Capital Programme Monitoring 2nd Period

Noted Committee 2 papers

Children and Young People's Services and Advisory Panel noted this item on Thursday 7 December 2006. Below is the council's own wording, with the papers it was decided on.

Item37

Resolved

Members considered a report which informed them of the likely out-turn position of the 2006/07 Capital Programme, based on the spend profile and information to the end of September 2006. Updates on, and variations to, the schemes in the programme were outlined in paragraphs 5 to 24 of the report. Those variations had produced a gross capital programme for 2006/07 of £12.879m, of which £11.792m was funded externally, resulting in a net cost to the City of £1.087m. In regard to the York High School Scheme, Members noted the increased costs and the need to identify further capital funding to meet the revised figures. It was recognised that the prudential borrowing mechanism was the only way forward. Members noted that there was no slippage in the capital programme and thanked Officers for their work in achieving that, and in producing the report. Advice of the Advisory Panel: That the Executive Member be advised: (i) To note the capital programme forecast out-turn for 2006/07, as shown in Annex A to the report. (ii) To approve the additions and amendments to the programme, as summarised in Annex A. (iii) To approve the use of prudential borrowing to increase the available funding for the York High School scheme, subject to the approval of the Schools forum and the Executive. (iv) Agree the revised capital programme as shown in Annex A, subject to the approval of the Executive. Decision of the Executive Member:
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Children and Young People's Services and Advisory Panel

Executive Member for Education and Children’s Services and 7 December 2006 Advisory Panel

Report of the Director of Children’s Services and the Director of Resources

CAPITAL PROGRAMME MONITORING 2006/07 - REPORT 2

Summary 1 This report is to:

• inform Members of the likely out-turn position of the 2006/07 Capital Programme based on the spend profile and information to the end of September 2006

• advise Members of changes to existing schemes and reprofiling of expenditure to allow the more effective management and monitoring of the Capital Programme

• inform Members of any new schemes and seek approval for their addition to the Capital Programme.

Background 2 The original capital programme for the financial year 2006/07 was approved at Council on 1 March 2006. A number of amendments to the programme have been approved as part of the 2005/06 out-turn report and also at first monitor. This results in a current approved Education capital programme for 2006/07 which shows gross capital expenditure of £12.879m with £11.792m of other funding which gives a net capital programme cost to the authority of £1.087m.

3 The table below details the approved changes to the 2006/07 capital programme since the original programme was approved in March 2006.

Table 1 - Current Approved Children’s Services Capital Programme 2006/07

Gross Other Net Spend Funding Spend £m £m £m Original Capital Programme 2006/07 13.132 (12.266) 0.866 Slippage and Adjustments from the 2005/06 1.345 (1.157) 0.188 Outturn report Monitor 1 adjustments (1.598) 1.631 0.033 Current Approved Capital Programme 2006/07 12.879 (11.792)) 1.087 Consultation 4 Not applicable.

Options and Analysis

Scheme Progress Reports and Updates 5 The following section provides an update on all the major schemes in the capital programme with a brief summary of progress to date and any issues arising.

Condition Led Projects 6 The funding for this programme was provided via a DfES grant which ended in August 2004. The minor expenditure in 2006/07 represents a retention on the one remaining outstanding scheme.

Devolved Capital 7 This scheme represents the devolved capital which has been allocated to schools in 2006/07, net of any contributions which the schools have agreed towards LEA led schemes.

Fulford Secondary Targeted Capital (Scheme Cost £3.518m) 8 This scheme is now complete with only retention payments outstanding.

Applefields Targeted Capital Fund (Scheme Cost £3.740m) 9 The main work on this scheme is now complete. A small number of issues remain to be resolved, but the remaining budget should be sufficient to deal with these.

Huntington Secondary (Scheme Cost £4.940m) 10 Construction is progressing well and the new buildings are on schedule to be open by Easter 2007.

Local Authority Formula Capital (Scheme Cost £11.760m) 11 This scheme addresses condition and suitability issues at a number of schools in the city. In order to maximise the resources available schools are invited to bid for this funding and are encouraged to contribute their devolved capital to projects.

12 The larger schemes within the Modernisation programme are now all progressing well. The works at Skelton and Scarcroft Primaries, Rufforth Community Hall and Canon Lee are all on schedule to be completed during 2006/07.

13 The majority of schemes which have been approved under the modernisation programme are now approaching completion. These schemes had committed all available modernisation funding to the end of 2006/07. However, apart from some funding which has been allocated to support key major schemes within the capital programme, modernisation funding beyond 2007/08 has not yet been allocated.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Monitoring 2nd PeriodReport 57 KB DownloadRead as text
PDF
Item 8 Annex AAppendix 27 KB Download

At this meeting

Whole meeting

Who was there

8 of 18 attended
CR
Councillor Carol RuncimanCabinet Member, present
CJ
Councillor Ceredig Jamieson-BallCabinet Member, present
KA
Councillor Keith AspdenCommittee Member, apologies
IC
Councillor Ian CuthbertsonCommittee Member, present
VK
Councillor Viv KindCommittee Member, present
KK
Councillor Ken KingCommittee Member, present
AD
Councillor Andy D'AgorneCommittee Member, apologies
FB
Ms Fiona BarclayCo-opted Non-Statutory Member, present
AB
Mrs Ann BurnCo-opted Non-Statutory Member, apologies
JE
Mrs Jona EllisCo-opted Non-Statutory Member, apologies
BR
Ms Barbara ReaganCo-opted Non-Statutory Member, present
MT
Mr Mike ThomasCo-opted Non-Statutory Member, apologies

All 18 on the meeting page

On this subject at York

Search all
  1. Capital Programme Monitoring 2nd PeriodThis decision
  2. Capital Programme Monitor Update 2 Report (4:47pm)Noted
  3. Capital Programme - Monitor 1 2026/27 (4:46pm)Noted
  4. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeApproved
  5. Recommendations of Executive in relation to the Capital Programme - Monitor 3 2025/26Approved
  6. Capital Programme - Monitor 3 2025/26Approved

More from York Children and Young People's Services and Advisory Panel

All decisions
MeetingDecisionOutcome
12 Mar 2009 MinutesThat the minutes of the last meeting of the Executive Member for Children and Young People’s Services and Advisory Pa... Approved Open
12 Mar 2009 Local Authority Governor AppointmentsAdvice of the Advisory Panel That the Executive Member be advised to appoint or re-appoint the Local Authority Govern... Decided Open
12 Mar 2009 Admission arrangements and admission limits for primary and secondary schools in York from September 2010Advice of the Advisory Panel That the Executive Member be advised (i) That the City of York co-ordinated schemes and ... Approved Open
12 Mar 2009 School Term Dates and Holidays 2010/2011Advice of the Advisory Panel That the Executive Member be advised that the pattern of school terms and holidays for 2... Approved Open
12 Mar 2009 Young People's Services: Service Asset Management PlanThat this item be deferred. REASONS: (i) The plan was to be updated in the light of current discussions around the My... Deferred Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies