Children and Young People's Services and Advisory Panel noted this item on Thursday 6 September 2007. Below is the council's own wording, with the papers it was decided on.
Advice of the Advisory Panel That the Executive Member be advised: · Note the capital programme forecast outturn for 2007/08 as shown in Annex A of the report · Approve the additions and amendments to the capital programme reported and summarised in Annex A of the report · Approve the scheme reprofiling and slippage reported and summarised in Annex A of the report · Agree the revised capital programme as shown at Annex A of the report, subject to the approval of the Executive Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Children and Young People's Services and Advisory Panel
Background
2 The original capital programme for the financial year 2007/08 was approved at Council on 21 February 2007. Since then, a number of amendments to the programme have been approved as part of the 2006/07 out-turn report, and at the Urgency meeting of 3 August 2007. This results in a current approved Children’s Services capital programme for 2007/08 which shows gross capital expenditure of £19.651m with £18.521m of other funding which gives a net capital programme cost to the authority of £1.130m.
3 The table below details the approved changes to the 2007/08 capital programme since the original programme was approved in February 2007.
Table 1- Current Approved Children’s Services Capital Programme 2007/08
Gross Other Net Spend Funding Spend £m £m £m Original Capital Programme 2007/08 16.485 16.225 0.260 Slippage and Adjustments from the 2006/07 2.368 2.052 0.316 Outturn report Amendment at Urgency Meeting 0.798 0.244 0.554 Current Approved Capital Programme 2007/08 19.651 18.521 1.130 Consultation
4 Not applicable.
Options and Analysis Scheme Progress Reports and Updates
5 The following section provides an update on all the major schemes in the capital programme with a brief summary of progress to date and any issues arising.
Devolved Capital 6 This scheme represents the devolved capital which has been allocated to schools in 2007/08, net of any contributions which the schools have agreed towards LA led schemes.
Fulford Secondary Targeted Capital (Scheme Cost £3.518m) 7 This scheme is now complete with only retention payments outstanding. The final payment for Phase 2 has just been agreed and results in a saving of £10k on the remaining budget. The final payment for Phase 1 is still being finalised but is expected to be within the remaining budget.
Huntington Secondary (Scheme Cost £5.295m) 8 The major scheme for the provision of new Teaching and Performing Arts blocks is complete with the new facilities in full use. However, there is a projected overspend of £420k on the overall scheme. This is mainly due (£300k) to design problems causing extensions of time and redesign of the structural elements of the scheme. Property Services are currently negotiating a final account and are pursuing outstanding claims which, together, should result in a reduction in the projected overspend.
Integrated Children’s Centres (Overall Scheme Cost (£4.728m) 9 Following the report to the Urgency meeting of the 3rd August 2007 the Capital programme has been amended to show the decisions made at that meeting. These amendments increase the overall capital programme due to the formal approval of the use of the Heworth Family Centre capital receipt of £275k, approval of £400k funding from the modernisation programme, and the addition of a further £279k of corporate capital resources.
10 Work on the New Earswick Children’s Centre is progressing well and the project is expected to be complete in October 2007.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children and Young People's Services and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Local Authority Governor AppointmentsAdvice of the Advisory Panel That the Executive Member be advised to appoint or re-appoint the Local Authority Govern...
School Term Dates and Holidays 2010/2011Advice of the Advisory Panel That the Executive Member be advised that the pattern of school terms and holidays for 2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.