Children and Young People's Services and Advisory Panel noted this item on Thursday 6 December 2007. Below is the council's own wording, with the papers it was decided on.

Item44

Resolved

Advice of the Advisory Panel That the Executive Member be advised to: · Note the capital programme forecast outturn for 2007/08 as shown in Annex A to the report. · Approve the additions and amendments to the capital programme reported above and summarised in Annex A · Approve the scheme reprofiling and slippage reported and slippage reported above and summarised in Annex A to the report. · Agree the revised capital programme as shown at Annex A to the report, subject to the approval of the Executive. Decision of the Executive Member
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Children and Young People's Services and Advisory Panel

Background

2 The original capital programme for the financial year 2007/08 was approved at Council on 21 February 2007. Since then, a number of amendments to the programme have been approved as part of the 2006/07 out-turn report, at the Urgency meeting of 3rd July 2007 and following the first monitoring report. This results in a current approved Children’s Services capital programme for 2007/08 which shows gross capital expenditure of £19.460m with £18.330m of other funding which gives a net capital programme cost to the authority of £1.130m.

3 The table below details the approved changes to the 2007/08 capital programme since the original programme was approved in February 2007.

Table 1- Current Approved Children’s Services Capital Programme 2007/08

Gross Other Net Spend Funding Spend £m £m £m Original Capital Programme 2007/08 16.485 16.225 0.260 Slippage and Adjustments from the 2006/07 2.368 2.052 0.316 Outturn report Amendment at Urgency Meeting 0.798 0.244 0.554 Monitor 1 Adjustments 0.488 0.109 0.379 Current Approved Capital Programme 2007/08 20.439 18.630 1.509 Consultation

4 Not applicable.

Options and Analysis Scheme Progress Reports and Updates

5 The following section provides an update on all the major schemes in the capital programme with a brief summary of progress to date and any issues arising.

Devolved Capital 6 This scheme represents the devolved capital which has been allocated to schools in 2007/08, net of any contributions which the schools have agreed towards LEA led schemes.

Fulford Secondary Targeted Capital (Scheme Cost £3.518m) 7 This scheme is now complete with only the retention payment on Phase 1 outstanding. This is still being finalised but is expected to be within the remaining budget.

Huntington Secondary (Scheme Cost £5.674m) 8 The major scheme for the provision of new Teaching and Performing Arts blocks is complete with the new facilities in full use. As reported previously to EMAP, there has been an overspend on the overall scheme. Property Services are currently negotiating a final account and are pursuing outstanding claims which may result in a variation to the previously reported overspend, which has been funded by corporate resources. Further detail will be reported when negotiations are concluded.

Integrated Children’s Centres (Overall Scheme Cost (£4.728m) 9 When tenders for the remaining five Children’s Centres were returned during the summer, it became apparent that funding for this important programme for re- shaping key statutory services for children from birth to five years was insufficient to meet the City’s aspirations for the Centres. The Urgency meeting of 3rd August 2007 therefore agreed to the allocation of additional funding, but this meant that there was a delay in awarding the tenders so that the summer holiday period for starting work was missed. This has had a knock-on effect on both programmes and budgets, although Project Managers are working hard to contain costs within the overall scheme budgets.

10 The scheme at Carr is currently on site with a provisional completion date of late March 2008.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Childrens 2007-08 Monitor 2Appendix A 29 KB Download
PDF
Capital Programme Monitoring Report 2Report 57 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 16 attended
CR
Councillor Carol RuncimanCabinet Member, present
KA
Councillor Keith AspdenCabinet Member, present
JA
Councillor James AlexanderChair, present
JB
Councillor Jenny BrooksVice-Chair, present
PF
Councillor Paul FirthCommittee Member, present
JG
Councillor Julie GunnellCommittee Member, present
DM
Councillor Dave MerrettCommittee Member, present
AD
Councillor Andy D'AgorneCommittee Member, apologies
FB
Ms Fiona BarclayCo-opted Non-Statutory Member, present
AB
Mrs Ann BurnCo-opted Non-Statutory Member, apologies
JE
Mrs Jona EllisCo-opted Non-Statutory Member, present
BR
Ms Barbara ReaganCo-opted Non-Statutory Member, apologies

All 16 on the meeting page

On this subject at York

Search all
  1. Capital Programme Monitoring Report 2This decision
  2. Capital Programme Monitor Update 2 Report (4:47pm)Noted
  3. Capital Programme - Monitor 1 2026/27 (4:46pm)Noted
  4. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeApproved
  5. Recommendations of Executive in relation to the Capital Programme - Monitor 3 2025/26Approved
  6. Capital Programme - Monitor 3 2025/26Approved

More from York Children and Young People's Services and Advisory Panel

All decisions
MeetingDecisionOutcome
12 Mar 2009 MinutesThat the minutes of the last meeting of the Executive Member for Children and Young People’s Services and Advisory Pa... Approved Open
12 Mar 2009 Local Authority Governor AppointmentsAdvice of the Advisory Panel That the Executive Member be advised to appoint or re-appoint the Local Authority Govern... Decided Open
12 Mar 2009 Admission arrangements and admission limits for primary and secondary schools in York from September 2010Advice of the Advisory Panel That the Executive Member be advised (i) That the City of York co-ordinated schemes and ... Approved Open
12 Mar 2009 School Term Dates and Holidays 2010/2011Advice of the Advisory Panel That the Executive Member be advised that the pattern of school terms and holidays for 2... Approved Open
12 Mar 2009 Young People's Services: Service Asset Management PlanThat this item be deferred. REASONS: (i) The plan was to be updated in the light of current discussions around the My... Deferred Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies