstanding.
Applefields Targeted Capital Fund (Scheme Cost £3.740m) 9 The main work on this scheme is now complete. A small number of issues remain to be resolved, but the remaining budget should be sufficient to deal with these.
Huntington Secondary (Scheme Cost £4.940m) 10 Construction is progressing well and the new buildings are on schedule to be open by Easter 2007.
Local Authority Formula Capital (Scheme Cost £11.760m) 11 This scheme addresses condition and suitability issues at a number of schools in the city. In order to maximise the resources available schools are invited to bid for this funding and are encouraged to contribute their devolved capital to projects.
12 The larger schemes within the Modernisation programme are now all progressing well. The works at Skelton and Scarcroft Primaries, Rufforth Community Hall and Canon Lee are all on schedule to be completed during 2006/07.
13 The majority of schemes which have been approved under the modernisation programme are now approaching completion. These schemes had committed all available modernisation funding to the end of 2006/07. However, apart from some funding which has been allocated to support key major schemes within the capital programme, modernisation funding beyond 2007/08 has not yet been allocated.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children and Young People's Services and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Local Authority Governor AppointmentsAdvice of the Advisory Panel That the Executive Member be advised to appoint or re-appoint the Local Authority Govern...
School Term Dates and Holidays 2010/2011Advice of the Advisory Panel That the Executive Member be advised that the pattern of school terms and holidays for 2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.