Children and Young People's Services and Advisory Panel noted this item on Thursday 6 December 2007. Below is the council's own wording, with the papers it was decided on.
Advice of the Advisory Panel That the Executive Member be advised to: · Note the capital programme forecast outturn for 2007/08 as shown in Annex A to the report. · Approve the additions and amendments to the capital programme reported above and summarised in Annex A · Approve the scheme reprofiling and slippage reported and slippage reported above and summarised in Annex A to the report. · Agree the revised capital programme as shown at Annex A to the report, subject to the approval of the Executive. Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Children and Young People's Services and Advisory Panel
Background
2 The original capital programme for the financial year 2007/08 was approved at Council on 21 February 2007. Since then, a number of amendments to the programme have been approved as part of the 2006/07 out-turn report, at the Urgency meeting of 3rd July 2007 and following the first monitoring report. This results in a current approved Children’s Services capital programme for 2007/08 which shows gross capital expenditure of £19.460m with £18.330m of other funding which gives a net capital programme cost to the authority of £1.130m.
3 The table below details the approved changes to the 2007/08 capital programme since the original programme was approved in February 2007.
Table 1- Current Approved Children’s Services Capital Programme 2007/08
Gross Other Net Spend Funding Spend £m £m £m Original Capital Programme 2007/08 16.485 16.225 0.260 Slippage and Adjustments from the 2006/07 2.368 2.052 0.316 Outturn report Amendment at Urgency Meeting 0.798 0.244 0.554 Monitor 1 Adjustments 0.488 0.109 0.379 Current Approved Capital Programme 2007/08 20.439 18.630 1.509 Consultation
4 Not applicable.
Options and Analysis Scheme Progress Reports and Updates
5 The following section provides an update on all the major schemes in the capital programme with a brief summary of progress to date and any issues arising.
Devolved Capital 6 This scheme represents the devolved capital which has been allocated to schools in 2007/08, net of any contributions which the schools have agreed towards LEA led schemes.
Fulford Secondary Targeted Capital (Scheme Cost £3.518m) 7 This scheme is now complete with only the retention payment on Phase 1 outstanding. This is still being finalised but is expected to be within the remaining budget.
Huntington Secondary (Scheme Cost £5.674m) 8 The major scheme for the provision of new Teaching and Performing Arts blocks is complete with the new facilities in full use. As reported previously to EMAP, there has been an overspend on the overall scheme. Property Services are currently negotiating a final account and are pursuing outstanding claims which may result in a variation to the previously reported overspend, which has been funded by corporate resources. Further detail will be reported when negotiations are concluded.
Integrated Children’s Centres (Overall Scheme Cost (£4.728m) 9 When tenders for the remaining five Children’s Centres were returned during the summer, it became apparent that funding for this important programme for re- shaping key statutory services for children from birth to five years was insufficient to meet the City’s aspirations for the Centres. The Urgency meeting of 3rd August 2007 therefore agreed to the allocation of additional funding, but this meant that there was a delay in awarding the tenders so that the summer holiday period for starting work was missed. This has had a knock-on effect on both programmes and budgets, although Project Managers are working hard to contain costs within the overall scheme budgets.
10 The scheme at Carr is currently on site with a provisional completion date of late March 2008.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children and Young People's Services and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Local Authority Governor AppointmentsAdvice of the Advisory Panel That the Executive Member be advised to appoint or re-appoint the Local Authority Govern...
School Term Dates and Holidays 2010/2011Advice of the Advisory Panel That the Executive Member be advised that the pattern of school terms and holidays for 2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.